HARGA BAHAN dan UPAH KERJA

A. LOKASI PROYEK DI BIME

BERAT HARGA BIAYA BAHAN BIAYA ANGKUT BIAYA ANGKUT BIAYA ANGKUT HARGA S/D LOKASI JASA HARGA
NO NAMA BAHAN UKURAN SATUAN
BAHAN (Kg) JAYAPURA /KG (Rp) JYPR - SNTI (Rp) PESAWAT (Rp) BNDRA - Oksibil (Rp) DAN RESIKO TOTAL
1 2 3 4 5 7 8 9 10 11 12

I BAHAN KAYU

Kayu Kelas I :
1 Balok 10/10 kls 1 10 x 10 M³ 3,000,000.00
2 Balok 5/10 kls 1 5 x 10 M³ 2,500,000.00
3 Balok 5/5 kls 1 5x5 M³ 2,500,000.00
4 Papan 2/20 2 x 20 M³ 2,500,000.00
Kayu Kelas II :
1 Balok 10/10 kls 2 10 x 10 M³ 2,000,000.00
2 Balok 5/10 kls 2 5 x 10 M³ 1,800,000.00
3 Balok 5/5 kls 2 5x5 M³ 1,800,000.00
4 Papan 2,5/20 2 x 20 M³ 1,800,000.00
5 Teak Wood 122 x 244 Lbr 5.20 0.00 0.00 0.00 0.00
6 Melamin 1 Lbr 5.20 60,000.00 0.00 60,000.00 9,000.00 69,000.00
7 List Siku Profil 1 Btg 3.00 37,500.00 0.00 37,500.00 5,625.00 43,125.00
8 List Rata Profil 1 Btg 2.00 6,000.00 0.00 6,000.00 900.00 6,900.00
9 Tripleks 1.22x2.44 Lbr 5.20 37,000.00 0.00 37,000.00 5,550.00 42,550.00

II BAHAN GALIAN
1 Kerikil / Sirtu Beton 1 M³ 500,000.00
2 Pasir Pasang 1 M³ 500,000.00
3 Pasir Urug 1 M³ 500,000.00
4 Pasir Beton 1 M³ 500,000.00
5 Karang Kasar / Timbunan/tanah timbunan 1 M³ 350,000.00
6 Batu Kali / Gunung 1 M³ 400,000.00
7 Batu Tela 1 Bh 8,700.00

III BAHAN PAKU


1 Paku Seng 1 Kg 1.00 15,000.00 0.00 15,000.00 2,250.00 17,250.00
2 Paku Tripleks 1 Kg 1.00 12,000.00 0.00 12,000.00 1,800.00 13,800.00
3 Paku Campuran 1 Kg 1.00 10,000.00 0.00 10,000.00 1,500.00 11,500.00
4 Paku Genteng Zincalume 1 Kg 1.00 80,000.00 0.00 80,000.00 12,000.00 92,000.00
BERAT HARGA TIMBANGAN BIAYA ANGKUT BIAYA ANGKUT BIAYA ANGKUT HARGA S/D LOKASI JASA HARGA TOTAL
NO NAMA BAHAN UKURAN SATUAN
BAHAN (Kg) JAYAPURA /KG (Rp) JYPR - SNTI (Rp) PESAWAT (Rp) BNDRA - Oksibil (Rp) DAN RESIKO (Rp)
1 2 3 4 5 7 8 9 10 11 12 13

IV BAHAN PASANGAN
1 Semen PC 1 Zak 50.00 57,000.00 0.00 57,000.00 8,550.00 65,550.00
2 Semen Putih 1 Kg 1.00 4,000.00 0.00 4,000.00 600.00 4,600.00
3 semen warna 1 Kg 1.00 4,000.00 0.00 4,000.00 600.00 4,600.00
4 Keramik 20/20 20 x 20 Krt 15.00 53,000.00 0.00 53,000.00 7,950.00 60,950.00
5 Keramik 30/30 30 x 30 Krt 20.00 51,000.00 0.00 51,000.00 7,650.00 58,650.00
6 Ubin Plin 10 x 20 Krt 13.00 46,000.00 0.00 46,000.00 6,900.00 52,900.00
7 Keramik plin 20/20 20 x 20 Krt 15.00 43,000.00 0.00 43,000.00 6,450.00 49,450.00

V BAHAN BESI
1 Besi beton 6 mm 6 mm Btg 2.66 20,000.00 0.00 20,000.00 3,000.00 23,000.00
Besi beton 6,5 mm 6,5 mm Btg 3.20 24,000.00 0.00 24,000.00 3,600.00 27,600.00
Besi beton 8 mm 8 mm Btg 4.74 26,000.00 0.00 26,000.00 3,900.00 29,900.00
Besi beton 9 mm 9 mm Btg 6.00 32,000.00 0.00 32,000.00 4,800.00 36,800.00
Besi beton 10 mm 10 mm Btg 7.40 37,000.00 0.00 37,000.00 5,550.00 42,550.00
Besi beton 12 mm 12 mm Btg 10.66 48,000.00 0.00 48,000.00 7,200.00 55,200.00
Besi beton 13 mm 13 mm Btg 12.48 65,000.00 0.00 65,000.00 9,750.00 74,750.00
Besi beton 14 mm 14 mm Btg 14.50 89,000.00 0.00 89,000.00 13,350.00 102,350.00
Besi beton 16 mm 16 mm Btg 18.96 105,000.00 0.00 105,000.00 15,750.00 120,750.00
Besi beton 18 mm 18 mm Btg 26.76 135,000.00 0.00 135,000.00 20,250.00 155,250.00
Besi beton 22 mm 22 mm Btg 35.76 176,000.00 0.00 176,000.00 26,400.00 202,400.00
Besi beton 23 mm 23 mm Btg 36.13 195,000.00 0.00 195,000.00 29,250.00 224,250.00
Besi beton 25 mm 25 mm Btg 46.20 210,000.00 0.00 210,000.00 31,500.00 241,500.00
VI BAHAN PIPA
1 Pipa PVC 1/2" Btg 0.35 19,000.00 0.00 19,000.00 2,850.00 21,850.00
Pipa PVC 3/4" Btg 0.40 22,000.00 0.00 22,000.00 3,300.00 25,300.00
Pipa PVC 1" Btg 0.55 28,000.00 0.00 28,000.00 4,200.00 32,200.00
Pipa PVC 11/4" Btg 0.70 36,000.00 0.00 36,000.00 5,400.00 41,400.00
Pipa PVC 11/2" Btg 0.85 59,000.00 0.00 59,000.00 8,850.00 67,850.00
Pipa PVC 2" Btg 1.20 76,000.00 0.00 76,000.00 11,400.00 87,400.00
Pipa PVC 3" Btg 3.00 89,000.00 0.00 89,000.00 13,350.00 102,350.00
Pipa PVC 4" Btg 4.00 98,000.00 0.00 98,000.00 14,700.00 112,700.00
Pipa PVC 5" Btg 6.20 105,000.00 0.00 105,000.00 15,750.00 120,750.00
Pipa PVC 6" Btg 7.50 135,000.00 0.00 135,000.00 20,250.00 155,250.00
2 Pipa (galvanis) GIP 1/2" Btg 1.22 75,000.00 0.00 75,000.00 11,250.00 86,250.00
Pipa (galvanis) GIP 3/4" Btg 1.58 96,000.00 0.00 96,000.00 14,400.00 110,400.00
Pipa (galvanis) GIP 1" Btg 2.44 110,000.00 0.00 110,000.00 16,500.00 126,500.00
Pipa (galvanis) GIP 11/4" Btg 3.14 134,000.00 0.00 134,000.00 20,100.00 154,100.00
Pipa (galvanis) GIP 11/2" Btg 3.61 156,000.00 0.00 156,000.00 23,400.00 179,400.00
Pipa (galvanis) GIP 2" Btg 5.10 176,000.00 0.00 176,000.00 26,400.00 202,400.00
Pipa (galvanis) GIP 3" Btg 8.47 189,000.00 0.00 189,000.00 28,350.00 217,350.00
Pipa (galvanis) GIP 4" Btg 12.10 198,000.00 0.00 198,000.00 29,700.00 227,700.00
Pipa (galvanis) GIP 5" Btg 16.20 210,000.00 0.00 210,000.00 31,500.00 241,500.00
Pipa (galvanis) GIP 6" Btg 19.20 245,000.00 0.00 245,000.00 36,750.00 281,750.00
Pipa (galvanis) GIP
BERAT HARGA BIAYA BAHAN BIAYA ANGKUT BIAYA ANGKUT BIAYA ANGKUT HARGA S/D LOKASI JASA HARGA TOTAL
NO NAMA BAHAN UKURAN SATUAN
BAHAN (Kg) JAYAPURA /KG (Rp) JYPR - SNTI (Rp) PESAWAT (Rp) BNDRA - Oksaibil (Rp) DAN RESIKO (Rp)
1 2 3 4 5 6 7 9 11

VII BAHAN SANITAIR


1 Klosed Jongkok Porselin 1 Bh 10.00 175,000.00 0.00 175,000.00 26,250.00 201,250.00
2 Klosed Jongkok KIA 1 Bh 7.50 195,000.00 0.00 195,000.00 29,250.00 224,250.00
3 Klosed Duduk Keramik / KIA 1 Bh 11.00 225,000.00 0.00 225,000.00 33,750.00 258,750.00
4 Bak Viber 1 Bh 8.50 350,000.00 0.00 350,000.00 52,500.00 402,500.00
VIII BAHAN KAWAT BETON BAJA
1 Kawat Bronjong ukuran 4 mm 1 Bh 2.00 0.00 0.00 0.00 0.00
2 Kawat ikat 1 Bh 1.00 15,000.00 0.00 15,000.00 2,250.00 17,250.00
3 Kawat Harmonika 1 Bh 12.00 0.00 0.00 0.00 0.00
IX BAHAN PENGUNCI / PENGGANTUNG
Kunci Tanam :
1 Union 2 Slaag Bh 1.50 55,000.00 0.00 55,000.00 8,250.00 63,250.00
2 Kuda Terbang 2 Slaag Bh 1.50 75,000.00 0.00 75,000.00 11,250.00 86,250.00
3 Royal 2 Slaag Bh 1.60 86,000.00 0.00 86,000.00 12,900.00 98,900.00
4 Engsel - engsel :
5 Engsel Pintu 1 Pas 0.40 9,000.00 0.00 9,000.00 1,350.00 10,350.00
6 Engsel Jendela 1 Pas 0.25 7,500.00 0.00 7,500.00 1,125.00 8,625.00
3 Hak Angin Biasa 1 Pas 0.03 12,000.00 0.00 12,000.00 1,800.00 13,800.00
4 Hak Angin Lipat / Putar 1 Pas 0.06 19,200.00 0.00 19,200.00 2,880.00 22,080.00
5 Grendel Pintu 1 Bh 0.50 4,000.00 0.00 4,000.00 600.00 4,600.00
6 Grendel Jendela 1 Bh 0.40 4,000.00 0.00 4,000.00 600.00 4,600.00
7 Kaca bening t. 5 mm 2438x2134 Lbr 12.00 180,000.00 0.00 180,000.00 27,000.00 207,000.00
8 Kunci Gembok 1 Bh 0.10 6,000.00 0.00 6,000.00 900.00 6,900.00
X BAHAN ATAP
1 Atap Seng Gelombang 0.3 1 Lbr 4.00 48,000.00 0.00 48,000.00 7,200.00 55,200.00
2 Atap Seng Gelombang 0.20 1 Lbr 2.00 28,000.00 0.00 28,000.00 4,200.00 32,200.00
3 Seng Plat 0.30 1 Lbr 5.00 25,000.00 0.00 25,000.00 3,750.00 28,750.00
4 Seng Plat 0.20 1 M' 3.00 14,000.00 0.00 14,000.00 2,100.00 16,100.00
5 Genteng Zincalume 1 Lbr 2.50 49,000.00 0.00 49,000.00 7,350.00 56,350.00
6 Nok Genteng Zincalume 1 Lbr 1.50 31,000.00 0.00 31,000.00 4,650.00 35,650.00
XI BAHAN CAT
1 Cat Tembok 5 Kg 5.00 4,500.00 0.00 4,500.00 675.00 5,175.00
2 Cat Tembok 20 Kg 20.00 0.00 0.00 0.00 0.00
3 Cat Kilat Kayu 1 Kg 1.00 24,000.00 0.00 24,000.00 3,600.00 27,600.00
4 Cat Kayu dasar 1 Kg 1.00 0.00 0.00 0.00 0.00
5 Cat Meni 1 Kg 1.00 21,000.00 0.00 21,000.00 3,150.00 24,150.00
6 Cat Besi 1 Kg 1.00 0.00 0.00 0.00 0.00
7 Plamur Tembok 5 Kg 5.00 8,000.00 0.00 8,000.00 1,200.00 9,200.00
BERAT HARGA BIAYA BAHAN BIAYA ANGKUT BIAYA ANGKUT BIAYA ANGKUT HARGA S/D LOKASI JASA HARGA TOTAL
NO NAMA BAHAN UKURAN SATUAN
BAHAN (Kg) JAYAPURA /KG (Rp) JYPR - SNTI (Rp) PESAWAT (Rp) BNDRA - Oksibil (Rp) DAN RESIKO (Rp)
1 2 3 4 5 6 7 9 11

7 Plamur Kayu 1 Klg 1.00 8,000.00 0.00 8,000.00 1,200.00 9,200.00


8 Dempul Besi 1 Klg 1.00 7,000.00 0.00 7,000.00 1,050.00 8,050.00
9 Dempul Kayu 1 Klg 1.00 6,500.00 0.00 6,500.00 975.00 7,475.00
10 Amplas Kayu 1 Lbr 0.05 2,500.00 0.00 2,500.00 375.00 2,875.00
11 Amplas Besi 1 Lbr 0.05 2,500.00 0.00 2,500.00 375.00 2,875.00
12 Residu 1 Ltr 1.20 13,000.00 0.00 13,000.00 1,950.00 14,950.00
13 Meni Kayu 1 Ltr 0.70 21,000.00 0.00 21,000.00 3,150.00 24,150.00
14 Meni Besi 1 Ltr 0.70 21,000.00 0.00 21,000.00 3,150.00 24,150.00
15 Thiner 1 Ltr 0.60 28,000.00 0.00 28,000.00 4,200.00 32,200.00
16 Lem Kayu 1 Klg 1.00 15,000.00 0.00 15,000.00 2,250.00 17,250.00
17 Politur / Teak Oil 1 Ltr 1.00 37,000.00 0.00 37,000.00 5,550.00 42,550.00
18 Talang Atap segi empat PVC 3" 1 Btg 3.00 60,000.00 0.00 60,000.00 9,000.00 69,000.00
19 Lem PVC 1 Bh 0.25 15,000.00 0.00 15,000.00 2,250.00 17,250.00
20 Pengait talang 1 Bh 0.25 20,000.00 0.00 20,000.00 3,000.00 23,000.00

XII BAHAN LISTRIK


1 Lampu TL Lengkap 20 Watt Bh 1.20 31,000.00 0.00 31,000.00 4,650.00 35,650.00
40 Watt Bh 2.20 46,000.00 0.00 46,000.00 6,900.00 52,900.00
2 x 40 Watt Bh 3.50 65,000.00 0.00 65,000.00 9,750.00 74,750.00
2 Lampu pijar 60 Watt Bh 0.03 15,000.00 0.00 15,000.00 2,250.00 17,250.00
100 Watt Bh 0.03 21,000.00 0.00 21,000.00 3,150.00 24,150.00
3 Lampu PLC 18 Watt Bh 0.10 25,000.00 0.00 25,000.00 3,750.00 28,750.00
25 Watt Bh 0.10 29,500.00 0.00 29,500.00 4,425.00 33,925.00
30 Watt Bh 0.10 36,000.00 0.00 36,000.00 5,400.00 41,400.00
4 Stop Kontak 1 Bh 0.06 5,000.00 0.00 5,000.00 750.00 5,750.00
5 Saklar Tunggal 1 Bh 0.06 13,000.00 0.00 13,000.00 1,950.00 14,950.00
Saklar Duoble 1 Bh 0.06 16,000.00 0.00 16,000.00 2,400.00 18,400.00
6 Sekring khas 1 Bh 0.08 10,000.00 0.00 10,000.00 1,500.00 11,500.00
7 Sekring otomat 1 Bh 0.08 12,000.00 0.00 12,000.00 1,800.00 13,800.00
8 Sekring Box 1 Bh 0.08 15,000.00 0.00 15,000.00 2,250.00 17,250.00
9 Kabel NGA 1 M 2.30 5,000.00 0.00 5,000.00 750.00 5,750.00
10 Kabel NYM 2.5 mm Rol 4.00 195,000.00 0.00 195,000.00 29,250.00 224,250.00
11 Kabel NYM 2 x 2.5 mm Rol 8.00 235,000.00 0.00 235,000.00 35,250.00 270,250.00

UPAH KERJA
No Uraian Biaya
1 Pekerja H/o 70,000.00
2 Tukang H/o 100,000.00
3 Kepala Tukang H/o 120,000.00
4 Mandor H/o 130,000.00
HARGA BAHAN DAN UPAH KERJA
KEGIATAN : Pembangunan Rumah Mewah
PEKERJAAN : Rumah Mewah Tipe 120
LOKASI : Jayapura, Papua

A. HARGA BAHAN

NO NAMA BAHAN Satuan Harga di Lokasi

1 2 3 4
I. HARGA BAHAN LOKAL

A. KELOMPOK BAHAN BATU, PASIR, DAN TANAH


1. Batu Kali M³ 510,000.00
2. Batu Kerikil M³ 530,000.00
3. Batu Tela Bh 3,850.00
4. Batu Kerawang Bh 10,300.00
5. Paving Blok Bh 5,000.00
6. Batu Alam Bh 20,000.00
7. Sirtu M³ 285,000.00
8. Batu Pecah :
a. Ukuran 1 - 2 cm M³ 1,225,000.00
b. Ukuran 2 - 3 cm M³ 1,145,000.00
c. Ukuran 3 - 5 cm M³ 1,070,000.00
d. Ukuran 5 - 7 cm M³ 990,500.00
9. Pasir Pasang M³ 510,000.00
10. Pasir Beton M³ 530,000.00
11. Pasir Urug M³ 460,000.00
12. Tanah Timbunan/Urugan Pilihan M³ 290,000.00
13. Karang Timbunan M³ 320,000.00
14. Urugan Tanah Humus M³ 430,000.00

B. KELOMPOK BAHAN KAYU


1. KAYU KELAS I (Kayu Besi)
a. Balok Kayu uk. 10 x 10 M³ 5,100,000.00
b. Balok Kayu uk. 5 x 10 M³ 5,100,000.00
c. Balok Kayu uk. 5 x 5 M³ 5,100,000.00
d. Papan Kayu uk. 2 x 20 x 400 M³ 5,100,000.00
e. Balok Kayu uk. 6 x 12 M³ 5,100,000.00
2. KAYU KELAS II (Kayu Matoa)
a. Balok Kayu uk. 5 x 10 M³ 2,950,000.00
b. Balok Kayu uk. 5 x 5 M³ 2,950,000.00
c. Papan Kayu uk. 2 x 20 x 400 M³ 2,950,000.00
d. Kayu Steger / Buah M³ 2,400,000.00
e. Papan Bekisting M³ 2,750,000.00
f. Kayu List Kaca Batang 35,000.00
g. List Profil Kayu Batang 51,000.00
3. Besi Type C (Rangka Baja Ringan) 6 m
Lebar 15, Tebal, 1,8-2,00 mm Batang 153,800.00
4. Besi Hollow 40x40,2 mm L=4 m Batang 26,500.00

