Professional Documents
Culture Documents
6 Concrete Kerbs, Footpaths and Minor Works 6-2
6 Concrete Kerbs, Footpaths and Minor Works 6-2
6.02 STANDARDS
Work carried out and testing performed under this Section of the Specification shall comply with the
requirements of the following Standards to the extent that they are relevant and not overridden by the
Specification.
A Testing Authority shall be employed by the Contractor to carry out all testing. The Authority shall hold a
current NATA (National Association of Testing Authorities) Registration for the relevant tests, and a copy of
results shall be forwarded to the Superintendent without delay.
6.03 MATERIALS
6.03.1 Concrete
Concrete and reinforcement shall comply with the requirements of Section 15 of this Specification.
Unless noted otherwise in the Contract, concrete shall meet the following requirements:
The top surfaces of bitumen impregnated canite or other approved material sealers shall be taped.
6.04 EARTHWORKS
Carry out earthworks and preparation of surfaces as specified in Section 2 of this Specification. Subgrades shall
be compacted to 90% of modified maximum dry density as determined by Test Method AS 1289.5.4.1 for a
minimum depth of 150mm.Where levels are not specified, trim surfaces to conform to the grades and cross
sections specified in Clause 6.05.
Unless otherwise permitted, excavated material shall not be deposited on existing grassed areas.
Longitudinal grades normally shall be in the range 0.5% to 10%. Longitudinal grades differing by more than 2%
shall be connected by smooth vertical curves. Construct minimum earthworks to meet this requirement.
Batters in cut or fill generally shall be 1:6 where cut or fill does not exceed 300mm in depth.
6.06 SUBBASE
Unless otherwise specified or permitted, subbase material for kerbs and concrete paving shall be crusher dust or
subbase material complying with the requirements of Clause 4.03.2. Crusher dust used as subbase shall have the
following properties: -
6.08 FINISHING
After placing and compaction, concrete shall be finished monolithically to a smooth, even surface by means of
steel floats or other suitable equipment.
On completion of steel floating and before initial set, the surfaces of concrete paths, driveways and minor paving
shall be brushed to a "non-skid" texture. This shall be achieved by drawing a moistened nylon broom lightly
across the surface at right angles to the direction of the path or paving.
6.09 JOINTS
6.09.1 Kerbing
Weakened plane (shrinkage control) joints shall be 1-3mm wide, clean cut and made vertically through the
concrete at right-angles to the direction of the work. Normally they shall be spaced at 3m intervals with minor
adjustments to avoid short closing lengths.
Where kerbing is laid by machine, joints shall be formed in a manner which does not cause damage to the
adjoining concrete during cutting and to a depth which will prevent cracking elsewhere. A minimum of 50
percent of the section shall be cut for the full width of the section.
The resultant slot in the section shall be tooled to a depth of not less than 5mm to produce a neat groove with
rounded arrises.
Where kerbing is cast against fixed forms, contraction joints shall be formed by means of a 3mrn thick steel plate
cut to profile which shall be withdrawn before final finishing.
Expansion joints shall be formed adjacent to drainage structures, at changes in cross-section, at tangent points of
curves of less than 25m radius and at 12m intervals elsewhere. Expansion joints shall be sealed with 15mm wide
joint sealer cut to the full profile of the kerb section. Remove tape from top of sealer at about the time of final set
of the concrete. Joint arrises abutting joint sealer shall not be tooled off.
Where kerbing is laid as part of rigid pavement or adjacent to rigid pavement joints of the same type shall
coincide with joints in the rigid pavement.
Weakened plane (shrinkage control) joints shall be formed by making a cut 3mm wide for at least one quarter of
the depth of the paving. Arrises shall be tooled to suitable radius. Unless otherwise specified or detailed, the
spacing of weakened plane joints shall approximate the width of the path with minor adjustments to avoid short
closing lengths. Spacing shall not normally exceed 2m.
Expansion joints shall be constructed for the full depth of the paving using 15mm wide joint sealer. They shall be
provided wherever the paving abuts fixed structures, such as buildings and manholes, transversely at maximum
intervals of 15m along path and at path intersections. Joint sealer shall be bonded to the first placed concrete
using a suitable contact adhesive. Remove tape from top sealer at about the time of final set of the concrete. Joint
arrises abutting cork joint sealer shall not be tooled off.
Submission Details: At least four (4) working hours prior to commencement of concrete paving.
the Contractor shall provide notification that the works have been set out
suitably on site, subgrade has been compacted as specified with submission
of test results where appropriate and when any reinforcing will be ready for
inspection.
