Professional Documents
Culture Documents
1
Case Study: Energy
Efficiency Best Practice
Pumping Systems
Murray Goulburn
Co-operative Koroit Plant
Best Practice Guide
Pumping Systems
Introduction
This approach can be readily replicated in many production
Murray Goulburn Co-operative was formed in 1950 and has
plants utilising similar multiple process pumps. In many of these
grown to become the largest processor of milk in Australia
plants, multiple pump systems operate in series at suboptimum
and the nation’s largest exporter of processed food. With eight
operating conditions. Whilst every application will be different,
plants located throughout Victoria, Murray Goulburn processes
there is real potential to undertake similar process analysis to
over 35% of the nation’s milk supply into quality products
improve individual plant operation.
which are sold on both domestic and export markets.
The processes used to manufacture market, powdered Key outcomes and benefits
milk and cheese products are relatively energy intensive,
so the company has always strived to maximise its energy The key outcomes and benefits of an upgrade to the system
performance. This has typically included selection of the are as follows:
most efficient process plant, steam, refrigeration and • reduced pump system running costs by 42% for separator
compressed air systems. As a part of the overall plant energy bank no.1
improvement programs, the engineering group implemented • reduced carbon emissions through lower power consumption
a pump system upgrade to improve the energy performance • improved process control
of identified systems in the plant. The program involved • reduced piping system component wear by reducing
detailed analysis of existing milk separation pump systems to friction losses through the system.
determine if pump flows matched the required system duties.
At the Koroit processing facility, Murray Goulburn recognised
Return on investment
that these pump systems were operating at below optimum The total cost of replacement equipment was $24,878
and were inefficient and costly to operate. So, as a part of (pumps, modifications and controls).
the company’s ongoing plant upgrade, they undertook a The savings achieved included:
comprehensive program to improve on this. Subsequent to Annual energy savings $6029
the review, they have installed correctly sized pumps on this Annual GHG^ reduction $1840*
system, an initiative which has exceeded expectations. Total savings $7869
^ Greenhouse gas
The project * Carbon savings based on Scope 2 and nominal value of $20/tonne carbon equivalence
2
Best Practice Guide
Pumping Systems
3
Best Practice Guide
Pumping Systems
•A
reconfiguration of the inlet pipe work to the separator After the three new pumps were installed on this bank, the
supply pumps also improved the balance between both power consumption for these new units was measured and
of these pumps, reducing the need for throttling of the then compared with the power absorbed by the original pumps.
butterfly valves. The before and after comparison is shown in the following table.
• Pump 3 easily met the duty required. Due to the positive Actual power
feed from the system, this pump was being controlled via a used (kW)
variable-speed drive (VSD), with the operators throttling the
Pump Original New pump Original New Annual
inlet valves to obtain the required flow and pressure to the
no. installed installed pumps power
separator. The pump motor was only using around 3.0kW, yet
(kW) (kW) savings
the unit had an 11kW motor fitted. However, it was decided
(kWh)
that, due to the VSD control, changing to a smaller (7.5kW)
motor would not result in significant power improvements. 2 22 11 20.8 10 51,360
4 15 11 7.5 5.7 8640
• Pump 4 is also VSD controlled to meet the duty required.
5 11 7.5 9.0 5.8 15,360
This pump was generating around 5.2 bar at 100%, was
fitted with a 15kW motor and was consuming around 7.5kW Total annual power savings 75,360
at the duty point. The operators were throttling the discharge A similar test procedure was undertaken for separator bank no.
from the system to get the balance in flow to the separator. 2. These tests indicated that the pumps and drives for separator
It was decided that a reduction in the size of this unit would bank no. 2 were correctly sized for the required system duty, so
give better control and allow a smaller motor to be installed. no changes were recommended.
• Pump 5 was oversized compared to a pump providing “This project has demonstrated that real power savings can be
similar duty on the other separator bank. This pump was made by carefully analysing existing pump and process systems,
resized to allow it to perform closer to the required duty and then improving their efficiency by matching the various pumps
and reduce the power required. to their system duty requirements. Projects of this type help us to
think outside the square and challenge the way we do things. Murray
• Pump 6 was positively fed from the separator discharge Goulburn intends to continue to refine its pumping processes to
and met the duty required, so no changes were made for improve energy efficiency and reduce its carbon footprint..”
this pump. Quote from Leon Ryan,
Corporate Energy Manager at Murray Goulburn
Modifications made
The following are the changes that were made to separator Related references
Energy Efficiency and Renewable Energy (EERE), US Department of Energy,
system no. 1, with the view to rationalising the power required. May 2006, Boise Paper: Process Pumping System Optimization Saves
Separator bank no.1 Energy and Improves Production. www.eere.energy.gov/industry
Pump Original Motor Modified pump Motor Energy Efficiency and Renewable Energy (EERE), US Department of Energy,
December 2008, Improve the Energy Efficiency of Pump Systems. www.
no. pump frame selection frame eere.energy.gov
1 W+30/80 Hydraulic Institute, May 2006, Improving Pumping System Performance:
132 Remain as installed 132 A Sourcebook for Industry.
145 7.5kW
NSW Agriculture, Agfact E5.11, November 2003, How efficient is your pump?
2 LKH40/235 Replace with LKH
180 160
22kW 45/170 11kW
3 W 55/60
160 Remain as installed 160
180 11kW
4 LKH 30/200 Replace with LKH
160 160
15kW 25/185 11kW
5 ALC 3/155 Replace with LKH
160 132
11kW 45/150 7.5kW
6 W+30/80
132 Remain as installed 132
120 5.5kW
Best Practice Guide
Pumping Systems
Acknowledgements
Sustainability Victoria would like to acknowledge Arup
for preparing this report and IBM and EDS Australia for
their review of this guide.