II. HARGA BAHAN NON LOKAL

A. KELOMPOK BAHAN SEMEN DAN KERAMIK


1. Semen PC 50 Kg Zak 99,900.00
2. Semen Warna Kg 24,000.00
3. Keramik uk. 50 x 50 Dos 350,000.00
4. Keramik uk. 40 x 40 Dos 122,000.00
5. Keramik uk. 30 x 30 Dos 115,000.00
6. Keramik uk. 20 x 20 Dos 105,000.00
7. Keramik uk. 20 x 25 Bh 4,000.00
8. Ubin Plint uk. 10 x 40 Bh 30,000.00
9. Ubin Homogeunes Tile 40/40 M² 138,000.00
10. Ubin Homogeunes Tile 20/20 Type Castelo M² 119,000.00
11. Ubin Homogeunes Tile 25/40 Type castelo Dos 150,000.00
12. List Keramik Dinding 5/20 Motif Bh 18,000.00
B. KELOMPOK BAHAN ATAP
1. Seng Gelombang BJLS 30 mm Lbr 94,500.00
2. Seng Gelombang BJLS 20 mm Lbr 68,500.00
3. Seng Plat BJLS 30 mm Lbr 94,500.00
4. Seng Plat BJLS 20 mm Lbr 68,500.00
7. Genteng Metal (Zincalume) Lbr 114,000.00
8. Nok Genteng Metal Lbr 96,000.00
9. Seng Roftop Lbr 216,000.00
10. Polikarbonat M² 70,000.00
11. Seng Singgalbani Lbr 95,000.00

C. KELOMPOK BAHAN PLAFOND


1. Tripleks 4 mm Lbr 80,000.00
2. Tripleks 6 mm Lbr 150,000.00
3. Multipleks 9 mm Lbr 210,000.00
3. Teakwood uk. 122 x 244 Lbr 185,000.00
4. Plafond Gypsum Board t. 9 mm
a. Rangka Hollow 4 x 4 M' 36,000.00
b. Gypsum Board t. 9 mm Lbr 114,000.00
c. Kasa Gypsum Roll 48,000.00
d. Tepung Gypsum Kg 21,600.00
e. Alkasit Kg 600,000.00
f. Paku Skrup Bh 840.00
g. Kawat Penggantung M' 6,000.00
h. List Profil Cornees Gypsum M' 50,000.00
i. List Profil Kayu 3-4 , 4 M M' 36,000.00
5. Plafond Kalsiboard t. 3,5 mm Lbr 108,000.00

NO NAMA BAHAN Satuan Harga di Lokasi


1 2 3 4

D. KELOMPOK BAHAN BESI


1. Besi Beton Polos Kg 19,750.00
2. Besi Beton Ulir Kg 19,950.00
3. Kawat Ikat Kg 30,500.00
4. Kawat Duri Pagar Kg 220,000.00
5. Kawat Harmonika T. 150 cm M¹ 88,000.00
6. Besi Siku/Strip Kg 19,000.00
7. Baja Tempa M' 45,000.00
8. Pengelasan Cm 0.00
9. Profil Aluminium M' 150,000.00
E. KELOMPOK BAHAN PIPA
1. PIPA GIP MEDIUM
a. Pipa GIP dia. 1/2" - 6 M Btg 148,000.00
b. Pipa GIP dia. 3/4" - 6 M Btg 187,200.00
c. Pipa GIP dia. 1" - 6 M Btg 244,200.00
d. Pipa GIP dia. 2" - 6 M Btg 414,500.00
e. Pipa GIP dia. 3" - 6 M Btg 665,500.00
f. Pipa GIP dia. 4" - 6 M Btg 895,000.00
g. Pipa GIP dia. 6" - 6 M Btg 3,504,000.00
2. PIPA PVC AW
a. Pipa PVC dia. ½" Btg 39,500.00
b. Pipa PVC dia. 1" Btg 51,400.00
c. Pipa PVC dia. 1½" Btg 67,400.00
d. Pipa PVC dia. 2" Btg 99,500.00
e. Pipa PVC dia. 2½" Btg 135,000.00
f. Pipa PVC dia. 3" Btg 210,000.00
g. Pipa PVC dia. 4" Btg 327,500.00
h. Pipa PVC dia. 6" Btg 695,000.00
i. Pipa PVC dia. 8" Btg 1,423,000.00

F. KELOMPOK BAHAN PAKU


1. Paku Campur Kg 27,500.00
2. Paku Seng + Ring Karet Kg 33,500.00
3. Paku Tripleks Kg 29,500.00
4. Karet Paku Bh 200.00
5. Skrup Fixer Bh 700.00
6. Pengelasan Cm' 0.00

G. KELOMPOK BAHAN KACA


1. Kaca Polos Bening 5 mm M² 345,000.00
2. Kaca Polos Rayben 5 mm M² 420,000.00
3. Kaca Polos Bening 12 mm M² 550,000.00
4. Kaca Nako Rayben 5 mm + tralis 8 Klip Set 325,000.00
5. Kaca Nako Rayben 5 mm + tralis 7 Klip Set 284,000.00
6. Bahan Dinding Aluminium Composit Panel
a. Composit Panel m2 580,000.00
b. Hollow Alumunium 2 x 4 m1 51,600.00
c. Siku Alumunium 2 x 2 m1 12,000.00
d. Baut V 25 mm bh 600.00
e. Spon tbl. 10 mm m2 21,600.00
f. Sealant tube 42,000.00
H. KELOMPOK BAHAN ELEKTRIKAL
1. Lampu TL 2 x 40 watt Lengkap + Casing Bh 131,500.00
2. Lampu TL 2 x 20 watt Lengkap + Casing Bh 109,000.00
3. Lampu SL Philips 18 watt + fiting ulir Bh 40,000.00
4. Lampu SL Philips 14 watt + fiting ulir Bh 32,000.00
5. Lampu Tanam (Down laight) Philips SL 18 watt Set 385,000.00
6. Lampu Hologen 500 Watt Set 250,000.00
7. Kabel Listrik NYM 2 x 2,5 mm M¹ 17,500.00
8. Stop Kontak Set 34,500.00
9. Saklar Tunggal Bh 34,500.00
10. Saklar Double Bh 34,500.00
11. Sekring Khass 2 Group + ACC Bh 67,000.00
12. Pipa kabel PVC ½" - 4 mm Btg 28,000.00
13. Fitting Lampu Bh 11,000.00
14. Kipas Exhaust Ceiling Bh 975,000.00
15. Baut Bh 350.00
16. Box Panel uk. 90 x 70 x 30 cm Unit 8,021,000.00
17. Box Panel uk. 80 x 60 x 40 cm Unit 7,112,300.00
18. Kabel NYY 4 x 70 mm² M' 729,750.00
19. Kabel NYY 4 x 35 mm² M' 143,000.00
20. Kabel 2 x NYA 2,5 mm² M' 29,900.00
21. AC Spilit Wall 5 PK Unit 23,100,000.00
22. AC Spilit Wall 2 PK Unit 11,136,000.00
23. AC Spilit Wall 1,5 PK Unit 7,930,800.00
24. AC Spilit Wall 1 PK Unit 5,820,000.00
25. Lift Type VSM - 630 - C0105 Unit 886,077,000.00
26. Hoisway Beam Unit 18,800.00

NO NAMA BAHAN Satuan Harga di Lokasi

1 2 3 4

I. KELOMPOK BAHAN PENGUNCI/PENGGANTUNG


1. Kunci Tanam 2 Slaag Bh 165,000.00
2. Kunci Tanam Silinder Bh 165,000.00
3. Engsel Pintu ring nilon Kuningan Psg 45,000.00
4. Engsel Jendela ring nilon Kuningan Psg 16,800.00
5. Engsel Pintu Stainless Bh 70,000.00
6. Engsel Jendela Stainless Bh 60,000.00
7. Kunci Grendel Jendela Bh 18,500.00
8. Door holder Bh 30,000.00
9. Hak Angin Psg 23,000.00

J. KELOMPOK BAHAN CAT


1. Cat Dinding Interior DULUX Kg 125,000.00
2. Cat Dinding Exterior DULUX Kg 131,000.00
3. Cat Plafond Tembok Kg 26,800.00
4. Cat Kilat Kayu setara EMCO Kg 61,500.00
5. Cat Besi Kg 61,500.00
6. Cat Meni Kayu Kg 30,200.00
7. Minyak Cat (Thineer) Ltr 29,500.00
8. Residu Kg 13,000.00
9. Teak Oil / Politur Ltr 49,000.00
10. Plamur Tembok Kg 30,000.00
11. Dempul Kayu Kg 30,200.00
12. Amplas Lbr 7,500.00
13. Kuwas Sedang Bh 9,500.00
14. Lem Kayu Kg 83,000.00
15. Karpet anti Selip M' 360,000.00
16. Sealant Tube 30,000.00
K. KELOMPOK BAHAN SANITAIR
1. Klosed Jongkok KIA Standar / Sejenis Bh 630,000.00
2. Klosed Duduk KIA Standar / Sejenis Bh 2,000,000.00
3. Wastafel lengkap Cermin Set 2,200,000.00
4. Bak Cuci Aluminium + Asesoris Set 945,000.00
5. Urinoir Porselin + Asesoris lengkap Set 1,600,000.00
6. Kran Air Kepala Putih Bh 74,000.00
7. Stop Kran Bh 103,000.00
8. Floor Drain Stainlees Bh 81,600.00
9. Mesin Pompa Air Sanyo + Asesories 450 Watt Unit 2,520,000.00
10. Shell Tape Bh 6,000.00
11. Bak Air Fiberglass 1 M³ Bh 3,400,000.00
12. Bak Air Fiberglass 2000 ltr Bh 6,100,000.00
13. Water Profing Kg 16,000.00
14. Sewa Pipa Support Set 16,000.00
15. Sewa Scafolding Set 35,000.00
16. Jack Base + Clamp Bh 15,000.00
17. Shower Spray Bh 495,000.00
18. Hand Shower Bh 750,000.00
19. Wastafel untuk Meja Bh 260,000.00
20. Cermin T. 5 mm M² 155,000.00
21. Shink Stainles Steel Bh 530,000.00
22. Water Drain + Asesories Set 98,500.00
23. Penggatung Tisu Bh 190,000.00
24. Baut Bh 500.00
25. Tempat Sabun Bh 220,000.00
26. Air bersih Ltr 600.00
27. Wastafel Bh 1,824,000.00
28. Dop Pipa Penguras Bak Bh 8,000.00

B UPAH KERJA

NO URAIAN TENAGA Satuan UPAH KERJA


1 2 3 4

1 Pekerja OH 107,000.00
2 Tukang OH 141,500.00
3 kepala Tukang OH 155,500.00
4 Mandor OH 176,000.00
ANALISA HARGA SATUAN
KEGIATAN :Pembangunan Rumah Mewah
PEKERJAAN :Rumah Mewah Type 120
LOKASI : Jayapura, Papua, Indonesia

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6

# PEKERJAAN PERSIAPAN

1. 1 M² Pembersihan Lokasi
SNI No. 6.1 ~ Pekerja 0.1000 H/o 107,000.00 10,700.00
2835-2002 ~ Mandor 0.0500 H/o 176,000.00 8,800.00
JUMLAH 19,500.00
DIBULATKAN 19,500.00
2. 1 M¹ Pagar Sementara dari Seng Gel. T. 2 m
SNI No. 6.2 ~ Dolken Kayu Buah 1.2500 Btg 68,571.43 85,714.29
2835-2002 ~ Semen PC 2.5000 Kg 1,998.00 4,995.00
~ Seng Gelombang BJLS. 20 1.2000 Lbr 68,500.00 82,200.00
~ Pasir Beton 0.0050 M³ 430,000.00 2,150.00
~ Koral Beton 0.0090 M³ 285,000.00 2,565.00
~ Kayu Kls. II 0.0720 M³ 2,950,000.00 212,400.00
~ Paku Campur 0.0600 Kg 27,500.00 1,650.00
~ Meni Besi 0.4500 Kg 30,200.00 13,590.00
~ Pekerja 0.2000 H/o 107,000.00 21,400.00
~ Tukang 0.4000 H/o 141,500.00 56,600.00
~ Kepala Tukang 0.0200 H/o 155,500.00 3,110.00
~ Mandor 0.0200 H/o 176,000.00 3,520.00
JUMLAH 489,894.29
DIBULATKAN 489,890.00
3. 1 M¹ Pengukuran dan Pemasangan Bouwplank
SNI No. 6.4 ~ Kayu Papan 3/20 0.0070 M³ 2,950,000.00 20,650.00
2835-2002 ~ Kayu Skoor 5/7 0.0120 M³ 2,950,000.00 35,400.00
~ Paku Campur 0.0200 Kg 27,500.00 550.00
~ Tukang Kayu 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang Kayu 0.0100 H/o 155,500.00 1,555.00
~ Pekerja 0.1000 H/o 107,000.00 10,700.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 83,885.00
DIBULATKAN 83,880.00

# PEKERJAAN TANAH DAN PASIR

4. 1 M³ Galian Tanah Biasa sedalam 1 M


SNI No. 6.1 ~ Pekerja 0.7500 H/o 107,000.00 80,250.00
2836-2008 ~ Mandor 0.0250 H/o 176,000.00 4,400.00
JUMLAH 84,650.00
DIBULATKAN 84,650.00
5. 1 M³ Galian Tanah Biasa sedalam 2 M
SNI No. 6.2 ~ Pekerja 0.9000 H/o 107,000.00 96,300.00
2836-2008 ~ Mandor 0.0450 H/o 176,000.00 7,920.00
JUMLAH 104,220.00
DIBULATKAN 104,220.00
6. 1 M³ Pembuangan Tanah sejauh 150 M
SNI No. 6.8 ~ Pekerja 0.5160 H/o 107,000.00 55,212.00
2835-2002 ~ Mandor 0.0500 H/o 176,000.00 8,800.00
JUMLAH 64,012.00
DIBULATKAN 64,010.00
7. 1 M³ Urugan Kembali Galian Tanah
SNI No. 6.9 ~ Pekerja 0.1333 H/o 107,000.00 14,263.10
2836-2008 ~ Mandor 0.0830 H/o 176,000.00 14,608.00
JUMLAH 28,871.10
DIBULATKAN 28,870.00
8. 1 M³ Urugan Pasir
SNI No. 6.11 ~ Pasir Urug 1.2000 M³ 460,000.00 552,000.00
2836-2008 ~ Pekerja 0.3000 H/o 107,000.00 32,100.00
~ Mandor 0.0100 H/o 176,000.00 1,760.00
JUMLAH 585,860.00
DIBULATKAN 585,860.00
9. 1 M³ Urugan Sirtu
SNI No. 6.15 ~ Urugan Sirtu 1.2000 M³ 200,000.00 240,000.00
2836-2008 ~ Pekerja 0.3000 H/o 107,000.00 32,100.00
~ Mandor 0.0100 H/o 176,000.00 1,760.00
JUMLAH 273,860.00
DIBULATKAN 273,860.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
10. 1 M³ Urugan Tanah Humus
SNI No. 6.15 ~ Urugan Tanah Humus 1.2000 M³ 430,000.00 516,000.00
2836-2008 ~ Pekerja 0.3000 H/o 107,000.00 32,100.00
~ Mandor 0.0100 H/o 176,000.00 1,760.00
JUMLAH 549,860.00
DIBULATKAN 549,860.00
# PEKERJAAN PASANGAN PONDASI

11. 1 M³ Pasangan Pondasi Batu Kosong (Aanstamping)


SNI No. 6.9 ~ Batu Belah 15/20 cm 1.2000 M³ 510,000.00 612,000.00
2836-2008 ~ Pasir Urug 0.4320 M³ 460,000.00 198,720.00
~ Pekerja 0.7800 H/o 107,000.00 83,460.00
~ Tukang 0.3900 H/o 141,500.00 55,185.00
~ Kepala Tukang 0.0390 H/o 155,500.00 6,064.50
~ Mandor 0.0390 H/o 176,000.00 6,864.00
JUMLAH 962,293.50
DIBULATKAN 962,290.00
12. 1 M³ Pasangan Pondasi Footplate
SNI No. 6.2 Campuran 1 Pc : 4 Psr
2836-2008 ~ Batu Belah 15/20 cm 1.2000 M³ 510,000.00 612,000.00
~ Sement PC 163.0000 Kg 1,998.00 325,674.00
~ Pasir Pasang 0.5200 M³ 400,000.00 208,000.00
~ Pekerja 1.5000 H/o 107,000.00 160,500.00
~ Tukang 0.7500 H/o 141,500.00 106,125.00
~ Kepala Tukang 0.0750 H/o 155,500.00 11,662.50
~ Mandor 0.0750 H/o 176,000.00 13,200.00
JUMLAH 1,437,161.50
DIBULATKAN 1,437,160.00

# PEKERJAAN PASANGAN DINDING

13. 1 M² Pasangan Dinding Batu Tela


SNI No. 6.16 Campuran 1 Pc : 2 Psr
6897-2008 ~ Batu Tela 20.000 Bh 3,850.00 77,000.00
~ Sement PC 19.000 Kg 1,998.00 37,962.00
~ Pasir Pasang 0.038 M³ 400,000.00 15,200.00
~ Pekerja 0.300 H/o 107,000.00 32,100.00
~ Tukang 0.100 H/o 141,500.00 14,150.00
~ Kepala Tukang 0.010 H/o 155,500.00 1,555.00
~ Mandor 0.015 H/o 176,000.00 2,640.00
JUMLAH 180,607.00
DIBULATKAN 180,600.00
14. 1 M² Pasangan Dinding Batu Tela Tidur
SNI No. 6.16 Campuran 1 Pc : 3 Psr
6897-2008 ~ Batu Tela 52.300 Bh 3,850.00 201,355.00
~ Sement PC 32.950 Kg 1,998.00 65,834.10
~ Pasir Pasang 0.073 M³ 400,000.00 29,200.00
~ Pekerja 0.350 H/o 107,000.00 37,450.00
~ Tukang 0.150 H/o 141,500.00 21,225.00
~ Kepala Tukang 0.015 H/o 155,500.00 2,332.50
~ Mandor 0.018 H/o 176,000.00 3,168.00
JUMLAH 360,564.60
DIBULATKAN 360,560.00
15. 1 M² Pasangan Dinding Batu Tela
SNI No. 6.17 Campuran 1 Pc : 4 Psr
6897-2008 ~ Batu Tela 20.000 Bh 3,000.00 60,000.00
~ Sement PC 12.0000 Kg 1,998.00 23,976.00
~ Pasir Pasang 0.043 M³ 400,000.00 17,200.00
~ Pekerja 0.300 H/o 107,000.00 32,100.00
~ Tukang 0.100 H/o 141,500.00 14,150.00
~ Kepala Tukang 0.010 H/o 155,500.00 1,555.00
~ Mandor 0.015 H/o 176,000.00 2,640.00
JUMLAH 151,621.00
DIBULATKAN 151,620.00
# PEKERJAAN PLESTERAN
16. 1 M² Plesteran Tebal 15 mm
SNI No. 6.2 Campuran 1 Pc : 2 Psr
2837-2008 ~ Sement PC 10.2240 Kg 1,998.00 20,427.55
~ Pasir Pasang 0.0200 M³ 400,000.00 8,000.00
~ Pekerja 0.3840 H/o 107,000.00 41,088.00
~ Tukang 0.1500 H/o 141,500.00 21,225.00
~ Kepala Tukang 0.0150 H/o 155,500.00 2,332.50
~ Mandor 0.0150 H/o 176,000.00 2,640.00
JUMLAH 95,713.05
DIBULATKAN 95,710.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
17. 1 M² Acian Dinding Batu Tela
SNI No. 6.27 ~ Sement PC 3.2500 Kg 1,998.00 6,493.50
2837-2008 ~ Pekerja 0.2000 H/o 107,000.00 21,400.00
~ Tukang 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0100 H/o 176,000.00 1,760.00
JUMLAH 45,358.50
DIBULATKAN 45,350.00

# PEKERJAAN BETON

18. 1 M³ Membuat Beton Mutu f'c : 7,4 Mpa (K100)