Release of Hold Point: The Superintendent will inspect the site and review the submitted details
where appropriate, prior to authorising the release of the Hold Point.
Expansion joints shall be formed adjacent to any structures or paving, at changes in cross-section, at tangent
points of curves of less than 25m radius and at a minimum interval of 12m elsewhere. Expansion joints shall be
sealed with 15mm wide joint sealer cut to the full profile of the kerb section, Remove tape from top of sealer at
about the time of final set of the concrete. Joint arrises abutting joint sealer shall not be tooled off.
Concrete shall be cured by protection against loss of moisture and rapid temperature changes for a period of not
less than 5 days from the completion of the finishing operations. Curing shall be accomplished by the application
of a sprayed membrane forming curing compound to the whole of the concrete surfaces including edges exposed
by the removal of formwork. If membrane curing is delayed for any reason, then suitable alternative means shall
be employed to prevent drying of the concrete until the membrane can be applied.
The compound shall form a uniform, continuous, cohesive film. If discontinuities, pin holes, or abrasions exist,
an additional coat shall be applied to the affected areas within 30 minutes. Concrete surfaces which are subjected
to heavy rainfall within 3 hours after the curing compound has been applied shall be resprayed.
Provide protection as necessary to prevent cracking of the concrete due to temperature changes during the curing
period. Whenever temperatures below 3°C are forecast, concrete shall be protected from frost for 24 hours after
placing by covering with suitable heat insulating material.
As an alternative to membrane curing, the concrete shall be kept continuously wet for five (5) days by covering
with wet bags or wet sand or with a waterproof membrane such as polyethylene sheeting held in intimate contact
with the surface.
(a) In plantation areas backfill to 75mm below finished surface as specified in Clause 2.06 for general
fill. The top 75mrn of backfill shall be topsoil from stockpile. Grade surfaces as specified in Clause
2.08 to remove abrupt changes of slope or level and to finish flush with new concrete.
(b) Unless otherwise detailed, where existing road pavement has been disturbed, the pavement shall be
trimmed back to a straight undisturbed edge between 150 and 30Omm from and parallel to the new
kerb or gutter for the full depth of kerb section. Backfill with asphaltic concrete rammed solid using
suitable tampers.
6.13.1 Materials
All concrete shall be tested as follows:
6.13.2 Tolerances
(i) Subbase
The level of the subbase bedding layer shall not deviate by more than 25mm above the specified level. The
surface of the subbase bedding layer shall not deviate by more than 10mm from a 3m straightedge or 10mm in
3m from the true vertical curve on vertical curves.
(b) A construction joint, expansion joint or weakened plane joint has been made at a location or in a
manner not in accordance with this Specification,
(c) The concrete kerb, edging or paving contains cracks exceeding 0.5mm in width at locations other
than weakened plane or construction joint locations.
The Contractor shall include in the management review of the Quality System, a review of the appropriateness of
the frequency of testing nominated in the Inspection and Test Plan(s). Such review shall take into account the
frequency of nonconformity detected, including nonconformities remedied by simple reworking.
Table 6.1
- Level
- horizontal alignment
- level
- Straightness/deviation
from vertical curve
The pay items applicable to particular activities are listed in the Specifications for these activities.
A lump sum price for any of these items shall not be accepted.
If any pay item for which a quantity of work is listed in the Contract has not been priced by the Contractor, it
shall be understood that due allowance has been made in the prices of other items for the cost of the activity
which has not been priced.
The Contractor shall allow in the pay items generally for the costs associated with all testing required to prove
conformance of the works as specified.
This pay item shall include all operations involved in the forming, compaction of foundations, supply and
construction of subbase, supply and placement of concrete, jointing, kerb markings, curing, and backfilling
adjacent to the kerb.
Kerb transitions are to be measured as part of the relevant kerb type length with the length of kerb through the
transition split equally between the kerb types each side of the transition. An extra over rate is provided for kerb
transitions.
An extra over rate is provided, for supply and placement of reinforcing steel where specified on the drawings.
A separate pay item shall be included in the Contract for each kerb type.
This pay item shall include all operations involved in the forming, compaction of foundations, subbase,
concreting, finishing, jointing, curing and backfilling.
Where specified, this pay item shall include the supply and placement of reinforcing steel.
A separate pay item shall be included in the Contract for each thickness of concrete paving specified.
603P2.10 Extra over rate for reinforced concrete paving using F82 mesh
603P2.11 Extra over rate for reinforced concrete paving using F92 mesh
603P2.12 Extra over rate for reinforced concrete paving using F981mesh