Pekerjaan Area Cucian

No. Uraian Keterangan Satuan Volume Harga Satuan


1 Galian Buang Desposal m3 16.20 240,000.00
2 Pemadatan tanah dengan alat m2 24.00 17,000.00
3 Straus + Beton D=40cm, T=5m Unit 6.00 2,600,000.00
4 Pile Cap 30x70x70 m3 0.88 2,100,000.00
5 Sloop 30x40 m 3
3.24 1,600,000.00
6 Lantai Beton T=30cm m3 7.20 1,210,000.00
7 Dinding T=20cm m 3
6.60 1,210,000.00
8 Wiremesh m8 m2 114.00 18,000.00
9 Pipa output 3" AW m 1.50 80,000.00
Total

Pekerjaan Area Crusher


No. Uraian Keterangan Satuan Volume Harga Satuan
1 Straus + Beton D=40cm, T=5m Unit 6.00 2,600,000.00
2 Pile Cap 30x70x70 m3 0.88 2,100,000.00
3 Sloop 30x40x21 m3 2.52 1,600,000.00
4 Lantai Beton T=60cm m 3
9.90 1,210,000.00
5 Wiremesh m8 m2 33.00 18,000.00
Total
Total
3,888,000.00
408,000.00
15,600,000.00
1,852,200.00
5,184,000.00
8,712,000.00
7,986,000.00
2,052,000.00
120,000.00
45,802,200.00

Total
15,600,000.00
1,852,200.00
4,032,000.00
11,979,000.00
594,000.00
34,057,200.00