SNI No. 6.1 ~ Sement PC 247.0000 Kg 1,998.00 493,506.00
7394-2008 ~ Pasir Beton 0.4340 M³ 430,000.00 186,620.00
~ Kerikil Beton 0.5940 M³ 530,000.00 314,820.00
~ Air 215.000 Ltr 600.00 129,000.00
~ Pekerja 1.6500 H/o 107,000.00 176,550.00
~ Tukang 0.2750 H/o 141,500.00 38,912.50
~ Kepalla Tukang 0.0280 H/o 155,500.00 4,354.00
~ Mandor 0.0830 H/o 176,000.00 14,608.00
JUMLAH 1,358,370.50
DIBULATKAN 1,358,370.00
19. 1 M³ Membuat Beton Mutu f'c : 19,3 Mpa (K225)
SNI No. 6.1 ~ Sement PC 371.0000 Kg 1,998.00 741,258.00
7394-2008 ~ Pasir Beton 0.3490 M³ 530,000.00 184,970.00
~ Kerikil/Batu Pecah uk. 2 - 3 cm 0.6220 M³ 1,145,000.00 712,190.00
~ Air 215.000 Ltr 600.00 129,000.00
~ Pekerja 1.6500 H/o 107,000.00 176,550.00
~ Tukang 0.2750 H/o 141,500.00 38,912.50
~ Kepalla Tukang 0.0280 H/o 155,500.00 4,354.00
~ Mandor 0.0830 H/o 176,000.00 14,608.00
JUMLAH 2,001,842.50
DIBULATKAN 2,001,840.00
20. 1 Kg Pembesian dengan Besi Polos/Ulir
SNI No. 6.17 ~ Besi Beton Polos/Ulir 1.0500 Kg 19,750.00 20,737.50
7394-2008 ~ Kawat Beton 0.0150 Kg 30,500.00 457.50
~ Pekerja 0.0070 H/o 107,000.00 749.00
~ Tukang 0.0070 H/o 141,500.00 990.50
~ Kepalla Tukang 0.0007 H/o 155,500.00 108.85
~ Mandor 0.0004 H/o 176,000.00 70.40
JUMLAH 23,113.75
DIBULATKAN 23,110.00
21. 1 M² Memasang Bekisting untuk Pondasi
SNI No. 6.2 ~ Kayu Matoa 0.0400 M³ 2,950,000.00 118,000.00
7394-2008 ~ Paku Campur 0.1500 Kg 27,500.00 4,125.00
~ Pekerja 0.5200 H/o 107,000.00 55,640.00
~ Tukang 0.2600 H/o 141,500.00 36,790.00
~ Kepalla Tukang 0.0260 H/o 155,500.00 4,043.00
~ Mandor 0.0260 H/o 176,000.00 4,576.00
JUMLAH 223,174.00
DIBULATKAN 223,170.00
22. 1 M² Pasang Bekisting Sloof
~ Kayu Begisting 0.0450 M³ 2,400,000.00 108,000.00
~ Paku Campur 0.3000 Kg 27,500.00 8,250.00
~ Pekerja 0.5200 H/o 107,000.00 55,640.00
~ Tukang 0.2600 H/o 141,500.00 36,790.00
~ Kepalla Tukang 0.0260 H/o 155,500.00 4,043.00
~ Mandor 0.0260 H/o 176,000.00 4,576.00
JUMLAH 217,299.00
DIBULATKAN 217,290.00
23. 1 M² Bekisting Kolom
~ Kayu Begisting 0.0400 M³ 2,400,000.00 96,000.00
~ Paku Campur 0.4000 Kg 27,500.00 11,000.00
~ Balok Kayu 0.0150 M³ 2,950,000.00 44,250.00
~ Tripleks 9 mm 0.3500 Lbr 210,000.00 73,500.00
~ Pekerja 0.3000 H/o 107,000.00 32,100.00
~ Tukang 0.2600 H/o 141,500.00 36,790.00
~ Kepalla Tukang 0.0260 H/o 155,500.00 4,043.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 298,563.00
DIBULATKAN 298,560.00
24. 1 M² Memasang Bekisting untuk Balok
SNI No. 6.23 ~ Kayu Matoa 0.0400 M³ 2,950,000.00 118,000.00
7394-2008 ~ Paku Campur 0.2000 Kg 27,500.00 5,500.00
~ Multiplek 9 mm 0.3500 Lbr 210,000.00 73,500.00
~ Sewa Scafolding 1.0000 Set 35,000.00 35,000.00
~ Pekerja 0.6600 H/o 107,000.00 70,620.00
~ Tukang 0.3300 H/o 141,500.00 46,695.00
~ Kepalla Tukang 0.0330 H/o 155,500.00 5,131.50
~ Mandor 0.0330 H/o 176,000.00 5,808.00
JUMLAH 360,254.50
DIBULATKAN 360,250.00
25. 1 M² Bekisting Dinding
~ Kayu Matoa 0.0300 M³ 2,950,000.00 88,500.00
~ Paku Campur 0.2000 Kg 27,500.00 5,500.00
~ Sewa Pipa Support 1.0000 Set 16,000.00 16,000.00
~ Tripleks 9 mm 0.3500 Lbr 210,000.00 73,500.00
~ Jack Base + Clamp 1.0000 Bh 15,000.00 15,000.00
~ Pekerja 0.3000 H/o 107,000.00 32,100.00
~ Tukang 0.2600 H/o 141,500.00 36,790.00
~ Kepalla Tukang 0.0260 H/o 155,500.00 4,043.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 272,313.00
DIBULATKAN 272,310.00
26. 1 M² Bekisting Plat Lantai
~ Kayu Begisting 0.0400 M³ 2,400,000.00 96,000.00
~ Paku Campur 0.4000 Kg 27,500.00 11,000.00
~ Balok Kayu 0.0150 M³ 2,950,000.00 44,250.00
~ Tripleks 9 mm 0.3500 Lbr 210,000.00 73,500.00
~ Pekerja 0.3200 H/o 107,000.00 34,240.00
~ Tukang 0.3300 H/o 141,500.00 46,695.00
~ Kepalla Tukang 0.0330 H/o 155,500.00 5,131.50
~ Mandor 0.0060 H/o 176,000.00 1,056.00
JUMLAH 311,872.50
DIBULATKAN 311,870.00
27. 1 M³ Membongkar Cetakan
~ Pekerja 4.0000 H/o 107,000.00 428,000.00
JUMLAH 428,000.00
DIBULATKAN 428,000.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
28. 1 M³ Beton Pondasi Poer Plat (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 246.8278 Kg 23,110.00 5,704,190.02
~ Begisting Pondasi 1.8461 M² 223,170.00 411,992.95
JUMLAH 8,118,022.97
DIBULATKAN 8,118,020.00
29. 1 M³ Cor Sloof (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 167.1851 Kg 23,110.00 3,863,647.05
~ Begisting Sloof 7.1829 M² 217,290.00 1,560,770.35
JUMLAH 7,426,257.41
DIBULATKAN 7,426,250.00
30. 1 M³ Cor Kolom (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 208.2019 Kg 23,110.00 4,811,544.80
~ Begisting Kolom 13.3333 M² 298,560.00 3,980,800.00
JUMLAH 10,794,184.80
DIBULATKAN 10,794,180.00
31. 1 M³ Cor Kolom Praktis 15 x 15 (K175)
~ Beton K100 1.0000 M³ 1,358,370.00 1,358,370.00
~ Pembesian 110.0000 Kg 23,110.00 2,542,100.00
~ Begisting Kolom 13.3333 M² 298,560.00 3,980,800.00
JUMLAH 7,881,270.00
DIBULATKAN 7,881,270.00
32. 1 M³ Cor Beton Balok (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 183.1246 Kg 23,110.00 4,232,009.37
~ Begisting Balok 14.5918 M² 360,250.00 5,256,681.65
JUMLAH 11,490,531.02
DIBULATKAN 11,490,530.00
33. 1 M³ Cor Beton Rinkbalk 15 x 15 (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 196.8119 Kg 23,110.00 4,548,321.90
~ Begisting Balok 28.7111 M² 360,250.00 10,343,177.78
JUMLAH 16,893,339.67
DIBULATKAN 16,893,330.00
34. 1 M³ Cor Plat Lantai dasar T. 12 cm (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 197.7634 Kg 23,110.00 4,570,312.51
~ Begisting 0.7390 M² 311,870.00 230,471.93
~ Pembongkaran Bekisting 0.0060 M³ 428,000.00 2,568.00
JUMLAH 6,805,192.44
DIBULATKAN 6,805,190.00
35. 1 M³ Cor Plat Lantai T. 12 cm (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 197.7634 Kg 23,110.00 4,570,312.51
~ Begisting 9.2336 M² 311,870.00 2,879,686.06
~ Pembongkaran Bekisting 0.9800 M³ 428,000.00 419,440.00
JUMLAH 9,871,278.56
DIBULATKAN 9,871,270.00
36. 1 M³ Cor Plat Lantai T. 10 cm (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 110.0000 Kg 23,110.00 2,542,100.00
~ Begisting 9.2340 M² 311,870.00 2,879,807.58
~ Pembongkaran Bekisting 0.9800 M³ 428,000.00 419,440.00
JUMLAH 7,843,187.58
DIBULATKAN 7,843,180.00
37. 1 M³ Cor Beton Plat Tangga T. 12 cm (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 150.0000 Kg 23,110.00 3,466,500.00
~ Begisting 8.3330 M² 311,870.00 2,598,812.71
~ Pembongkaran Bekisting 2.5000 M³ 428,000.00 1,070,000.00
JUMLAH 9,137,152.71
DIBULATKAN 9,137,150.00
38. 1 M³ Cor Beton Listplank 12/40 (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 110.0000 Kg 23,110.00 2,542,100.00
~ Begisting Balok 6.0000 M² 360,250.00 2,161,500.00
JUMLAH 6,705,440.00
DIBULATKAN 6,705,440.00
39. 1 M³ Cor Listplank Beton T. 12 cm (K225)
~ Beton K225 1.0000 M³ 2,001,840.00 2,001,840.00
~ Pembesian 324.7778 Kg 23,110.00 7,505,614.44
~ Begisting 25.0000 M² 360,250.00 9,006,250.00
~ Pembongkaran Bekisting 1.5000 M³ 428,000.00 642,000.00
JUMLAH 19,155,704.44
DIBULATKAN 19,155,700.00

# PEKERJAAN PELAPIS LANTAI DAN DINDING

40. 1 M² Pasang Lantai Ubin Keramik 40/40


SNI No. 6.1 ~ Ubin Keramik uk. 40/40 6.6300 Bh 122,000.00 808,860.00
7395-2008 ~ Semen PC 9.8000 Kg 1,998.00 19,580.40
~ Pasir Pasang 0.0450 M³ 400,000.00 18,000.00
~ Pekerja 0.2500 H/o 107,000.00 26,750.00
~ Tukang 0.1250 H/o 141,500.00 17,687.50
~ Kepalla Tukang 0.0130 H/o 155,500.00 2,021.50
~ Mandor 0.0130 H/o 176,000.00 2,288.00
JUMLAH 895,187.40
DIBULATKAN 895,180.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
41. 1 M² Pasang Lantai Ubin Keramik 30/30
SNI No. 6.2 ~ Ubin Keramik uk. 30/30 11.8700 Bh 10,454.55 124,095.45
7395-2008 ~ Semen PC 10.0000 Kg 1,998.00 19,980.00
~ Pasir Pasang 0.0450 M³ 400,000.00 18,000.00
~ Pekerja 0.2600 H/o 107,000.00 27,820.00
~ Tukang 0.1300 H/o 141,500.00 18,395.00
~ Kepalla Tukang 0.0130 H/o 155,500.00 2,021.50
~ Mandor 0.0130 H/o 176,000.00 2,288.00
JUMLAH 212,599.95
DIBULATKAN 212,590.00
42. 1 M² Pasang Lantai Ubin Keramik 20/20
SNI No. 6.3 ~ Ubin Keramik uk. 20/20 26.5000 Bh 4,200.00 111,300.00
7395-2008 ~ Semen PC 10.4000 Kg 1,998.00 20,779.20
~ Pasir Pasang 0.0450 M³ 400,000.00 18,000.00
~ Pekerja 0.2700 H/o 107,000.00 28,890.00
~ Tukang 0.1350 H/o 141,500.00 19,102.50
~ Kepalla Tukang 0.0130 H/o 155,500.00 2,021.50
~ Mandor 0.0130 H/o 176,000.00 2,288.00
JUMLAH 202,381.20
DIBULATKAN 202,380.00
43. 1 M² Pasang Lantai Ubin 20/20
SNI No. 6.1 ~ Ubin uk. 20/20 Type Castelo 26.5000 Bh 4,760.00 126,140.00
7395-2008 ~ Semen PC 10.4000 Kg 1,998.00 20,779.20
~ Pasir Pasang 0.0450 M³ 400,000.00 18,000.00
~ Pekerja 0.2700 H/o 107,000.00 28,890.00
~ Tukang 0.1350 H/o 141,500.00 19,102.50
~ Kepalla Tukang 0.0140 H/o 155,500.00 2,177.00
~ Mandor 0.0140 H/o 176,000.00 2,464.00
JUMLAH 217,552.70
DIBULATKAN 217,550.00
44. 1 M² Pasang Dinding Keramik Homogeunes Tile 20/25
SNI No. 6.1 ~ Keramik Homogeunes Tile uk. 20/25 Type C 1.0000 M² 80,000.00 80,000.00
7395-2008 ~ Semen PC 10.0000 Kg 1,998.00 19,980.00
~ Pasir Pasang 0.0450 M³ 400,000.00 18,000.00
~ Pekerja 0.7000 H/o 107,000.00 74,900.00
~ Tukang 0.3500 H/o 141,500.00 49,525.00
~ Kepalla Tukang 0.0350 H/o 155,500.00 5,442.50
~ Mandor 0.0350 H/o 176,000.00 6,160.00
JUMLAH 254,007.50
DIBULATKAN 254,000.00
45. 1 M² Pasang Dinding Keramik 25/40 Type castelo
SNI No. 6.54 ~ Ubin Keramik uk. 25/40 Type Castelo 1.0000 M² 150,000.00 150,000.00
7395-2008 ~ Semen PC 9.3000 Kg 1,998.00 18,581.40
~ Pasir Pasang 0.0180 M³ 400,000.00 7,200.00
~ Pekerja 0.9000 H/o 107,000.00 96,300.00
~ Tukang 0.4500 H/o 141,500.00 63,675.00
~ Kepalla Tukang 0.0450 H/o 155,500.00 6,997.50
~ Mandor 0.0450 H/o 176,000.00 7,920.00
JUMLAH 350,673.90
DIBULATKAN 350,670.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
46. 1 M' Pasang List Keramik Dinding 5/20 Motif
SNI No. 6.54 ~ List Keramik Dinding Motif 5.1000 Bh 18,000.00 91,800.00
7395-2008 ~ Semen PC 0.5700 Kg 1,998.00 1,138.86
~ Pasir Pasang 0.0015 M³ 400,000.00 600.00
~ Semen Warna 0.0130 Kg 24,000.00 312.00
~ Pekerja 0.0900 H/o 107,000.00 9,630.00
~ Tukang 0.0900 H/o 141,500.00 12,735.00
~ Kepalla Tukang 0.0090 H/o 155,500.00 1,399.50
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 118,495.36
DIBULATKAN 118,490.00
47. 1 M' Pasang List Plint Keramik Dinding 10/40
SNI No. 6.21 ~ List Plint Keramik 10 x 40 2.6500 Bh 30,000.00 79,500.00
7395-2008 ~ Semen PC 1.1400 Kg 1,998.00 2,277.72
~ Pasir Pasang 0.0030 M³ 400,000.00 1,200.00
~ Semen Warna 0.1000 Kg 24,000.00 2,400.00
~ Pekerja 0.0900 H/o 107,000.00 9,630.00
~ Tukang 0.0900 H/o 141,500.00 12,735.00
~ Kepalla Tukang 0.0090 H/o 155,500.00 1,399.50
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 110,022.22
DIBULATKAN 110,020.00
48. 1 M² Pasang Paving Block
SNI No. 6.21 ~ Pasir Pasang 0.1100 M³ 400,000.00 44,000.00
7395-2008 ~ Sirtu 0.2200 M³ 200,000.00 44,000.00
~ Paving Block 30.0000 Bh 5,000.00 150,000.00
~ Pekerja 0.7500 H/o 107,000.00 80,250.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepalla Tukang 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0010 H/o 176,000.00 176.00
JUMLAH 396,951.00
DIBULATKAN 396,950.00
49. 1 M² Pasangan Dinding Batu Alam
Empiris ~ Batu Alam 10.0000 Bh 20,000.00 200,000.00
~ Pasir Pasang 0.0370 M³ 400,000.00 14,800.00
~ Semen PC 14.0000 Kg 1,998.00 27,972.00
~ Tukang 0.2440 oh 141,500.00 34,526.00
~ Kepala tukang 0.0244 org 155,500.00 3,794.20
~ Pekerja 0.5700 org 107,000.00 60,990.00
~ Mandor 0.0336 org 176,000.00 5,913.60
JUMLAH 347,995.80
DIBULATKAN 347,990.00
50. 1 M² Pasangan Dinding Batu Terawang/Roster
Empiris ~ Batu Kerawang 10.0000 Bh 530,000.00 5,300,000.00
~ Pasir Pasang 0.0370 M³ 400,000.00 14,800.00
~ Semen PC 14.0000 Kg 1,998.00 27,972.00
~ Tukang 0.2440 oh 141,500.00 34,526.00
~ Kepala tukang 0.0244 org 155,500.00 3,794.20
~ Pekerja 0.5700 org 107,000.00 60,990.00
~ Mandor 0.0336 org 176,000.00 5,913.60
JUMLAH 5,447,995.80
DIBULATKAN 5,447,990.00

