You are on page 1of 1

Manfacturer Client: NFC (Hyderabad)

M/s Bhavi Plast Pvt Ltd Bar Chart for Project Execution Manfacturer: M/s Bhavi Plast Pvt Ltd
Unit No. 1,2,3,4, Building No. 37,
Indian Commercial Complex, Dapode, Bhiwandi Tender No : 584
TEL: 022 25366002/003/004
Sr.No. DESCRIPTION Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21

1 Receipt of PO
2 Acknowledgment & Acceptance of PO
3 Final Design Simulation & sizing
Submission of GA drawing and Layout
4 drawings for Approval
5 Approval/Comments by NFC on drawings
6 Submission of revised Drawing.
7 Final Approval by NFC
8 Ordering out of Raw Material
9 Receipt of Raw Material
10 Fabrication of Spray Tower 2 Nos
11 Ordering Out of Recirculation Pumps
12 Receipt of Recirculation Pumps
Fabrication of Plant ducting &Recirculation
13 piping
Ordering Out of Other bought outs(MCC
panel,Cables, Cable tray Push button&
14 hardware
Receipt of bought outs(MCC panel,Cables,
15 Cable tray Push button& hardware
16 Inspection Call
17 Inspection of Equipments and Bought outs
18 Dipatch Clearance & Dispatch
19 Receipt of Material at site
20 Mobilosation of Installation team
21 Gate entry formality& safety training
Dismantling of Existing Ducting and
22 equipments
23 Installation & Commissioning