# PEKERJAAN KAYU dan PLAFOND

51. 1 M³ Kusen Pintu dan Jendela 5/10


SNI No. 6.1 ~ Kayu Besi uk. 5/10 1.1000 M³ 5,100,000.00 5,610,000.00
3434-2008 ~ Paku 1.2500 Kg 27,500.00 34,375.00
~ Lem Kayu 1.0000 Kg 83,000.00 83,000.00
~ Pekerja 7.0000 H/o 107,000.00 749,000.00
~ Tukang 21.0000 H/o 141,500.00 2,971,500.00
~ Kepalla Tukang 2.1000 H/o 155,500.00 326,550.00
~ Mandor 0.3500 H/o 176,000.00 61,600.00
JUMLAH 9,836,025.00
DIBULATKAN 9,836,020.00
52. 1 M² Pasang Daun Pintu Panil Kayu
SNI No. 6.5 ~ Papan Kayu Besi 0.0400 M³ 5,100,000.00 204,000.00
3434-2008 ~ Lem Kayu 0.5000 Kg 83,000.00 41,500.00
~ Pekerja 1.0000 H/o 107,000.00 107,000.00
~ Tukang 3.0000 H/o 141,500.00 424,500.00
~ Kepalla Tukang 0.3000 H/o 155,500.00 46,650.00
~ Mandor 0.0500 H/o 176,000.00 8,800.00
JUMLAH 832,450.00
DIBULATKAN 832,450.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
53. 1 M² Pasang Daun Pintu Panil Kaca
SNI No. 6.6 ~ Kaca Ryben T. 5 mm 1.1000 M² 51,400.00 56,540.00
3434-2008 ~ Papan kayu Besi 0.0240 M³ 5,100,000.00 122,400.00
~ Lem Kayu 0.3000 Kg 83,000.00 24,900.00
~ Pekerja 0.8000 H/o 107,000.00 85,600.00
~ Tukang 2.4000 H/o 141,500.00 339,600.00
~ Kepalla Tukang 0.2400 H/o 155,500.00 37,320.00
~ Mandor 0.0400 H/o 176,000.00 7,040.00
JUMLAH 673,400.00
DIBULATKAN 673,400.00
54. 1 M² Pasangan Jendela Panil Kaca
~ Papan Kayu Besi 0.0240 M³ 5,100,000.00 122,400.00
~ Lem Kayu 0.3000 Kg 83,000.00 24,900.00
~ Kaca Ryben T. 5 mm 1.1000 M² 51,400.00 56,540.00
~ Tukang Kayu 2.4000 H/o 141,500.00 339,600.00
~ Pekerja 0.8000 H/o 107,000.00 85,600.00
~ Kepala Tukang Kayu 0.2400 H/o 155,500.00 37,320.00
~ Mandor 0.0400 H/o 176,000.00 7,040.00
JUMLAH 673,400.00
DIBULATKAN 673,400.00
55. 1 M² Pasangan Jalusi
~ Papan Kayu Besi 0.0640 M³ 5,100,000.00 326,400.00
~ Tukang Kayu 3.0000 H/o 141,500.00 424,500.00
~ Kepala Tukang Kayu 0.3000 H/o 155,500.00 46,650.00
~ Pekerja 1.0000 H/o 107,000.00 107,000.00
~ Mandor 0.0500 H/o 176,000.00 8,800.00
~ Paku 0.1500 Kg 27,500.00 4,125.00
JUMLAH 917,475.00
DIBULATKAN 917,470.00
56. 1 M² Pasang Daun Pintu Panil Kayu Lapis Seng Plat
SNI No. 6.5 ~ Papan Kayu Besi 0.0400 M³ 5,100,000.00 204,000.00
3434-2008 ~ Lem Kayu 0.5000 Kg 83,000.00 41,500.00
~ Seng Plat BJLS 30 0.5300 Lbr 94,500.00 50,085.00
~ Pekerja 1.0000 H/o 107,000.00 107,000.00
~ Tukang 3.0000 H/o 141,500.00 424,500.00
~ Kepalla Tukang 0.3000 H/o 155,500.00 46,650.00
~ Mandor 0.0500 H/o 176,000.00 8,800.00
JUMLAH 882,535.00
DIBULATKAN 882,530.00
57. 1 M² Dinding Partisi Double Gypsumboard R, Ky. Besi
SNI No. 6.5 ~ Balok Ky. Besi 0.0195 M³ 5,100,000.00 99,450.00
3434-2008 ~ Papan Ky. Besi 0.0070 M³ 5,100,000.00 35,700.00
~ Paku 0.1000 Kg 27,500.00 2,750.00
~ Lem Kayu 0.5600 Ltr 83,000.00 46,480.00
~ Gypsumboard T 9 mm 1.0000 Lbr 114,000.00 114,000.00
~ Pekerja 0.1500 H/o 107,000.00 16,050.00
~ Tukang 0.4500 H/o 141,500.00 63,675.00
~ Kepalla Tukang 0.0450 H/o 155,500.00 6,997.50
~ Mandor 0.0750 H/o 176,000.00 13,200.00
JUMLAH 398,302.50
DIBULATKAN 398,300.00
58. 1 M² Pasang Jendela Kaca Mati (kaca bening t. 5 mm)
~ Kaca Bening T. 5 mm 1.1000 M² 51,400.00 56,540.00
~ Pekerja 0.0150 H/o 107,000.00 1,605.00
~ Tukang 0.1500 H/o 141,500.00 21,225.00
~ Kepalla Tukang 0.0150 H/o 155,500.00 2,332.50
~ Mandor 0.0080 H/o 176,000.00 1,408.00
JUMLAH 83,110.50
DIBULATKAN 83,110.00
59. 1 M² Pasang Dinding Kaca Mati (kaca bening t. 12 mm)
~ Kaca Bening T. 12 mm 1.2000 M² 550,000.00 660,000.00
~ Kusen Aluminium 1.0000 M² 123,843.00 123,843.00
~ Pekerja 0.0150 H/o 107,000.00 1,605.00
~ Tukang 0.1500 H/o 141,500.00 21,225.00
~ Kepalla Tukang 0.0150 H/o 155,500.00 2,332.50
~ Mandor 0.0080 H/o 176,000.00 1,408.00
JUMLAH 810,413.50
DIBULATKAN 810,410.00
60. 1 M² Rangka plafond 60 x 60 Ky Besi 5/5,
SNI ~ Balok kayu Besi 5/5 0.0163 M³ 5,100,000.00 83,130.00
2839-2008 ~ Paku campur 0.2500 kg 36,000.00 9,000.00
~ Pekerja 0.2000 H/o 107,000.00 21,400.00
~ Tukang 0.3000 H/o 141,500.00 42,450.00
~ Kepala tukang 0.0300 H/o 155,500.00 4,665.00
~ Mandor 0.0100 H/o 176,000.00 1,760.00
JUMLAH (Belum PPn) 162,405.00
DIBULATKAN 162,400.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
61. 1 M² Langit - langit Gypsum Board t. 9 mm,
SNI ~ Gypsum board 9 mm 0.3640 lbr 94,500.00 34,398.00
2839-2008 ~ Kasa gypsum 0.0500 roll 68,500.00 3,425.00
~ Tepung gypsum 0.4500 kg 94,500.00 42,525.00
~ Alkasit 0.0030 kg 68,500.00 205.50
~ Paku skrup 20.0000 kg 114,000.00 2,280,000.00
~ Pekerja 0.2400 H/o 107,000.00 25,680.00
~ Tukang 0.3700 H/o 141,500.00 52,355.00
~ Kepalla Tukang 0.0370 H/o 155,500.00 5,753.50
~ Mandor 0.0120 H/o 176,000.00 2,112.00
JUMLAH 2,446,454.00
DIBULATKAN 2,446,450.00
62. 1 M² Langit - langit Calsiboard t. 6 mm,
SNI ~ Calsiboard 6 mm 0.3640 lbr 95,000.00 34,580.00
2839-2008 ~ Kasa gypsum 0.0500 roll 68,500.00 3,425.00
~ Tepung gypsum 0.4500 kg 94,500.00 42,525.00
~ Alkasit 0.0030 kg 68,500.00 205.50
~ Paku skrup 20.0000 kg 114,000.00 2,280,000.00
~ Pekerja 0.2400 H/o 107,000.00 25,680.00
~ Tukang 0.3700 H/o 141,500.00 52,355.00
~ Kepalla Tukang 0.0370 H/o 155,500.00 5,753.50
~ Mandor 0.0120 H/o 176,000.00 2,112.00
JUMLAH 2,446,636.00
DIBULATKAN 2,446,630.00
63. 1 M' Pasang List Profil Cornees Gypsum 5 - 10 cm
SNI ~ List Profil Cornees Gypsum 1.0500 M' 216,000.00 226,800.00
2839-2008 ~ Tepung Gypsum 0.1500 Kg 21,600.00 3,240.00
~ Alkasit 0.0040 Kg 600,000.00 2,400.00
~ Pekerja 0.0600 H/o 107,000.00 6,420.00
~ Tukang 0.0600 H/o 141,500.00 8,490.00
~ Kepalla Tukang 0.0060 H/o 155,500.00 933.00
~ Mandor 0.0030 H/o 176,000.00 528.00
JUMLAH 248,811.00
DIBULATKAN 248,810.00
64. 1 M' Pasang List Profil Kayu
SNI ~ List Profil Kayu 1.2000 M' 70,000.00 84,000.00
2839-2008 ~ Paku 0.0100 Kg 414,500.00 4,145.00
~ Pekerja 0.0500 H/o 107,000.00 5,350.00
~ Tukang 0.0500 H/o 141,500.00 7,075.00
~ Kepalla Tukang 0.0050 H/o 155,500.00 777.50
~ Mandor 0.0030 H/o 176,000.00 528.00
JUMLAH 101,875.50
DIBULATKAN 101,870.00
65. 1 M² Pekerjaan Dinding Skat Double Teakwood
~ Teakwood 0.7600 Lbr 185,000.00 140,600.00
~ Rangka Kayu Besi 5/10 0.0200 M³ 5,100,000.00 102,000.00
~ Kayu Besi Papan 0.0070 M³ 5,100,000.00 35,700.00
~ Paku Tripleks 0.1000 Kg 29,500.00 2,950.00
~ Lem Kayu 0.5600 Kg 83,000.00 46,480.00
~ Tukang Kayu 0.4500 H/o 141,500.00 63,675.00
~ Pekerja 0.1500 H/o 107,000.00 16,050.00
~ Kepala Tukang 0.0450 H/o 155,500.00 6,997.50
~ Mandor 0.0750 H/o 176,000.00 13,200.00
JUMLAH 427,652.50
DIBULATKAN 427,650.00
66. 1 Set Pek. Kaca Nako 8 Klip + Tralis
~ Stang Louver + Kaca + Tralis 1.0000 Set 325,000.00 325,000.00
~ Tukang Kayu 1.3000 H/o 141,500.00 183,950.00
~ Pekerja 0.2800 H/o 107,000.00 29,960.00
~ Kepala Tukang 0.1300 H/o 155,500.00 20,215.00
~ Mandor 0.1000 H/o 176,000.00 17,600.00
JUMLAH 576,725.00
DIBULATKAN 576,720.00
67. 1 M² Memasang Teralis Besi Tempa
~ Baja Tempa 6.1770 M' 45,000.00 277,965.00
~ Pengelasan 27.0800 Cm 4,570.80 123,777.26
~ Tukang Las 1.6700 H/o 141,500.00 236,305.00
~ Pekerja 1.6700 H/o 107,000.00 178,690.00
~ Kepala Tukang 0.1670 H/o 155,500.00 25,968.50
~ Mandor 0.0830 H/o 176,000.00 14,608.00
JUMLAH 857,313.76
DIBULATKAN 857,310.00
68. 1 M² Pas. Kawat Harmonika
~ Papan Kayu Besi 0.0018 M³ 5,100,000.00 9,180.00
~ Kawat Harmonika 1.1000 M² 88,000.00 96,800.00
~ Paku 0.0200 Kg 27,500.00 550.00
~ Tukang Kayu 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang Kayu 0.0100 H/o 155,500.00 1,555.00
~ Pekerja 0.1000 H/o 107,000.00 10,700.00
~ Mandor 0.0005 H/o 176,000.00 88.00
JUMLAH 123,843.00
DIBULATKAN 123,840.00

# PEKERJAAN PENGGANTUNG & PENGUNCI

69. 1 Bh Pasang Kunci Tanam 2 Slaag


SNI ~ Kunci Tanam Dua Slaag 1.0000 Bh 350.00 350.00
2835-2002 ~ Pekerja 0.0100 H/o 107,000.00 1,070.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH (Belum PPn) 74,605.00
DIBULATKAN 74,600.00
70. 1 Bh Pasang Kunci Silinder
SNI ~ Kunci Silinder 1.0000 Bh 8,021,000.00 8,021,000.00
2835-2002 ~ Pekerja 0.0050 H/o 107,000.00 535.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0003 H/o 176,000.00 52.80
JUMLAH (Belum PPn) 8,093,892.80
DIBULATKAN 8,093,890.00
71. 1 Bh Pasang Engsel Pintu Ring Nilon
SNI ~ Engsel Pintu Ring Nilon 1.0000 M¹ 45,000.00 45,000.00
2835-2002 ~ Pekerja 0.0150 H/o 107,000.00 1,605.00
~ Tukang 0.1500 H/o 141,500.00 21,225.00
~ Kepala Tukang 0.0150 H/o 155,500.00 2,332.50
~ Mandor 0.0008 H/o 176,000.00 132.00
JUMLAH (Belum PPn) 70,294.50
DIBULATKAN 70,290.00
72. 1 Bh Pasang Engsel Jendela Ring Nilon
SNI ~ Engsel Jendela Ring Nilon 1.0000 M¹ 16,800.00 16,800.00
2835-2002 ~ Pekerja 0.0100 H/o 107,000.00 1,070.00
~ Tukang 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH (Belum PPn) 34,455.00
DIBULATKAN 34,450.00
73. 1 Bh Pasang Grendel Jendela
SNI ~ Kunci Grendel Jendela 1.0000 Bh 23,100.00 23,100.00
2835-2002 ~ Pekerja 0.0500 H/o 107,000.00 5,350.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0025 H/o 176,000.00 440.00
JUMLAH (Belum PPn) 107,415.00
DIBULATKAN 107,410.00
74. 1 Bh Pasang Hak Angin Jendela
SNI ~ Hak Angin Biasa 1.0000 Bh 7,930,800.00 7,930,800.00
2835-2002 ~ Pekerja 0.0500 H/o 107,000.00 5,350.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0025 H/o 176,000.00 440.00
JUMLAH (Belum PPn) 8,015,115.00
DIBULATKAN 8,015,110.00
75. 1 Bh Pasang Door Closer
SNI ~ Dor Closer 1.0000 Bh 11,136,000.00 11,136,000.00
2835-2002 ~ Pekerja 0.0500 H/o 107,000.00 5,350.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0025 H/o 176,000.00 440.00
JUMLAH (Belum PPn) 11,220,315.00
DIBULATKAN 11,220,310.00

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6

# PEKERJAAN KAP dan ATAP

76. 1 M3 Pemasangan Rangka Atap Baja Ringan


~ Main Truss C 2.8000 M1 17,550.00 49,140.00
~ Roof Botton/Reng 5.1000 M1 25,600.00 130,560.00
~ Dynabold 12x120 mm 1.0000 Bh 1,500.00 1,500.00
~ Self Driling Screw Truss Screw 6x20 mm 25.0000 Bh 375.00 9,375.00
~ Self Driling Screw Roof Bottom 4x16 mm 35.0000 Bh 300.00 10,500.00
~ Pekerja 0.2000 H/o 107,000.00 21,400.00
~ Tukang Kayu 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang Kayu 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0010 H/o 176,000.00 176.00
JUMLAH 238,356.00
DIBULATKAN 238,350.00
77. 1 M² Pasang Atap Genteng Roftop
SNI No. 6.32 ~ Atap Roftop 1.0200 Lbr 216,000.00 220,320.00
03-3436-2002 ~ Paku 0.2000 Kg 27,500.00 5,500.00
~ Pekerja 0.2000 H/o 107,000.00 21,400.00
~ Tukang Kayu 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang Kayu 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0010 H/o 176,000.00 176.00
JUMLAH 263,101.00
DIBULATKAN 263,100.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6

78. 1 M' Pasang Nok Genteng Metal


SNI No. 6.36 ~ Nok Genteng Metal 1.1000 Lbr 96,000.00 105,600.00
03-3436-2002 ~ Paku 0.0500 Kg 27,500.00 1,375.00
~ Pekerja 0.2500 H/o 107,000.00 26,750.00
~ Tukang Kayu 0.1500 H/o 141,500.00 21,225.00
~ Kepala Tukang Kayu 0.0150 H/o 155,500.00 2,332.50
~ Mandor 0.0130 H/o 176,000.00 2,288.00
JUMLAH 159,570.50
DIBULATKAN 159,570.00
79. 1 M² Pasang Kaso + Reng Genteng Metal
~ Usuk kayu 5/7 Kayu Besi 0.0140 M³ 0.00 0.00
~ Reng 3/4 Besi 0.0072 M³ 0.00 0.00
~ Paku usuk & reng 0.2500 Kg 27,500.00 6,875.00
~ Pekerja 0.1000 H/o 107,000.00 10,700.00
~ Tukang Kayu 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang Kayu 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 34,160.00
DIBULATKAN 34,160.00
80. 1 M' Pasang Talang Seng
SNI No. 6.36 ~ Talang Seng 0.3 x 0.45 1.0500 Lbr 0.00 0.00
03-3436-2002 ~ Papan Kayu 0.0190 Lbr 5,100,000.00 96,900.00
~ Paku 0.0150 Kg 187,200.00 2,808.00
~ Pekerja 0.2000 H/o 107,000.00 21,400.00
~ Tukang Kayu 0.4000 H/o 141,500.00 56,600.00
~ Kepala Tukang Kayu 0.0250 H/o 155,500.00 3,887.50
~ Mandor 0.0100 H/o 176,000.00 1,760.00
JUMLAH 183,355.50
DIBULATKAN 183,350.00
81. 1 M² Pasang Listplank uk. 2.5 x 20 cm
SNI No. 6.22 ~ Papan Kayu Besi 0.0110 M³ 5,100,000.00 56,100.00
3434-2008 ~ Paku 0.0500 Kg 27,500.00 1,375.00
~ Pekerja 0.1100 H/o 107,000.00 11,770.00
~ Tukang Kayu 0.2200 H/o 141,500.00 31,130.00
~ Kepala Tukang Kayu 0.0220 H/o 155,500.00 3,421.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 104,676.00
DIBULATKAN 104,670.00

# PEKERJAAN PENGECATAN

82. 1 M² Pengecatan Interior Tembok Baru ( 1 lapis plamir,


1 lapis cat dasar, 2 lapis cat penutup)
SNI - 6.14 ~ Plamir tembok 0.1000 Kg 30,000.00 3,000.00
2835-2002 ~ Cat Dasar 0.1000 Kg 125,000.00 12,500.00
~ Cat Penutup 2x 0.2600 Kg 125,000.00 32,500.00
~ Pekerja 0.0200 H/o 107,000.00 2,140.00
~ Tukang Kayu 0.0630 H/o 141,500.00 8,914.50
~ Kepala Tukang 0.0063 H/o 155,500.00 979.65
~ Mandor 0.0030 H/o 176,000.00 528.00
JUMLAH 60,562.15
DIBULATKAN 60,560.00
83. 1 M² Pengecatan Exterior Tembok Baru ( 1 lapis plamir,
1 lapis cat dasar, 2 lapis cat penutup)
~ Plamir tembok 0.1000 Kg 30,000.00 3,000.00
~ Cat Dasar 0.1000 Kg 131,000.00 13,100.00
~ Cat Penutup 2x 0.2600 Kg 131,000.00 34,060.00
~ Pekerja 0.0200 H/o 107,000.00 2,140.00
~ Tukang Kayu 0.0630 H/o 141,500.00 8,914.50
~ Kepala Tukang 0.0063 H/o 155,500.00 979.65
~ Mandor 0.0030 H/o 176,000.00 528.00
JUMLAH 62,722.15
DIBULATKAN 62,720.00
84. 1 M² Pengecatan Bidang kayu Baru (1 lapis palmir,
1 lapis cat dasar, 3 lapis cat penutup)
SNI - 6.9 ~ Cat Menie 0.2000 Kg 30,200.00 6,040.00
2835-2002 ~ Plamir 0.1500 Kg 30,000.00 4,500.00
~ Cat dasar 0.1700 Kg 61,500.00 10,455.00
~ Cat Kilat/Minyak 0.3500 Kg 61,500.00 21,525.00
~ Pekerja 0.0700 H/o 107,000.00 7,490.00
~ Tukang 0.1050 H/o 141,500.00 14,857.50
~ Kepala Tukang 0.0040 H/o 155,500.00 622.00
~ Mandor 0.0025 H/o 176,000.00 440.00
JUMLAH 65,929.50
DIBULATKAN 65,920.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
85. 1 M² Pekerjaan Teak Oil Politur
SNI - 6.9 ~ Teak oil / Politur 0.1500 Ltr 49,000.00 7,350.00
2835-2002 ~ Dempul 0.0500 Kg 30,200.00 1,510.00
~ Amplas 2.0000 Lbr 7,500.00 15,000.00
~ Kuas 0.0100 Bh 9,500.00 95.00
~ Pekerja 0.1600 H/o 107,000.00 17,120.00
~ Tukang Kayu 0.1600 H/o 141,500.00 22,640.00
~ Kepala Tukang Kayu 0.0160 H/o 155,500.00 2,488.00
~ Mandor 0.0025 H/o 176,000.00 440.00
JUMLAH 66,643.00
DIBULATKAN 66,640.00
86. 1 M² Cat Tembok Baru / Kapur
Dinding (3 X Cat)
SNI - 6.9 ~ Plamir 0.1000 Kg 30,000.00 3,000.00
2835-2002 ~ Cat Tembok 0.2600 Kg 26,800.00 6,968.00
~ Pekerja 0.0200 H/o 107,000.00 2,140.00
~ Tukang Kayu 0.0630 H/o 141,500.00 8,914.50
~ Kepala Tukang Kayu 0.0063 H/o 155,500.00 979.65
~ Mandor 0.0030 H/o 176,000.00 528.00
JUMLAH 22,530.15
DIBULATKAN 22,530.00
87. 1 M² Cat Kayu / Kilat Baru (3 X )
Menggosok & Mendempul
SNI - 6.9 ~ Cat Menie 0.2000 Kg 30,200.00 6,040.00
2835-2002 ~ Plamir 0.1500 Kg 30,000.00 4,500.00
~ Cat dasar 0.1700 Kg 30,200.00 5,134.00
~ Cat Kilat/Minyak 0.3500 Kg 61,500.00 21,525.00
~ Pekerja 0.0700 H/o 107,000.00 7,490.00
~ Tukang Kayu 0.1050 H/o 141,500.00 14,857.50
~ Kepala Tukang Kayu 0.0040 H/o 155,500.00 622.00
~ Mandor 0.0025 H/o 176,000.00 440.00
JUMLAH 60,608.50
DIBULATKAN 60,600.00

# PEKERJAAN ELEKTRIKAL

88. 1 TTK DownLight XL 18 Watt Grill Armatur


~ Downlight XL 18W Grill Armatur 1.0000 Set 385,000.00 385,000.00
~ Acsesoris 1.0000 Ls 11,000.00 11,000.00
~ Kabel Listrik 5.0000 M' 17,500.00 87,500.00
~ Pekerja 1.0000 H/o 107,000.00 107,000.00
~ Tukang 1.0000 H/o 141,500.00 141,500.00
~ Kepala Tukang 0.1000 H/o 155,500.00 15,550.00
~ Mandor 0.0500 H/o 176,000.00 8,800.00
JUMLAH 756,350.00
DIBULATKAN 756,350.00
89. 1 TTK Pasang Lampu PLC 18 Watt
~ Lampu PLC 18 Watt 1.0000 Bh 40,000.00 40,000.00
~ Acsesoris 1.0000 Bh 11,000.00 11,000.00
~ Kabel Listrik 5.0000 M' 17,500.00 87,500.00
~ Pekerja 1.0000 H/o 107,000.00 107,000.00
~ Tukang 1.0000 H/o 141,500.00 141,500.00
~ Kepala Tukang 0.1000 H/o 155,500.00 15,550.00
~ Mandor 0.0500 H/o 176,000.00 8,800.00
JUMLAH 411,350.00
DIBULATKAN 411,350.00
90. 1 TTK Pasang Saklar Tunggal
~ Saklar Tunggal 1.0000 Bh 34,500.00 34,500.00
~ Kabel Listrik 5.0000 M' 17,500.00 87,500.00
~ Pipa Kabel Union 1.0000 Btg 28,000.00 28,000.00
~ Pekerja 0.5000 H/o 107,000.00 53,500.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang Listrik 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0250 H/o 176,000.00 4,400.00
JUMLAH 286,425.00
DIBULATKAN 286,420.00

91. 1 TTK Pasang Saklar Double


~ Saklar Double 1.0000 Bh 34,500.00 34,500.00
~ Kabel 5.0000 M' 17,500.00 87,500.00
~ Pipa Kabel Union 1.0000 Btg 28,000.00 28,000.00
~ Pekerja 0.5000 H/o 107,000.00 53,500.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang Listrik 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0250 H/o 176,000.00 4,400.00
JUMLAH 286,425.00
DIBULATKAN 286,420.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
92. 1 Ttk Pasang Stop Kontak
~ Stop Kontak 1.0000 Bh 34,500.00 34,500.00
~ Kabel 5.0000 M 17,500.00 87,500.00
~ Pipa Kabel Union 1.0000 Btg 28,000.00 28,000.00
~ Pekerja 0.5000 H/o 107,000.00 53,500.00
~ Tukang 0.5000 H/o 141,500.00 70,750.00
~ Kepala Tukang Listrik 0.0500 H/o 155,500.00 7,775.00
~ Mandor 0.0250 H/o 176,000.00 4,400.00
JUMLAH 286,425.00
DIBULATKAN 286,420.00

# PEKERJAAN SANITAIR

93. 1 M¹ Memasang PIPA GIP Medium Ø ½"


~ Pipa GIP Medium Ø ½" 1.2000 M¹ 0.00 0.00
~ Aksesoris (35 % dari Harga Bahan) 0.00
~ Pekerja 0.0540 H/o 107,000.00 5,778.00
~ Tukang 0.0900 H/o 141,500.00 12,735.00
~ Kepala Tukang 0.0090 H/o 155,500.00 1,399.50
~ Mandor 0.0270 H/o 176,000.00 4,752.00
JUMLAH 24,664.50
DIBULATKAN 24,660.00
94. 1 M¹ Memasang PIPA GIP Medium Ø ¾"
~ Pipa GIP Medium Ø ¾" 1.2000 M¹ 0.67 0.80
~ Aksesoris (35 % dari Harga Bahan) 0.23
~ Pekerja 0.0540 H/o 107,000.00 5,778.00
~ Tukang 0.0900 H/o 141,500.00 12,735.00
~ Kepala Tukang 0.0090 H/o 155,500.00 1,399.50
~ Mandor 0.0270 H/o 176,000.00 4,752.00
JUMLAH 24,665.53
DIBULATKAN 24,660.00
95. 1 M¹ Memasang Pipa GIP Ø 1"
~ Pipa GIP Ø 1 1.2000 Bh 0.00 0.00
~ Perlengkapan (35% Harga Pipa) 0.3500 0.00
~ Pekerja 0.5400 H/o 107,000.00 57,780.00
~ Tukang 0.0900 H/o 141,500.00 12,735.00
~ Kepala Tukang 0.0900 H/o 155,500.00 13,995.00
~ Mandor 0.0270 H/o 176,000.00 4,752.00
JUMLAH 89,262.00
DIBULATKAN 89,260.00
96. 1 M¹ Memasang Pipa GIP Ø 2"
~ Pipa GIP Ø 2 1.2000 Bh 0.00 0.00
~ Perlengkapan (35% Harga Pipa) 0.3500 0.00
~ Pekerja 0.5400 H/o 107,000.00 57,780.00
~ Tukang 0.0900 H/o 141,500.00 12,735.00
~ Kepala Tukang 0.0900 H/o 155,500.00 13,995.00
~ Mandor 0.0270 H/o 176,000.00 4,752.00
JUMLAH 89,262.00
DIBULATKAN 89,260.00
97. 1 M¹ Memasang Pipa PVC Ø 2" AW
~ Pipa PVC Ø 2 AW 1.2000 Bh 11,250.00 13,500.00
~ Perlengkapan (35% Harga Pipa) 3,937.50
~ Pekerja 0.0810 H/o 107,000.00 8,667.00
~ Tukang 0.1350 H/o 141,500.00 19,102.50
~ Kepala Tukang 0.0135 H/o 155,500.00 2,099.25
~ Mandor 0.0041 H/o 176,000.00 721.60
JUMLAH 48,027.85
DIBULATKAN 48,020.00
98. 1 M¹ Memasang Pipa PVC Ø 2,5" AW
~ Pipa PVC Ø 2,5 AW 1.2000 Bh 0.00 0.00
~ Perlengkapan (35% Harga Pipa) 0.00
~ Pekerja 0.0810 H/o 107,000.00 8,667.00
~ Tukang 0.1350 H/o 141,500.00 19,102.50
~ Kepala Tukang 0.0135 H/o 155,500.00 2,099.25
~ Mandor 0.0041 H/o 176,000.00 721.60
JUMLAH 30,590.35
DIBULATKAN 30,590.00
99. 1 M¹ Memasang Pipa PVC Ø 3" AW
~ Pipa PVC Ø 3 AW 1.2000 Bh 37,500.00 45,000.00
~ Perlengkapan (35% Harga Pipa) 13,125.00
~ Pekerja 0.0810 H/o 107,000.00 8,667.00
~ Tukang 0.1350 H/o 141,500.00 19,102.50
~ Kepala Tukang 0.0135 H/o 155,500.00 2,099.25
~ Mandor 0.0041 H/o 176,000.00 721.60
JUMLAH 88,715.35
DIBULATKAN 88,710.00
100. 1 M¹ Memasang Pipa PVC Ø 4" AW
~ Pipa PVC Ø 4 AW 1.2000 Bh 0.00 0.00
~ Perlengkapan (35% Harga Pipa) 0.00
~ Pekerja 0.0810 H/o 107,000.00 8,667.00
~ Tukang 0.1350 H/o 141,500.00 19,102.50
~ Kepala Tukang 0.0135 H/o 155,500.00 2,099.25
~ Mandor 0.0041 H/o 176,000.00 721.60
JUMLAH 30,590.35
DIBULATKAN 30,590.00
101. 1 Bh Memasang Kloset Jongkok Porselin
~ Kloset Jongkok Porselin 1.0000 Bh 0.00 0.00
~ Semen Portland 6.0000 Kg 99,900.00 599,400.00
~ Pasir Pasang 0.0100 M³ 990,500.00 9,905.00
~ Pekerja 1.0000 H/o 107,000.00 107,000.00
~ Tukang 1.5000 H/o 141,500.00 212,250.00
~ Kepala Tukang 1.5000 H/o 155,500.00 233,250.00
~ Mandor 0.1600 H/o 176,000.00 28,160.00
JUMLAH 1,189,965.00
DIBULATKAN 1,189,960.00
102. 1 Bh Memasang Kloset Duduk/Monoblock
~ Kloset Duduk/Monoblock 1.0000 Bh 0.00 0.00
~ Perlengkapan (6% Harga Bahan) 0.00
~ Pekerja 3.3000 H/o 107,000.00 353,100.00
~ Tukang 1.1000 H/o 141,500.00 155,650.00
~ Kepala Tukang 0.0010 H/o 155,500.00 155.50
~ Mandor 0.1600 H/o 176,000.00 28,160.00
JUMLAH 537,065.50
DIBULATKAN 537,060.00
103. 1 Bh Memasang Urinoir
~ Urinoir 1.000 bh 26,800.00 26,800.00
~ Harga urinoir (Perlengkapan) 0.300 x 1,608.00
~ PC 6.000 kg 99,900.00 599,400.00
~ Pasir pasang 0.010 m3 990,500.00 9,905.00
~ Tukang batu 1.000 org 141,500.00 141,500.00
~ Kepala tukang batu 0.100 org 155,500.00 15,550.00
~ Pekerja 1.000 org 107,000.00 107,000.00
~ Mandor 0.100 org 176,000.00 17,600.00
JUMLAH 919,363.00
DIBULATKAN 919,360.00
104. 1 Bh Memasang Kran Air Ø ½"
~ Kran Air Ø ½" 1.0000 Bh 61,500.00 61,500.00
~ Seal Tape 0.0250 Bh 67,400.00 1,685.00
~ Pekerja 0.0100 H/o 107,000.00 1,070.00
~ Tukang 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 80,840.00
DIBULATKAN 80,840.00
108. 1 Bh Memasang Floor Drain
~ Floor Drain 1.0000 Bh 39,500.00 39,500.00
~ Pekerja 0.0100 H/o 107,000.00 1,070.00
~ Tukang 0.1000 H/o 141,500.00 14,150.00
~ Kepala Tukang 0.0100 H/o 155,500.00 1,555.00
~ Mandor 0.0050 H/o 176,000.00 880.00
JUMLAH 57,155.00
DIBULATKAN 57,150.00
109. 1 Bh Pas. Bak Air Lapis Keramik 80 x 80 x 80 cm
~ Pas. Batu Tela 1 : 3 4.8000 M² 151,620.00 727,776.00
~ Spesi 1 : 2 t.1,5 cm 6.2000 M² 95,710.00 593,402.00
~ Keramik 20/25 cm 3.2000 M² 254,000.00 812,800.00
~ Lantai Kerja 1 : 3 : 5 0.0480 M³ 1,358,370.00 65,201.76
~ Dop Pipa Penguras 1.0000 Bh 81,600.00 81,600.00
~ Pekerja 2.3000 H/o 107,000.00 246,100.00
~ Tukang 3.5000 H/o 141,500.00 495,250.00
~ Kepala Tukang 0.2400 H/o 155,500.00 37,320.00
~ Mandor 0.2400 H/o 176,000.00 42,240.00
JUMLAH 3,101,689.76
DIBULATKAN 3,101,680.00
RENCANA ANGGARAN BIAYA
KEGIATAN : Pembangunan Rumah Mewah
PEKERJAAN : PEMBANGUNAN RUMAH TIPE 120
LOKASI : Jayapura, Papua

HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6

I. PEKERJAAN PERSIAPAN
1. Pek. Pembersihan Lokasi 322.00 M² 19,500.00 6,279,000.00
2. Pek. Pengukuran dan Pemasangan Bouwplank 115.50 M¹ 83,880.00 9,688,140.00
15,967,140.00

JUMLAH I Rp 15,967,140.00
II. PEKERJAAN TANAH
1. Penggalian Tanah Pondasi 46.46 M³ 84,650.00 3,933,177.60
2. Tanah Urugan Hasil Galian Pondasi 34.46 M³ 28,870.00 994,860.20
3. Pasir Urug Bawah Pondasi 2.11 M³ 585,860.00 1,237,336.32
4. Pasir Urug Bawah Lantai 1.52 M³ 585,860.00 890,331.44
5. Penimbunan Pilihan Peninggian Lantai 75.76 M³ 273,860.00 20,746,948.95
6. Pas. Pondasi Footplate 7.92 M³ 1,437,160.00 11,382,307.20
39,184,961.71

JUMLAH II Rp 39,184,961.71
III. PEKERJAAN BETON
1. Pek. Cor Sloof 25 x 20 0.21 M³ 7,426,250.00 1,548,373.13
2. Pek. Cor Kolom 15 x 15 2.06 M³ 7,881,270.00 16,225,564.61
3. Pek. Cor Ring Balok 15 x 20 0.02 M³ 16,893,330.00 339,991.78
4. Pek. Cor Lantai Bawah Keramik 0.91 M³ 2,001,840.00 1,816,910.02
5. Pek. Cor Lantai Dack Beton 11.49 M³ 1,358,370.00 15,607,671.30
6. Pek. Cor Meja Beton Wastafel Zing Aluminium 1.85 M³ 7,843,180.00 14,509,883.00
50,048,393.84

JUMLAH III Rp 50,048,393.84


IV. PEKERJAAN DINDING DAN LANTAI
1. Pek. Pasangan Batu Tela 1 : 4 306.20 M² 151,620.00 46,425,376.87
2. Pek. Plesteran Dinding 1 : 4 167.32 M² 95,710.00 16,014,197.20
3. Pek. Acian Dinding 250.98 M² 45,350.00 11,381,943.00
4. Pek. Lantai Keramik 40 x 40 90.40 M² 895,180.00 80,924,272.00
5. Pek. Tegel Plint Keramik 10 x 40 109.92 M' 110,020.00 12,093,398.40
6. Pek. Lantai Keramik 20 x 20 (KM/WC) 8.00 M² 217,550.00 1,740,400.00
7. Pek. Dinding Keramik 30 x 20 (KM/WC) 9.69 M² 212,590.00 2,059,997.10
8. Pek. List Dinding Keramik 10 x 20 (KM/WC) 24.60 M' 110,020.00 2,706,492.00
173,346,076.57

JUMLAH IV Rp 173,346,076.57
V. PEKERJAAN KAYU, PENGGANTUNG & PENGUNCI
1. Pek. Kusen Pintu, Jendela & Ventilasi Ky. Besi 5/10 0.91 M³ 9,836,020.00 8,950,778.20
2. Pek. Daun Pintu Panil Kayu 14.54 M² 832,450.00 12,099,660.75
3. Pek. Jendela Panil Kaca 15.65 M² 673,400.00 10,535,343.00
4. Pek. Ventilasi Kaca Mati 2.40 M² 83,110.00 199,464.00
5. Pek. Engsel Pintu 24 Psg 70,290.00 1,686,960.00
6. Pek. Engsel Jendela 30 Psg 34,450.00 1,033,500.00
7. Pek. Kunci Pintu Double 2 Bh 74,600.00 149,200.00
8. Pek. Kunci Tanam 2 Slaag 6 Bh 74,600.00 447,600.00
9. Pek. Grendel Jendela 15 Bh 107,410.00 1,611,150.00
10. Pek. Hak Kait Angin 15 Bh 107,315.00 1,609,725.00
38,323,380.95

JUMLAH V Rp 38,323,380.95
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6

VI. PEKERJAAN ATAP & PLAFOND


1. Pek. Rangka Atap Baja Ringan 0.75mm 2.56 M³ 8,396,800.00 21,461,381.12
4. Pek. Atap Multiroof 1.35 M² 263,101.00 355,186.35
5. Pek. Nok Seng Multiroof 22.85 M' 159,570.50 3,646,185.93
6. Pek. Lisplang Ky Besi Papan 2x 2/20 15.86 M² 104,676.00 1,660,161.36
7. Pek. Talang Seng Lapis Papan Kayu 8.24 M' 280,185.00 2,308,724.40
8. Pek. Rangka Plafond Ky. Besi 5 x 5 192.83 M² 162,405.00 31,316,556.15
9. Pek. Plafond Gypsumboard T 9 mm 156.35 M² 158,116.50 24,721,514.78
10. Pek. Plafond Calsiboard t 6 mm 36.48 M² 155,932.50 5,688,417.60
11. Pek. List Gypsumboard t 10 mm 148.91 M' 74,511.00 11,095,433.01
12. Pek. List Kayu Besi t 5 mm 92.59 M' 57,225.50 5,298,509.05
107,552,069.74

JUMLAH VI Rp 107,552,069.74
VII. PEKERJAAN PENGECETAN
1. Pek. Cat Dinding Tembok 306.20 M² 60,560.00 18,543,205.54
2. Pek. Cat Minyak Lisplang Kayu 24.90 M² 65,920.00 1,641,671.68
3. Pek. Cat Minyak Kayu Kusen 28.66 M² 65,920.00 1,888,937.60
4. Pek. Cat Teak Oil/Politur Daun Pintu Kayu + Jendela 245.19 M² 66,640.00 16,339,291.67
5. Pek. Cat Plafond 70.77 M² 22,530.00 1,594,448.10
6. Pek. Cat List Gybsumboard 17.87 M² 22,530.00 402,593.08
7. Pek. Cat Minyak List Kayu 62.26 M² 65,920.00 4,104,179.20
44,514,326.86

JUMLAH VII Rp 44,514,326.86


VIII. PEKERJAAN ELEKTRIKAL
1. Pek. Lampu SL 24 Watt (Down Light) 18.00 Ttik 286,420.00 5,155,560.00
2. Pek. Lampu SL 14 Watt 2.00 Ttik 411,350.00 822,700.00
3. Pek. Saklar Tunggal 5.00 Ttik 286,420.00 1,432,100.00
4. Pek. Saklar Ganda 4.00 Ttik 286,420.00 1,145,680.00
5. Pek. Stop Kontak 8.00 Ttik 286,420.00 2,291,360.00
6. Pek. Kwh/Meteran 1.00 Unit 4,000,000.00 4,000,000.00
14,847,400.00

JUMLAH VIII Rp 14,847,400.00


IX. PEKERJAAN MEKANIKAL & SANITAIR
Pekerjaan Mekanikal
1. Pek. Pipa GIP dia. 1/2" Air Bersih 2.00 M' 24,660.00 49,320.00
2. Pek. Pipa PVC dia. 2" Pembuangan Air Bersih 22.57 M' 48,020.00 1,083,811.40
3. Pek. Pipa PVC dia. 4" Pembuangan Air Kotor 17.88 M' 30,590.00 546,949.20

Pekerjaan Sanitair
1. Pek. Closed Jongkok 2.00 Bh 1,189,960.00 2,379,920.00
2. Klosed Jongkok KIA Standar / Sejenis 2.00 Bh 80,840.00 161,680.00
3. Pek. Kran Air dia. 1/2" 3.00 Bh 93,340.00 280,020.00
4. Pek. Washtafel Zing Aluminium 1.00 Bh 750,000.00 750,000.00
5. Pek. Septictank & Peresapan 1.00 Unit 919,360.00 919,360.00
6,171,060.60

JUMLAH IX Rp 6,171,060.60
X. PEKERJAAN AKHIR
1. Pek. Pembersihan Akhir 1.00 Ls 1,000,000.00
1,000,000.00

JUMLAH X Rp 1,000,000.00

REAL COST Rp 490,954,810.27

PEMBULATAN Rp 490,954,000.00
"REKAPITULASI ANGGARAN BIAYA"
KEGIATAN : Pembangunan Rumah Mewah
PEKERJAAN : PEMBANGUNAN RUMAH TIPE 120
LOKASI : Jayapura, Papua, Indonesia

NO URAIAN PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 15,967,140.00

II. PEKERJAAN TANAH Rp. 39,184,961.71

III. PEKERJAAN BETON Rp. 50,048,393.84

IV. PEKERJAAN DINDING DAN LANTAI Rp. 173,346,076.57

V. PEKERJAAN KAYU, PENGGANTUNG & PENGUNCI Rp. 38,323,380.95

VI. PEKERJAAN ATAP & PLAFOND Rp. 107,552,069.74

VII. PEKERJAAN PENGECETAN Rp. 44,514,326.86

VIII. PEKERJAAN ELEKTRIKAL Rp. 14,847,400.00

IX. PEKERJAAN MEKANIKAL & SANITAIR Rp. 6,171,060.60

X. PEKERJAAN AKHIR Rp. 1,000,000.00

REAL COST : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 490,954,810.27


PAJAK (PPn 10% : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 49,095,481.03
TOTAL COST : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 540,050,291.30

PEMBULATAN : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 540,050,000.00

Terbilang : LIMA RATUS EMPAT PULUH JUTA LIMA PULUH RIBU RUPIAH

Jayapura, …………………2019

MUHAMMAD FARID SAMSUDDIN


Mahasiswa Teknik Sipil - USTJ
URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
I. PEKERJAAN PERSIAPAN
1. Pekerjaan Pembersihan Lokasi

Luas Tanah
P= 34.50
L= 26.50

L= P X L
34.50 x 26.50 914.25 M²
= 914.25

2. Pek. Pengukuran dan Pemasangan Bouwplank

1450

P= 18.50
L= 14.50

K= ((P + 2) x 2) + ((L + 2) x 2)
((18.50 + 2) x 2) + ((14.50 + 2) x 2)
= 41 + 33
= 74 74 M¹
1850
URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
II. PEKERJAAN TANAH DAN PASIR
Panjang Galian Pondasi Horizontal

H13 PH
4.00 H1= 4.00 + 1.00 = 5.00
H12 H2= 7.00 + 1.00 = 8.00
4.00 H10
H11 4.00 H3= 4.00 + 1.00 = 5.00
1.60 H9
H4= 10.50 + 1.00 = 11.50
12.00
H8 H5= 4.00 + 1.00 = 5.00

2.00 H6= 6.50 + 1.00 = 7.50


H7
H6
4.00 H7= 4.00 + 1.00 = 5.00
6.50
H5
H8= 2.00 + 1.00 = 3.00
4.00
H4 H9= 12.00 + 1.00 = 13.00

10.50 H10= 4.00 + 1.00 = 5.00


H3
H11= 1.60 + 1.00 = 2.60
4.00
H2 H12= 4.00 + 1.00 = 5.00
7.00
H13= 4.00 + 1.00 = 5.00
H1 +
4.00 80.60

Panjang Galian Pondasi Vertikal

PV
2.50

V1= 4.00 - 1.00 = 3.00


V8

V2= 6.00 - 2.00 = 4.00


2.50
V7

V3= 8.00 - 3.00 = 5.00


V9

V4= 3.50 - 1.00 = 2.50


9.00

4.90
V10
12.50
V5

V5= 12.50 - 6.00 = 6.50

V6= 2.00 - 1.00 = 1.00


2.00
V6

V7= 2.50 - 2.00 = 0.50


2.00
V11
9.50
V12

V8= 2.50 - 1.00 = 1.50


3.50
V4

V9= 9.00 - 4.00 = 5.00

V10= 4.90 - 2.00 = 2.90

V11= 2.00 - 1.00 = 1.00


4.00

8.00
V1

V3
6.00

V12= 9.50 - 3.00 = 6.50


V2

+
39.40

P Total = PH + PV
6.00

V
V2
= 80.60 + 39.40
= 120.00 M¹

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
II. PEKERJAAN TANAH DAN PASIR
1. Pek. Galian Tanah Pondasi

L= 1.00
T= 0.80
P Total= 120.00

0.80 V= L x T x PT
V= 1.00 x 0.80 x 120.00
= 96.00 96.00 M³

1.00
2. Pek. Urugan Tanah Pondasi

A= 0.23
0.23 B= 0.09
T= 0.55
P Total= 120.00
0.55

V= (((A + B) / 2) x T x 2) x PT
(((0.23 + 0.09) / 2) x 0.55 x 2) x 121
= 0.176 x 120.00
0.09 = 21.12 21.12 M³

3. Pek. Pasir Urug Bawah Pondasi

L= 1.00
T= 0.05
0.05

P Total= 120.00

1.00 V= L x T x PT
= 1.00 x 0.05 x 120.00
= 6.00 6.00 M³

4. Pek. Anstamping/Batu Kosong

L= 1.00
T= 0.20
P Total= 120.00
0.20

V= L x T x PT
= 1.00 x 0.20 x 120.00
1.00 = 24.00 24.00 M³

5. Pek. Pasangan Pondasi Bt.Kali

0.40 A= 0.40
B= 0.80
T= 0.80
P Total= 120.00
0.80

V= (((A + B) / 2) x T ) x PT
(((0.40 + 0.80) / 2) x 0.80) x 121
= 0.48 x 120.00
= 57.60 57.60 M³

0.80
0.8
0.80

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
II. PEKERJAAN TANAH DAN PASIR
Luas Penimbunan Lantai dan Pasir Urug Bawah Lt
1. Teras Depan
(4.00-0.20) x (2.00-0.20)
1450
250 250 150 400 400 3.80 x 1.80 = 6.84
2. Kamar Tidur
K. Tidur Pembantu Gudang (3.00-0.20) x (4.00-0.20)
250

250
± 0.00
17
± 0.00
18 2.80 x 3.80 = 10.64
KM/WC 3. Ruang Tamu

140 110
120 130

16 -0.05 (4.00-0.20) x (4.00-0.20)


250

14
T.Cuci
15 -0.05
13Teras Belakang
- 0.05 3.80 x 3.80 = 14.44
160 240 4. Kamar Tidur Utama
200

10 Dapur
12 (4.00-0.20) x (4.00-0.20)
350

11 K. Tidur
9
-0.02
R. Makan ± 0.00 3.80 x 3.80 = 14.44
200

± 0.00
KM/WC
-0.05
5. KM/WC 1
(2.00-0.20) x (2.00-0.20)
1850

1850

5
200

6 KM/WC
8
-0.05 1.80 x 1.80 = 3.24
350

R. Keluarga 7
Teras Samp. Kiri
- 0.05 ± 0.00 6.
200

4 (2.00-0.20) x (2.00-0.20)
400

K. Tidur Utama
± 0.00 1.80 x 1.80 = 3.24
2 3 7. Ruang Keluarga
400

K. Tidur R. Tamu
± 0.00 - 0.30 (3.50-0.20) x (8.00-0.20)
200

3.30 x 7.80 = 25.74


8. Teras Samping Kiri
1 (2.50-0.20) x (3.50-0.20)
200

200

Teras Depan
- 0.35
2.30 x 3.30 = 7.59
250 300 400 400 9. KM/WC 2
100 1450 (2.00-0.20) x (2.00-0.20)
1.80 x 1.80 = 3.24
10. Dapur
(2.00-0.20) x (6.00-0.20)
1.80 x 5.80 = 10.44
11. Ruang Makan
(4.00-0.20) x (4.00-0.20)
3.80 x 3.80 = 14.44
12. Kamar Tidur
(3.50-0.20) x (4.00-0.20)
3.30 x 3.80 = 12.54
13. Teras Belakang
(1.40-0.20) x (4.00-0.20)
1.20 x 3.80 = 4.56
14.
(2.40-0.20) x (2.50-0.20)
2.20 x 2.30 = 5.06
15. T. Cuci
(1.20-0.20) x (1.60-0.20)
1.00 x 1.40 = 1.40
16. KM/WC 3
(1.30-0.20) x (1.60-0.20)
1.10 x 1.40 = 1.54
17. Kamar Tidur Pembantu
(2.50-0.20) x (2.50-0.20)
2.30 x 2.30 = 5.29
18. Gudang
(1.50-0.20) x (2.50-0.20)
1.30 x 2.30 = 2.99
+
Luas Total = 147.67

6. Pek. Penimbunan Pilihan Penimbunan Lantai


0.45

Penimbunan Tanah Pilihan


T= 0.45
L Total= 147.67

0.45 Penimbunan Tanah Pilihan


V= T x LT
= 0.45 x 147.67
= 66.45 66.45 M³

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
7. Pek. Pasir Urug Bawah Lantai

T= 0.10
L Total= 147.67
0.10

Pasi Urug Bawah Lantai


V= T x LT
= 0.10 x 147.67
= 14.77 14.77 M³

III. PEKERJAAN BETON


Panjang Sloof Horizontal

H13 PH
4.00 H1= 4.00 + 0.20 = 4.20
H12 H2= 7.00 + 0.20 = 7.20
4.00 H10
H11 4.00 H3= 4.00 + 0.20 = 4.20
1.60 H9
H4= 10.50 + 0.20 = 10.70
12.00
H8 H5= 4.00 + 0.20 = 4.20

2.00 H6= 6.50 + 0.20 = 6.70


H7
H6
4.00 H7= 4.00 + 0.20 = 4.20
6.50
H5
H8= 2.00 + 0.20 = 2.20
4.00
H4 H9= 12.00 + 0.20 = 12.20

10.50 H10= 4.00 + 0.20 = 4.20


H3
H11= 1.60 + 0.20 = 1.80
4.00
H2 H12= 4.00 + 0.20 = 4.20
7.00
H13= 4.00 + 0.20 = 4.20
H1 +
4.00 70.20
URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
III. PEKERJAAN BETON
Panjang Sloof Vertikal

PV
2.50

V1= 4.00 - 0.20 = 3.80


V8

V2= 6.00 - 0.40 = 5.60


2.50

V3= 8.00 - 0.80 = 7.20


V7

V9

V4= 3.50 - 0.20 = 3.30


9.00

4.90
V10
12.50
V5

V5= 12.50 - 1.20 = 11.30

V6= 2.00 - 0.20 = 1.80


2.00
V6

V7= 2.50 - 0.40 = 2.10


2.00
V11
9.50
V12

V8= 2.50 - 0.20 = 2.30


3.50
V4

V9= 9.00 - 0.80 = 8.20

V10= 4.90 - 0.40 = 4.50

V11= 2.00 - 0.20 = 1.80


4.00

8.00
V1

V3
6.00

V12= 9.50 - 0.60 = 8.90


V2

+
60.80

P Total = PH + PV
= 70.20 + 60.80
= 131.00 M¹

1. Pek. Cor Sloof 20 x 30

0.20 L= 0.20
T= 0.30
P Total= 131.00

V= L x T x PT
0.30

= 0.20 x 0.30 x 131.00


= 7.86 7.86 M³

2. Pek. Cor Kolom 20 x 20

P= 0.20
L= 0.20
T= 3.35

0.20 Kolom
B. Kolom= 28.00

V= (P x L) x (T x BK)
0.20

= (0.20 x 0.2) x (3.35 x 28)


3.35

= 0.04 x 93.80
0.20 Kolom

0.20

3.35
= 3.75 3.75 M³

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
III. PEKERJAAN BETON
3. Pek. Cor Kolom Praktis 15 x 15
P= 0.15

0.15 L= 0.15
T= 3.35
B. Kolom= 11.00
0.15

V= (P x L) x (T x BK)
= (0.15 x 0.15) x (3.35 x 11)
= 0.02 x 36.85
= 0.83 0.83 M³

Panjang Ring Balok Horizontal PH

H13 H1= 4.00 + 0.15 = 4.15


4.00
H2= 7.00 + 0.15 = 7.15
H12
4.00 H10 H3= 4.00 + 0.15 = 4.15
H11 4.00
1.60 H9 H4= 10.50 + 0.15 = 10.65

12.00 H5= 4.00 + 0.15 = 4.15


H8
2.00 H6= 6.50 + 0.15 = 6.65
H7
H6
8.00 H7= 8.00 + 0.15 = 8.15
6.50
H5 H8= 2.00 + 0.15 = 2.15
4.00
H4 H9= 12.00 + 0.15 = 12.15

10.50 H10= 4.00 + 0.15 = 4.15


H3
4.00 H11= 1.60 + 0.15 = 1.75

H2 H12= 4.00 + 0.15 = 4.15


7.00
H1 H13= 4.00 + 0.15 = 4.15
+
4.00
73.55
Panjang Ring Balok Vertikal PV

V1= 4.00 - 0.15 = 3.85


2.50
V8

V2= 6.00 - 0.30 = 5.70

V3= 8.00 - 0.60 = 7.40


2.50
V7

V9

V4= 3.50 - 0.15 = 3.35


9.00
12.50
V5

V5= 12.50 - 0.90 = 11.60


6.90
V10
2.00

V6= 2.00 - 0.15 = 1.85


V6

2.00
V11
9.50
V12
3.50
V4
9.0
12.50
V5

6.90
V10
2.00
V6

2.00
V11
9.50
V12
V7= 2.50 - 0.30 = 2.20

3.50
V4
V8= 2.50 - 0.15 = 2.35

V9= 9.00 - 0.60 = 8.40

V10= 4.90 - 0.45 = 4.45

8.00
4.00
V1

V3
6.00
V2
V11= 2.00 - 0.15 = 1.85

V12= 9.50 - 0.45 = 9.05


+
62.05

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
III. PEKERJAAN BETON Panjang Total Ring Balok

P Total = PH + PV
= 73.55 + 62.05
= 135.60 M¹
4. Pek. Ring Balok 15 x 20

0.15 L= 0.15
T= 0.20
P Total= 135.60
0.20

V= L x T x PT
= 0.15 x 0.20 x 140.00
= 4.20 4.20 M³

Luas Cor Lantai Bawah Keramik 1. Teras Depan


(4.00-0.14) x (2.00-0.14)
3.86 x 1.86 = 7.18
1450 2. Kamar Tidur
250 250 150 400 400 (3.00-0.14) x (4.00-0.14)
2.86 x 3.86 = 11.04
K. Tidur Pembantu Gudang
3. Ruang Tamu
250

250

± 0.00 ± 0.00
17 18
(4.00-0.14) x (4.00-0.14)
KM/WC
3.86 x 3.86 = 14.90
140 110
120 130

16 -0.05
250

14 4. Kamar Tidur Utama


T.Cuci 13Teras Belakang
15 -0.05 - 0.05 (4.00-0.14) x (4.00-0.14)
160 240
3.86 x 3.86 = 14.90
200

10 Dapur
12
350

-0.02 11 K. Tidur 5. KM/WC 1


R. Makan ± 0.00
9 (2.00-0.14) x (2.00-0.14)
200

KM/WC ± 0.00
-0.05 1.86 x 1.86 = 3.46
1850

1850

5
200

6 KM/WC 6.
-0.05
8 (2.00-0.14) x (2.00-0.14)
350

Teras Samp. Kiri R. Keluarga 7


- 0.05 ± 0.00
1.86 x 1.86 = 3.46
200

4
7. Ruang Keluarga
400

K. Tidur Utama
± 0.00
(3.50-0.14) x (8.00-0.14)
2 3 3.36 x 7.86 = 26.41
400

K. Tidur R. Tamu
- 0.30
± 0.00
8. Teras Samping Kiri
200

(2.50-0.14) x (3.50-0.14)
1 2.36 x 3.36 = 7.93
200
200

Teras Depan
- 0.35 9. KM/WC 2
(2.00-0.14) x (2.00-0.14)
250 300 400 400 1.86 x 1.86 = 3.46
100 1450 10. Dapur
(2.00-0.14) x (6.00-0.14)
1.80 x 5.80 = 10.44
11. Ruang Makan
(4.00-0.14) x (4.00-0.14)
3.86 x 3.86 = 14.90
12. Kamar Tidur
(3.50-0.14) x (4.00-0.14)
3.36 x 3.86 = 12.97
13. Teras Belakang
(1.40-0.14) x (4.00-0.14)
1.26 x 3.86 = 4.86
14.
(2.40-0.14) x (2.50-0.14)
2.26 x 2.36 = 5.33
15. T. Cuci
(1.20-0.14) x (1.60-0.14)
1.06 x 1.46 = 1.55
16. KM/WC 3
(1.30-0.14) x (1.60-0.14)
1.16 x 1.46 = 1.69
17. Kamar Tidur Pembantu
(2.50-0.14) x (2.50-0.14)
2.36 x 2.36 = 5.57
18. Gudang
(1.50-0.14) x (2.50-0.14)
1.36 x 2.36 = 3.21
+
Luas Total = 153.26

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
III. PEKERJAAN BETON
5. Pek. Cor Lantai Bawah Keramik

T= 0.07
L Total= 153.26
0.07

V= T x LT
= 0.07 x 153.26
= 10.73 10.73 M³

6. Pek. Cor Lantai Dack Beton

Luas
1. (4.00-0.15) x (5.00-0.15)
4.00 3.85 x 4.85 = 18.67
2. (1.40-0.15) x (4.00-0.15)
1.25 x 3.85 = 4.81
+
Luas Total = 23.49
5.00

1 T= 0.10
L Total= 23.49
1.40

2
V= T x LT
= 0.10 x 23.49
4.00 4.00 = 2.35 2.35 M³

7. Pek. Cor Meja Beton Wastafel Zing Aluminium

Luas
1. 0.60 x 1.85 = 1.11
Luas Lubang Wastafel
0.37 x 0.42 = 0.16
1 Meja Beton 2
-
0.95
1.85

0.60

3.40
1.20

2. 0.60 x 3.40 = 2.04


0.42

+
0.37 Luas Total = 2.99

0.45 T= 0.10
0.60 L Total= 2.99

V= T x LT
= 0.10 x 2.99
= 0.30 0.30 M³
URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
Panjang Dinding Batu Tela 1 : 4
14.50
2.50 2.50 1.50 4.00 4.00 1. Kamar Tidur
(3.00 + 4.00) + (3.00 + 4.00)
9 10 7.00 + 7.00 = 14.00
2.50

2.50

K. Tidur Pembantu Gudang


± 0.00 ± 0.00 2. Ruang Tamu
4.00 + 4.00
0.90
1.10

4.00 + 4.00 = 8.00


2.50

8
1.40

3. Kamar Tidur Utama


2.40 (2.00 + 4.00) + (2.00 + 4.00)
2.00

Dapur 7 6.00 + 6.00 = 12.00


3.50

-0.02 6 K. Tidur 4. Ruang Keluarga


5 R. Makan ± 0.00
2.00

± 0.00 (1.00 + 3.50) + 1.00


4.50 + 1.00 = 5.50
18.50

18.50
2.00

1.00 200 5. Dapur


4
2.00 + 2.40
3.50

R. Keluarga
± 0.00 2.00 + 2.40 = 4.40
200

3
6. Ruang Makan
4.00

K. Tidur Utama
± 0.00 4.00
1 2 4.00 = 4.00
4.00

K. Tidur R. Tamu
± 0.00 - 0.30 7. Kamar Tidur
2.00

(3.50 + 4.00) + (2.00 + 3.50)


7.50 + 5.50 = 13.00
2.00

2.00

8. 2.50
2.50 = 2.50
9. Kamar Tidur Pembantu
2.50 3.00 4.00 4.00
1.00 (0.90 + 2.50) + (2.50 + 2.50)
14.50
3.40 + 5.00 = 8.40
10. Gudang
(1.50 + 2.50) + 1.50
4.00 + 1.50 = 5.50
+
Dinding Panjang Total = 77.30

T= 3.35
335

P Total= 77.30

Luas Dinding Batu Tela 1 : 4


L= T x PT
= 3.35 x 77.30
= 258.96 M²

Panjang Dinding Batu Tela 1 : 2

1. KM/WC 1
(2.00 + 2.00) + (2.00 + 2.00)
160 4.00 + 4.00 = 8.00
KM/WC
1.30

4 -0.05
T.Cuci
1.20

3 -0.05
1.60
160
KM/WC

1.30
2. KM/WC 2
4 -0.05
T.Cuci (2.00 + 2.00) + (2.00 + 2.00)

1.20
3 -0.05 4.00 + 4.00 = 8.00
1.60 3. T. Cuci
(1.20 + 1.60) + (1.20 + 1.60)
2.80 + 2.80 = 5.60
2 4. KM/WC 3
200
2.00

KM/WC
-0.05 (1.30 + 1.60 ) + 1.30
1 2.90 + 1.30 = 4.20
200

2.00
KM/WC
-0.05 +
Panjang Total = 25.80

T= 3.35
P Total= 25.80

Luas Dinding Batu Tela 1 : 2


L= T x PT
= 3.35 x 25.80
= 86.43 M²

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
Luas Sopi-Sopi 1
Luas Sopi-Sopi

Bidang 1
LB= 9.68
2.27

2 T= 0.44
0.44

L= LB x T
1 = 9.68 x 0.44
9.68 = 4.26 M²

Bidang 2
A= 9.68
T= 2.27

L= 1/2 x A x T
= 1/2 x 9.68 x 2.27
= 10.99 M²

Jumlah= 4.26 + 10.99 = 15.25

Luas Sopi-Sopi 2
Luas Sopi-Sopi

Bidang 1
LB= 4.93
T= 0.95

L= LB x T
2.30

= 4.93 x 0.95
2.89

2 = 4.68 M²
3
0.95

1
0.37

4 Bidang 2
4.93 6.17 A= 4.93
T= 2.30

L= 1/2 x A x T
= 1/2 x 4.93 x 2.30
= 5.67 M²

Bidang 3
A= 6.17
T= 2.89
L= 1/2 x A x T
= 1/2 x 6.17 x 2.89
= 8.92 M²

Bidang 4
LB= 6.17
T= 0.37

L= LB x T
= 6.17 x 0.37
= 2.28 M²

Jumlah= 4.68 + 5.67 + 8.92


+ 2.28 = 21.55

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
Luas Sopi-Sopi 3
Luas Sopi-Sopi

Bidang 1
1.04

LB= 8.40
4 T= 0.37
2.89

2
1.84

3 L= LB x T
= 8.40 x 0.37
1 = 3.11 M²
6.17 2.23
0.37

8.40 Bidang 2
A= 6.17
T= 2.89

L= 1/2 x A x T
= 1/2 x 6.17 x 2.89
= 8.92 M²

Bidang 3
LB= 2.23
T= 1.84

L= LB x T
= 2.23 x 1.84
= 4.10 M²

Bidang 4
A= 2.23
T= 1.04

L= 1/2 x A x T
= 1/2 x 2.23 x 1.04
= 1.16 M²

Jumlah= 3.11 + 8.92 + 4.10


+ 1.16 = 17.29

Luas Sopi-Sopi 4
Luas Sopi-Sopi

Bidang 1
1.09

2
7
LB= 3.70

1.09
T= 0.57

0.57 2 L= LB x T
= 3.70 x 0.57
= 2.11 M²
1
3.70
Bidang 2
A= 3.70
T= 1.09

L= 1/2 x A x T
= 1/2 x 3.70 x 1.09
= 2.02 M²

Jumlah= 2.11 + 2.02 = 4.13

Jumlah Luas Total Sopi-Sopi =


15.25 + 21.55 + 17.29
+ 4.13 = 58.21

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
Luas Pintu P1 = 3 BH

LB= 1.30
T= 2.15
B. Pintu= 3.00
2.15

L= LB x T x BP
= 1.30 x 2.15 x 3.00
= 8.39 M²

1.30
Luas Pintu P2 = 6 BH

LB= 0.90
T= 2.15
B. Pintu= 6.00
2.15

L= LB x T x BP
= 0.90 x 2.15 x 6.00
= 11.61 M²

0.90
Luas Pintu P3 = 4 BH

LB= 0.70
T= 2.15
B. Pintu= 4.00
2.15

L= LB x T x BP
= 0.70 x 2.15 x 4.00
= 6.02 M²

0.70
Luas Jendela J1 = 6 BH

LB= 0.60
T= 1.85
1.85

B. Jendela= 6.00
1.85
L= LB x T x BJ
= 0.60 x 1.85 x 6.00
= 6.66 M²

0.60
Luas Jendela J2 = 1 BH

LB= 0.80
T= 1.45

1.45
B. Jendela= 1.00

L= LB x T x BJ
= 0.80 x 1.45 x 1.00
= 1.16 M²
0.80
Luas Jendela J3 = 5 BH

LB= 1.55
T= 1.45
1.45

B. Jendela= 5.00

L= LB x T x BJ
= 1.55 x 1.45 x 5.00
= 11.24 M²
1.55

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
Luas Ventilasi V1 = 5 BH
0.40

LB= 0.60
T= 0.40
B. Ventilasi= 5.00

L= LB x T x BV
= 0.60 x 0.40 x 5.00

0.60
= 1.20

Luas Ventilasi V2 = 32 BH

LB= 0.30
0.40

T= 0.40
B. Ventilasi= 32.00

L= LB x T x BV
= 0.30 x 0.40 x 32.00
= 3.84 M²

0.30
1. Pek. Pasangan Batu Tela 1 : 4 (Dinding Biasa)

Luas Dinding 1 : 4 = 258.96


Luas Dinding Sopi" = 58.21
Luas Kusen = 43.13

L= (Luas Dinding 1 : 4 + Luas Dinding


Sopi-Sopi) - Luas Kusen
= 258.96 + 58.21 - 43.13
= 274.03 274.03 M²

2. Pek. Pasangan Batu Tela 1 : 2 (Dinding Terasram)

Luas Dinding 1 : 2 = 86.43


Luas Kusen = 6.98
L= Luas Dinding 1 : 2 - Luas Kusen
= 86.43 - 6.98
= 79.45 79.45 M²

3. Pek. Plesteran Dinding 1 : 4 (Plesteran Biasa)

Luas Total Dinding 1 : 4 = ###

L= Luas Dinding 1 : 4 x 2 Sisi

= 274.03 x 2.00
= 548.06 548.06 M²

4. Pek. Plesteran Dinding 1 : 2 (Plesteran Terasram)

Luas Total Dinding 1 : 2 = ###

L= Luas Dinding 1 : 2 x 2 Sisi


= 79.45 x 2.00
= 158.90 158.90 M²

5. Pek. Acian Dinding

Luas Plesteran Dinding 1 : 4 = 548.06


Luas Plesteran Dinding 1 : 2 = 158.90

L= L Plesteran 1 : 4 + L Plesteran 1 : 2
= 548.06 + 158.90
= 706.96 706.96 M²

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
6. Pek. Lantai Keramik 40 x 40 Luas Lantai Keramik 40 x 40

1. Teras Depan
14.50 2.00 x 4.00 = 8.00
2.50 2.50 1.50 4.00 4.00 2. Kamar Tidur
3.00 x 4.00 = 12.00
2.50

2.50

13 14 3. Ruang Tamu
4.00 x 4.00 = 16.00
1.10

4. Kamar Tidur Utama


1.30

20 x 20
2.50

-0.05
12 40 x 40 4.00 x 4.00 = 16.00
1.40
1.20

20 x 20 11 -0.05
-0.05
5. 2.00 x 2.00 = 4.00
1.60 2.40
2.00 2.00

9
6. Ruang Keluarga
3.50

40 x 40
10 40 x 40 3.50 x 8.00 = 28.00
8 ± 0.00 ± 0.00
20 x 20 7. Teras Samping Kiri
-0.05
8.75
18.50

18.50

2.50 x 3.50 =
2.00

20 x 20
5 8. Dapur
7 6 -0.05
3.50

40 x 40
-0.05
40 x 40
± 0.00
2.00 x 6.00 = 12.00
4 9. Ruang Makan
4.00

40 x 40
± 0.00 4.00 x 4.00 = 16.00
2 3
10. Kamar Tidur
4.00

40 x 40 40 x 40 3.50 x 4.00 = 14.00


2.00 2.00

± 0.00 -0.30
11. Teras Belakang
1.40 x 4.00 = 5.60
2.00

1 40 x 40
12. 2.40 x 2.50 = 6.00
-0.35
13. Kamar Tidur Pembantu
2.50 3.00 4.00 4.00 2.50 x 2.50 = 6.25
1.00 14.50 14. Gudang
1.50 x 2.50 = 3.75
+
Luas Total = 156.35 156.35 M²

7. Pek. Tegel Plint Keramik 10 x 40 Panjang List Plint Keramik 10 x 40

1. Teras Depan
14.50 4.00 - 1.30 = 2.70
2.50 2.50 1.50 4.00 4.00 2. Kamar Tidur
2.50
2.50

13 14
1.10
1.30

20 x 20
2.50

-0.05
12 40 x 40
1.40
1.20

20 x 20 11 -0.05
-0.05
14.50
2.50 2.50 1.50 4.00 4.00
(3.00 + 4.00 + 3.00 + 4.00) - 0.9

2.50
2.50
13 14 14.00 - 0.90 = 13.10
3. Ruang Tamu

1.10
1.30
20 x 20
(4.00 + 4.00 + 4.00 + 4.00) - 1.30
2.50
-0.05
12 40 x 40

1.40
16.00 - 1.30 = 14.70
1.20
20 x 20 11 -0.05
-0.05
1.60 2.40 4. Kamar Tidur Utama
2.00 2.00

9 (4.00 + 4.00 + 4.00 + 4.00) - 0.9

3.50
10 40 x 40
8
40 x 40
± 0.00 ± 0.00 16.00 - 0.90 = 15.10
20 x 20 5. (2.00 + 2.00 + 2.00) - 2.5
-0.05
18.50

18.50
6.00 - 2.50 = 3.50

2.00
20 x 20
5
7 6 -0.05 6. Ruang Keluarga
3.50

40 x 40 40 x 40
-0.05 ± 0.00 (2.00 + 4.00 + 3.50 + 3.00) - 2.2
4 12.50 - 2.20 = 10.30

4.00
40 x 40
± 0.00 7. Teras Samping Kiri
2 3 3.50 - 1.30 = 2.20
4.00

40 x 40 40 x 40
8. Dapur

2.00 2.00
± 0.00 -0.30
(2.00 + 4.00 + 4.00 + 1.00) - 0.7
11.00 - 0.70 = 10.30
2.00

1 40 x 40
-0.35 9. Ruang Makan
(4.00 + 3.50) - 1.30
2.50 3.00 4.00 4.00 7.50 - 1.30 = 6.20
1.00 14.50 10. Kamar Tidur
(3.50 + 4.00 + 3.50 + 4.00) - 0.9
15.00 - 0.90 = 14.10
11. Teras Belakang
(4.00 + 1.40) - 2.2
5.40 - 2.20 = 3.20
12. (2.40 + 2.50 + 2.40 +2.50) - 4.1
9.80 - 4.10 = 5.70
13. Kamar Tidur Pembantu
(2.50 + 2.50 + 2.50 + 2.50) - 0.9
10.00 - 0.90 = 9.10

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
14. Gudang
(1.50 + 2.50 + 1.50 + 2.50) - 0.9
8.00 - 0.90 = 7.10
+
Panjang Total 117.30 117.30 M¹

8. Pek. Lantai Keramik 20 x 20 (KM/WC)


Luas Lantai Keramik KM/WC 1
Luas KM/WC 1

P= 2.00
L= 2.00
2.00

Lantai Keramik
20 x 20
-0.05
L= P x L
= 2.00 x 2.00
= 4.00 M²

2.00
Luas Lantai Keramik KM/WC 2
Luas KM/WC 2

2.00 P= 2.00
L= 2.00
2.00

Lantai Keramik
20 x 20 L= P x L
-0.05
= 2.00 x 2.00
= 4.00 M²
Luas Lantai Keramik KM/WC 3 dan T Cuci
Luas KM/WC 3

P= 1.60
L= 1.30

1.30 L= P x L
KM/WC = 1.60 x 1.30
-0.05 = 2.08 M²

Luas T Cuci
T.Cuci
1.20

P= 1.60
-0.05 L= 1.20

L= P x L
1.60 = 1.60 x 1.20
= 1.92 M²

Luas Total Keramik 20 x 20 =


= (KM 1 + KM 2) + (KM 3 + T. CUCI)
= (4.00 + 4.00) + (2.08 + 1.92)
= 8.00 + 4.00
= 12.00 12.00 M²

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
IV. PEKERJAAN DINDING DAN LANTAI
9. Pek. Dinding Keramik 20 x 25 (KM/WC)
Panjang Dinding KM/WC 1

Panjang Dinding Keramik


= (2-0.14)x2) + (2-0.14)x 2)-0.7
= 3.72 + 3.02 = 6.74

Panjang Dinding KM/WC 2

Panjang Dinding Keramik


1.40 0.10

= (2-0.14)x2) + (2-0.14)x 2)-0.7


= 3.72 + 3.02 = 6.74

Panjang Dinding KM/WC 3

Panjang Dinding Keramik


= (1.3-0.14)x2) + (1.6-0.14)x 2)-0.7
= 2.32 + 2.22 = 4.54
2.00
Panjang Dinding T. Cuci

Panjang Dinding Keramik


= (1.2-0.14)x2) + (1.6-0.14)x 2)-0.7
= 2.12 + 2.22 = 4.34
+
Panjang Total 22.36

Panjang Total Keramik Dinding 20 x 25 22.36


Tinggi Keramik = 1.40
L= PK x T
= 22.36 x 1.40
= 31.30 31.30 M²

10. Pek. List Dinding Keramik 10 x 20 (KM/WC)

Panjang Total Keramik Dinding 10 x 20 22.36

K= 22.36 22.36 M¹

11. Pek. Keramik 20 x 20 (Meja Beton)

Luas
1. 0.70 x 1.85 = 1.30
Luas Wastafel
1 Meja Keramik 2 0.37 x 1.20 = 0.44
20 x 20
-
1.85

3.40 0.60
0.85
1.20

2. 0.70 x 3.40 = 2.38


0.37 Luas Total = 3.23
+
3.23 M²
0.45
0.60

URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SATUAN
PEKERJAAN KAYU, PENGANTUNG DAN
V. PENGUNCI
1. Pek. Kusen Pintu, Jendela & Ventilasi Ky. Besi 5/10
URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN PERHITUNGAN VOL SAT
I. PEKERJAAN PERSIAPAN
1 Pekerjaan pembersihan

Luas Tanah 322 M²

P= 23.00
L= 14.00

L= P x L
23 x 14

L= 322 M²

2 Pek & Pemasangan Bouwplank

h= 50.50
v= 65.00

115.50 M¹
h+v 50.50
65.00 +
115.50

URAIAN PEKERJAAN
II. PEKERJAAN TANAH & PASIR
1. Panjang Galian Horizontal

Ph

H= 0.60 + 0.60 = 1.20


22 x 1.20
= 26.40 26.40 M¹
URAIAN PEKERJAAN
II. PEKERJAAN TANAH & PASIR
2. Panjang Galian Vertikal

Pv

V= 0.60 + 0.60 = 1.20


22 x 1.20
= 26.40

Tp= Ph + Pv 52.80 M¹
26.40 + 26.40
Tp= 52.80

1 Pek Galian Tanah Pondasi

L= 0.80 46.46 M³
T= 1.10
Tp= 52.80
110

V= L x T x Tp
0,80 x 1,10 x 52,80
V= 46.46 M³

80
2 Pek Pasir Urug Bawah Pondasi

L= 0.80
T= 0.05
Tp= 52.80
110

V= L x T x Tp
0,80 x 0,05 x 52,80
V= 2.11 M³ 2.11 M³
5

80
URAIAN PEKERJAAN
II. PEKERJAAN PANJANG PONDASI FOOTPLATE
3. Panjang Galian Horizontal
Ph

h1= 0.60 + 0.80 = 1.40 +


22 X 1.40
= 30.80

30.80 M¹

4. Panjang Galian Vertikal


Pv

v1= 0.60 + 0.80 = 1.40 +


22 X 1.40
= 30.80

61.60 M¹

Tp= Ph + Pv
30.80 + 30.80
Tp= 61.60 M¹

5. Pek Pasangan Pondasi Batu Kali

20
La= 0.20
Lb= 0.60 8.80 M³
T= 1.00
100

BP= 22

V= La + Lb x T x BP
2
20

V= 0,20+0,60 x 1,00 x 22
2
V= 8.80

60
URAIAN PEKERJAAN
6. Pek Urugan Tanah Pondasi

30 30 V. Pondasi - (V. Urug bawah + V. Batu Kali)

46,46 - (3,20 + 8,80)

20 65
= 46,46 - 12
= 34.46 M³ 34.46 M³

15
10

II
7. Luas Penimbunan Lantai dan Pasir Urug Bawah Lt 1.) Teras
3,50 x 1,50 x 0,28
= 1.47 M²
2.) Ruang Tamu
3,00 x 3,00 x 0,28
= 2.52 M²
3.) Kamar Tidur Utama
5,00 x 4,00 x 0,28
= 5.60 M²
Teras Belakang
4.) KM/WC (Kamar mandi di dalam kamar tidur utama)
±0.00 2,00 x 2,00 x 0,28
Dapur
±0.00
= 1.12 M²
5.) Taman belakang
Kamar Utama
±0.00 2,00 x 1,80 x 0,28
= 1.01 M²
6.) Ruang makan & ruang keuarga
Ruang makan/Ruang 4,10 x 4,00 x 0,28
Keluarga
±0.00 = 4.59 M²
Km/wc Km/wc
±0.05 ±0.05 7.) Dapur
3,40 x 2,00 x 0,28
= 1.90 M²
8.) Kamar tidur I
Kamar
Kamar Tidur 4,00 x 4,00 x 0,28 30.39 M²
Tidur ±0.00
±0.00 = 4.48 M²
9.) KM/WC Umum
1,50 x 2,00 x 0,28
Ruang Tamu
±0.00 = 0.84 M²
Garasi 10.) Kamar tidur II
±0.03
3,00 x 3,50 x 0,28
Teras = 2.94 M²
±0.03
11.) Garasi
4,00 x 3,50 x 0,28
= 3.92 M²

Luas Total = 30.39 M²


URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN PERHITUNGAN VOL SAT
II. PEKERJAAN TANAH DAN PASIR
8. Pek Pasir Urug di atas lantai

T= 0.05
L Total= 30.39

V= T x LT
= 0.05 x 30.39
= 1.52 1.52 M²

URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN PERHITUNGAN VOL SAT
III.PEKERJAAN BETON
1. Panjang Sloof Horizontal PH

h1= 8.00 x 0.05 = 0.40


h2= 2.00 x 0.05 = 0.10
h3= 2.00 x 0.05 = 0.10
h4= 4.00 x 0.05 = 0.20
h5= 3.00 x 0.05 = 0.15
h6= 3.50 x 0.05 = 0.18
h7= 3.50 x 0.05 = 0.18
h8= 3.00 x 0.05 = 0.15
h9= 3.50 x 0.05 = 0.18 +
1.63 1.63 M³

URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN PERHITUNGAN VOL SAT
III.PEKERJAAN BETON
2. Panjang Sloof Vertikal PV

v1= 11.00 x 0.05 = 0.55


v2= 2.50 x 0.05 = 0.13
v3= 3.40 x 0.05 = 0.17
v4= 3.50 x 0.05 = 0.18
v5= 13.50 x 0.05 = 0.68
v6= 2.00 x 0.05 = 0.10
v7= 15.00 x 0.05 = 0.75 +
2.55

Tp= Ph + Pv
1.63 + 2.55
Tp= 4.17 4.17 M³
URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN PERHITUNGAN VOL SAT
III.PEKERJAAN BETON
1 Pek Cor Sloof 20 x 25
L= 0.20
T= 0.25
P Total= 4.17

V= L x T x PT
= 0.20 x 0.25 x 4.17
25 = 0.21 M³

0.21 M³

2. Pek. Cor Kolom 15 x 15

Kolom
15

P= 0.15 2.06 M³
L= 0.15
T= 3.66
B. Kolom= 25.00
366

V= (P x L) x (T x BK)
= (0,15 x 0,15) x (3,66 x 25)
= 0.0225 x 91.5
= 2.06 M³
Tinggi Dinding

URAIAN PEKERJAAN
3. Panjang Ring Balok Horizontal PERHITUNGAN VOL SAT

Ph

h1= 8.00 x 0.03 = 0.24


h2= 2.00 x 0.03 = 0.06
h3= 2.00 x 0.03 = 0.06
h4= 4.00 x 0.03 = 0.12
h5= 3.00 x 0.03 = 0.09 1.08 M³
h6= 3.50 x 0.03 = 0.11
h7= 3.50 x 0.03 = 0.11
h8= 3.00 x 0.03 = 0.09
h9= 3.50 x 0.03 = 0.11
h10= 3.50 x 0.03 = 0.11 +
1.08
URAIAN PEKERJAAN
PEKERJAAN BETON PERHITUNGAN VOL SAT
4. Panjang Ring Balok Vertikal
Pv

v1= 11.00 x 0.03 = 0.33


v2= 3.40 x 0.03 = 0.10
v3= 3.50 x 0.03 = 0.11
v4= 2.50 x 0.03 = 0.08
v5= 1.37 x 0.03 = 0.04
v6= 13.50 x 0.03 = 0.41
v7= 2.00 x 0.03 = 0.06
v8= 15.00 x 0.03 = 0.45 +
1.12
1.12 M³

Tp= Ph + Pv
+ 1.12
Tp= 1.12

5. Panjang Ring Balok 12 x 15 PERHITUNGAN

T= 0.15
L= 0.12
P Tot = 1.12

V= T x L x P Tot 0.02 M³
= 0.15 x 0.12 x 2,20
0.02 M³

URAIAN PEKERJAAN
6. Luas Cor Bawah Lantai Keramik PEHITUNGAN VOL SAT

1.) Teras
3,50 x 1,50 x 0,12
Teras Belakang = 0.63 M²
±0.00
180

2.) Ruang Tamu


Dapur
±0.00 3,00 x 3,50 x 0,12
Kamar Utama = 1.26 M²
±0.00
3.) Kamar Tidur Utama
5,00 x 4,00 x 0,12
= 2.40 M²
Ruang makan/Ruang
Keluarga 4.) KM/WC (Kamar mandi di dalam kamar tidur utama)
±0.00
Km/wc
±0.05
K m/wc
±0.05
2,00 x 2,00 x 0,12
150
300 = 0.48 M²
200
5.) Taman belakang
2,00 x 1,80 x 0,12
Kamar = 0.43 M²
Kamar Tidur
Tidur
±0.00
±0.00 6.) Ruang Makan & ruang keuarga
4,10 x 4,00 x 0,12
= 1.97 M²
Ruang Tamu
±0.00
7.) Dapur 11.) Garasi
3,40 x 2,00 x 0,12 4,00 x 3,50 x 0,12
Garasi
±0.03 = 0.816 M² = 1.68 M² 12.97 M²
8.) Kamar tidur I
Teras
±0.03 4,00 x 3,50 x 0,12
= 1.68 M²
9.) KM/WC Umum
2,00 x 1,50 x 0,12
= 0.36 M²
10.) Kamar tidur II Luas Total = 12.97 M²
3,00 x 3,50 x 0,12
= 1.26 M²
URAIAN PEKERJAAN
PEKERJAAN BETON PERHITUNGAN VOL SAT
7. Pek Cor Lantai Bawah Keramik
T= 0.07
LT= 12.97 0.91 M³

V= T x LT
0.07

= 0.07 x 12.97
= 0.90762 M³

URAIAN PEKERJAAN
IV PEKERJAAN DINDING & LANTAI
1. Panjang Dinding Batu Tela 1 : 4 PH
h1= 8.00 - 0.24 = 7.76
h2= 2.00 - 0.24 = 1.76
h3= 2.00 - 0.12 = 1.88
h4= 4.00 - 0.24 = 3.76
h5= 3.00 - 0.24 = 2.76
h6= 3.00 - 0.24 = 2.76
h7= 3.50 - 0.24 = 3.26
h8= 3.50 - 0.12 = 3.38
h9= 3.50 - 0.24 = 3.26 33.84 M³
h10= 3.50 - 0.24 = 3.26 +
33.84

2. Panjang Dinding Batu Tela 1 : 4


Pv
v1= 15.00 - 0.12 = 14.88
v2= 2.00 - 0.12 = 1.88
v3= 13.50 - 0.12 = 13.38
v4= 3.50 - 0.12 = 3.38
v5= 3.40 - 0.12 = 3.28 49.82 M³
v6= 2.50 - 0.36 = 2.14
v7= 11.00 - 0.12 = 10.88 +
49.82

Panjang Total Dinding 1 : 4


P Total = PH + PV
= 33.84 + 49.82
= 83.66 M³ 83.66 M³

T= 3.66
P Total= 83.66

Luas Dinding Batu Tela 1 : 4


L= T x PT
= 3.66 x 83.66
= 306.20 M² 306.20 M³
366
V. PEKERJAAN KAYU, PENGANTUNG DAN VOL SAT
PERHITUNGAN
PENGUNCI
1. Panjang Kusen & Luas Pintu P1
Kusen

2.15 + 1.8 + 2.15 = 6.10 6.10 M¹

Daun pintu

215
0.9 x 2.1 = 1.89 1.89 M¹

2 pintu

2 x 1.89 = 3.78 3.78 M¹

2. Panjang Kusen & Luas Pintu P2 = 3 buah PERHITUNGAN VOL SAT

Kusen
2.15 + 0.8 + 2.15 = 5.10 15.30 M¹

Kusen x Jumlah Kusen P2


= 5.10 x 3
215

= 15.3

Daun pintu
0.8 x 2.1 = 1.68 5.04 M¹

Daun pintu x Jumlah Pintu P2


= 1.68 x 3
80 = 5.04

3. Panjang Kusen & Luas Pintu P3 = 2 Pintu PERHITUNGAN VOL SAT

Kusen
2.10 + 0.66 + 2.10 = 4.86

Kusen x Jumlah kusen P3


= 4.86 x 2
= 9.72 9.72 M¹
215

Daun pintu

0.6 x 2.05 = 1.23 2.46 M¹

Daun pintu x Jumlah Pintu P3


= 1.23 x 2.00
= 2.46
URAIAN PEKERJAAN
V. PEKERJAAN KAYU, PENGANTUNG DAN VOL SAT
PERHITUNGAN
PENGUNCI
4. Panjang Kusen & Luas Jendela J1 = 6 Jendela Kusen
1.35 + 1.6 + 1.35 + 1.60
+ 1.35 = 7.25
43.50 M¹
Kusen x Jumlah kusen J1
= 7.25 x 6
= 43.5

135
1 Daun jendela
0.7 x 1.25 = 0.875 0.875 M¹

2 Jendela
2 x 0.875 = 1.75 10.5 M¹

2 Jendela x Jumlah Jendela J1


160 = 1.75 6
= 10.5

5. Panjang Kusen & Luas PJendela 1 = 1 PJ PERHITUNGAN VOL SAT


Kusen Pintu
2.15 + 0.85 + 2.15 = 5.15

Kusen Jendela
1.25 + 0.8 + 1.25 + 0.8 9.25 M¹
= 4.1
125

= 9.25 x 1
= 9.25
215

Daun Pintu
0.75 x 2.1 = 1.575 2.38 M¹

Daun jendela
0.7 x 1.15 = 0.805

PJ x Jumlah PJ1
= 2.38 x 1
= 2.38
160
6. Panjang Kusen & Luas PJ 2 = 1 PJ PERHITUNGAN VOL SAT
Kusen Pintu
2.15 + 0.9 + 2.15 = 5.2

Kusen Jendela
1.55 + 1.25 + 1.55 + 1.25 12.05 M¹
+ 1.25 = 6.85

Kusen PJ2 x Jumlah Kusen PJ2

125
= 12.05 1
= 12.05
215

Daun Pintu
0.8 x 2.1 = 1.68

2 Daun Jendela
0.70 x 1.15 x 2
= 2
3.29 M¹
PJ2 x Jumlah PJ2
= 3.29 x 1
= 3

URAIAN PEKERJAAN
V. PEKERJAAN KAYU, PENGANTUNG DAN VOL SAT
PERHITUNGAN
PENGUNCI
7. Panjang Kusen & Luas Ventilasi V2 = 17

Ventilasi Jumlah 2 ventilasi

0.32 Ventilasi 18.7 M¹


0.23 = 1.1 x 17
0.32 = 18.7
32

0.23 +
1.1

URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN VOL SAT
PERHITUNGAN
IV. PEKERJAAN DINDING DAN LANTAI
1 Pek. Lantai Keramik 40 x 40
1.) Teras
400 200 200 2.) Ruang Tamu
3.) Kamar Tidur Utama
4.) Ruang Makan & ruang keuarga
340

5.) Dapur
500

6.) Kamar tidur I


7.) Kamar tidur II 90.40 M¹
410

1.) 1.50 x 4.65 = 6.98


2.) 4.65 x 2.50 = 11.63
400

350

3.) 5.00 x 4.00 = 20.00


4.) 4.10 x 5.00 = 20.50
5.) 2.00 x 3.40 = 6.80
6.) 3.50 x 4.00 = 14.00
250

7.) 3.00 x 3.50 = 10.50 +


90.40
150

350 465
2 Pek. Lantai Keramik 20 x 20 PERHITUNGAN VOL SAT
400 200 200

340
500
1.) KM/WC (Kamar mandi di dalam kamar tidur utama)
200
2.) KM/WC Umum

410
200
8.00 M¹
1.) 2.00 x 2.00 = 4.00
400

350
2.) 2.00 x 2.00 = 4.00 +
8.00

350 465 250


150

URAIAN PEKERJAAN
NO GAMBAR & JENIS PEKERJAAN VOL SAT
PERHITUNGAN
IV. PEKERJAAN DINDING DAN LANTAI
3. Luas Top Gavel
Luas Sopi-Sopi
35.70 M³
Bidang
349

A= 10.23
T= 3.49

1023 L= 1/2 x A x T x 2
= 1/2 x 10.23 x 3.49 x2
= 35.70
10.. Pek. Pasangan Batu Tela 1 : 4 (Dinding Biasa)
Luas = Luas Pintu + Jendela + Ventilasi
P1= 3.87
P2= 1.72
P3= 1.51
J1= 2.16
PJ1= 3.07 100.91 M²
PJ2= 3.07
V1= 3.07 +
18.45 M²

Luas Dinding 1 : 4 = 83.66


Luas Dinding Sopi" = 35.70
Luas Kusen = 18.45

L= (Luas Dinding 1 : 4 + Luas Dinding


Sopi-Sopi) - Luas Kusen
= 83.66 + 35.70 - 18.45
= 100.91 M²
11.. Pek. Pasangan Batu Tela 1 : 2 (Dinding Terasram)
Luas = Luas Pintu
P1= 3.87
P2= 1.72
P3= 1.51
J1= 2.16
PJ1= 1.57 29.33 M²
PJ2= 1.68 +
12.51 M²

Luas Dinding 1 : 2 = 41.83


Luas Kusen = 12.51

L= Luas Dinding 1 : 2 - Luas Kusen


= 41.83 - 12.51
= 29.33 M²

12. Pek. Plesteran Dinding 1 : 4 (Plesteran Biasa)


Luas Total Dinding 1 : 4 = 83.66

L= Luas Dinding 1 : 4 x 2 Sisi


= 83.66 x 2.00
= 167.32 M² 167.32 M²
13. Pek. Plesteran Dinding 1 : 2 (Plesteran Terasram)

Luas Total Dinding 1 : 2 = 41.83

L= Luas Dinding 1 : 2 x 2 Sisi


= 41.83 x 2.00
= 83.66 M² 83.66 M²

14. Pek. Acian Dinding


Luas Plesteran Dinding 1 : 4 = 167.32
Luas Plesteran Dinding 1 : 2 = 83.66

L= L Plesteran 1 : 4 + L Plesteran 1 : 2
= 167.32 + 83.66
= 250.98 M² 250.98 M²
NO URAIAN PEKERJAAN
V. PEKERJAAN SENG PERHITUNGAN VOL SAT

915 bidang 1 bidang 2


La= 9.15 La= 3.96
Lb= 6 Lb= 4.68
T= 6 T= 4
L= La + Lb X T X 2 Buah L= La + Lb X T X 2 Buah
2
= 181.8 M³ = 34.56 M³
1145

bidang 3
La= 6.65 234.9979 M³
Lb= 4.68
T= 3.29
L= La + Lb X T
2
400

= 18.638 M³

L= B1+B2+B3

L = 1205.49+ 189.47+18,64
L= 235.00 M³

665
NO URAIAN PEKERJAAN
GAMBAR DAN JENIS PEKERJAAN
VI. PEKERJAAN ATAP

502
319

250
250

192
192
134

134
77

77

1131
PERHITUNGAN VOL SAT

Jumlah besi di kuda-kuda 11.31


6.77
6.77
5.02
0.77
1.21
0.77
1.21
1.62
1.34
1.62
1.34
1.92
2.14
1.92
2.14
2.5
2.69
3.19
2.5
2.69 +
61.44 122.88 M¹

Ukuran atap sisi kuda-kuda yang lain sama = Jumlah x 2 depan belakang
= 61.44 x 2
= 122.88
URAIAN PEKERJAAN
VI. GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOL SAT
PEKERJAAN ATAP DAN PLAFOND
LUAS = LUASAN LANTAI (Luas lantai WC+Luas lantai)
TP= 70.77

B= 0.05
H= 0.05
0.18 M³

V= TP x B x H
V= 175.30 x 0.05 x 0.05
V= 0.18 M³

1537

Panjang Nok Seng Plat BJLS


Panjang = 32.15 M¹ 32.15 M¹

Luas Atap Seng

Luas Atap Seng

915

P Seng= 11.41
L= 9.15 (Lihat Kuda" K1) 62.26 M²

P seng= 6.61
L= 3.96 (Lihat Kuda" K2)
1141

L= 11,41x2+9,15x2+6,61x2+3,96x2
= 62.26
396

661
URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SAT
VII. PEKERJAAN PENGECETAN
1. Pek. Cat Dinding Tembok

Luasan Acian Dinding= 306.20 M² 306.20 M²

2. Pek. Cat Minyak Lisplang Kayu

T= 0.20
Jumlah Panjang Lisplang = 62.26

= 0,20x62,26x2
= 24.90 M² 24.90 M²

3. Pek. Cat Minyak Kayu Kusen


Panjang Kayu Kusen= 114.62
L Bidang Yg Dicat = 0.25

L= P x L
= 114.62 x 0.25
= 28.66 M² 28.66 M²

4. Pek. Cat Teak Oil/Politur Daun Pintu Kayu + Jendela


P1= 3.78
P2= 235.00
J1= 2.13
V1= 0.86
V2= 3.42 +

Jumlah= 245.19 M² 245.19 M²

5. Pek. Cat List Gybsumboard


Panjang List Gypsum= 83.66
L Bidang Yg Dicat = 0.15

L= P x L
= 83.66 x 0.15
= 12.55 M² 12.55 M²
URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SAT
VIII.PEKERJAAN ELEKTRIKAL
Jumlah Titik Lampu, Saklar, & Stop Kontak

1. Pek. Lampu SL 24 Watt (Downlight)

= 18.00 18.00 Titik

2. Pek. Lampu SL 14 Watt

= 2.00 2.00 Titik

3. Pek. Saklar Tunggal

= 5.00 5.00 Titik

4. Pek. Saklar Ganda

= 4.00 4.00 Titik

5. Pek. Stop Kontak

= 8.00 8.00 Titik

6. Pek. KWH/Meteran

= 1.00 1.00 Titik


URAIAN PEKERJAAN
NO GAMBAR DAN JENIS PEKERJAAN PERHITUNGAN VOLUME SAT
IX. PEKERJAAN MEKANIKAL & SANITAIR
Pek. Mekanikal
1. Pek. Pipa GIP dia. 1/2" Air Bersih
Panjang Pipa Gip dia. 1" Air Bersih
= 13.28+1.62+1.30+0.20
= 16.40 M¹ 16.40 M¹

2. Pek. Pipa PVC dia. 2" Pembuangan Air Bersih


Panjang Pipa PVC dia. 2" Pembuangan Air Bersih
= 13,11+3,02+6,44
= 22.57 M¹ 22.57 M¹
1311

302

3. Pek. Pipa PVC dia. 4" Pembuangan Air Kotor

Panjang Pipa PVC dia. 4" Pembuangan Air Kotor 17.88 M¹


= 8,78+1,12+7,98
= 17.88 M¹
112

878
798

1. Pek. Closed duduk

= 2.00 2.00 BH
2. Pek. Floor Drain

= 1.00 1.00 BH
3. Pek. Kran Air dia. 1/2"

= 2.00 2.00 BH
5. Pek. Bak Air /Mandi + Keramik

= 2.00 2.00 BH
7. Pek. Septictank & Peresapan

= 1.00 1.00 BH
Compatibility Report for RAB FAJAR.xls
Run on 29/07/2018 0:36

The following features in this workbook are not supported by earlier versions of
Excel. These features may be lost or degraded when opening this workbook in
an earlier version of Excel or if you save this workbook in an earlier file format.

Minor loss of fidelity # of occurrences

Some formulas in this workbook are linked to other workbooks that are 135
closed. When these formulas are recalculated in earlier versions of Excel
without opening the linked workbooks, characters beyond the 255-character
limit cannot be returned.
ANALISA'!H22:H24

ANALISA'!H26:H29

ANALISA'!H37:H39

ANALISA'!H92
ANALISA'!H100:H101

ANALISA'!H110:H111

ANALISA'!H125
ANALISA'!H148
ANALISA'!H160
ANALISA'!H179
ANALISA'!H188
ANALISA'!H199
ANALISA'!H201:H202

ANALISA'!H211:H214

ANALISA'!H222:H223

ANALISA'!H231:H232

ANALISA'!H240
ANALISA'!H251:H252

ANALISA'!H260:H263

ANALISA'!H271
ANALISA'!H273
ANALISA'!H275
ANALISA'!H285
ANALISA'!H294:H297

ANALISA'!F330:F331

ANALISA'!F342:F343

ANALISA'!F348:F349
ANALISA'!F361:F362

ANALISA'!H398
ANALISA'!H417:H418

ANALISA'!H427:H428

ANALISA'!H437
ANALISA'!H447
ANALISA'!H457
ANALISA'!H484
ANALISA'!H487
ANALISA'!H495
ANALISA'!H508
ANALISA'!H516
ANALISA'!H528
ANALISA'!H539:H541

ANALISA'!H549
ANALISA'!H592
ANALISA'!H597
ANALISA'!H603
ANALISA'!H613:H615

ANALISA'!H631
ANALISA'!H641
ANALISA'!H686:H687

ANALISA'!H704:H708

ANALISA'!H716
ANALISA'!H724:H726

ANALISA'!H733:H735

ANALISA'!H824:H826

ANALISA'!H836
ANALISA'!H844:H845

ANALISA'!H866:H867

ANALISA'!H877
ANALISA'!H895
ANALISA'!H908:H910

ANALISA'!H919:H921

ANALISA'!H930:H933

ANALISA'!H954:H957

ANALISA'!H966:H967

ANALISA'!H976:H979
ANALISA'!H990:H992

ANALISA'!H1000
ANALISA'!H1010
ANALISA'!H1021:H1023

ANALISA'!H1043
ANALISA'!H1160
ANALISA'!H1168

Some cells or styles in this workbook contain formatting that is not supported 98