N Location Work itme Finish date Remark

1 BVS1 Ground prepration


2 BVS1 Water or machean compaction
3 BVS1 300mm gypsum layer
4 BVS1 Water and compact
5 BVS1 Level check and modify
6 BVS1 Density test
7 BVS2 Ground prepration
8 BVS2 Water or machean compaction
9 BVS2 300mm gypsum layer
10 BVS2 Water and compact
11 BVS2 Level check and modify
12 BVS2 Density test
13 BVS3 Ground prepration
14 BVS3 Water or machean compaction
15 BVS3 300mm gypsum layer
16 BVS3 Water and compact
17 BVS3 Level check and modify
18 BVS3 Density test
19 BVS4 Ground prepration
20 BVS4 Water or machean compaction
21 BVS4 300mm gypsum layer
22 BVS4 Water and compact
23 BVS4 Level check and modify
24 BVS4 Density test
25 BVS5 Ground prepration
26 BVS5 Water or machean compaction
27 BVS5 300mm gypsum layer
28 BVS5 Water and compact
29 BVS5 Level check and modify
30 BVS5 Density test
48 GS1 Ground prepration
49 GS1 Water or machean compaction
50 GS1 300mm gypsum layer
51 GS1 Water and compact
52 GS1 Level check and modify
53 GS1 Density test
54 GS2 Ground prepration
55 GS2 Water or machean compaction
56 GS2 300mm gypsum layer
57 GS2 Water and compact
58 GS2 Level check and modify
59 GS2 Density test
60 REZ-1 Ground prepration
61 REZ-1 Water or machean compaction
62 REZ-1 300mm gypsum layer
63 REZ-1 Water and compact
64 REZ-1 Level check and modify
65 REZ-1 Density test
66 BOG-1 Ground prepration
67 BOG-1 Water or machean compaction
68 BOG-1 300mm gypsum layer
69 BOG-1 Water and compact
70 BOG-1 Level check and modify
71 BOG-1 Density test
72 BOG-2 Ground prepration
73 BOG-2 Water or machean compaction
74 BOG-2 300mm gypsum layer
75 BOG-2 Water and compact
76 BOG-2 Level check and modify
77 BOG-2 Density test
78 BOG-3 Ground prepration
79 BOG-3 Water or machean compaction
80 BOG-3 300mm gypsum layer
81 BOG-3 Water and compact
82 BOG-3 Level check and modify
83 BOG-3 Density test
84 BOG-4 Ground prepration
85 BOG-4 Water or machean compaction
86 BOG-4 300mm gypsum layer
87 BOG-4 Water and compact
88 BOG-4 Level check and modify
89 BOG-4 Density test
90 BOG-5 Ground prepration
91 BOG-5 Water or machean compaction
92 BOG-5 300mm gypsum layer
93 BOG-5 Water and compact
94 BOG-5 Level check and modify
95 BOG-5 Density test
96 BOG-6 Ground prepration
97 BOG-6 Water or machean compaction
98 BOG-6 300mm gypsum layer
99 BOG-6 Water and compact
100 BOG-6 Level check and modify
101 BOG-6 Density test
102 BOG-7 Ground prepration
103 BOG-7 Water or machean compaction
104 BOG-7 300mm gypsum layer
105 BOG-7 Water and compact
106 BOG-7 Level check and modify
107 BOG-7 Density test
108 BOG-8 Ground prepration
109 BOG-8 Water or machean compaction
110 BOG-8 300mm gypsum layer
111 BOG-8 Water and compact
112 BOG-8 Level check and modify
113 BOG-8 Density test
114 BOG-9 Ground prepration
115 BOG-9 Water or machean compaction
116 BOG-9 300mm gypsum layer
117 BOG-9 Water and compact
118 BOG-9 Level check and modify
119 BOG-9 Density test
120 BOG-10 Ground prepration
121 BOG-10 Water or machean compaction
122 BOG-10 300mm gypsum layer
123 BOG-10 Water and compact
124 BOG-10 Level check and modify
125 BOG-10 Density test
126 BOG-11 Ground prepration
127 BOG-11 Water or machean compaction
128 BOG-11 300mm gypsum layer
129 BOG-11 Water and compact
130 BOG-11 Level check and modify
131 BOG-11 Density test
132 BOG-12 Ground prepration
133 BOG-12 Water or machean compaction
134 BOG-12 300mm gypsum layer
135 BOG-12 Water and compact
136 BOG-12 Level check and modify
137 BOG-12 Density test
138 BOG-13 Ground prepration
139 BOG-13 Water or machean compaction
140 BOG-13 300mm gypsum layer
141 BOG-13 Water and compact
142 BOG-13 Level check and modify
143 BOG-13 Density test
144 BOG-14 Ground prepration
145 BOG-14 Water or machean compaction
146 BOG-14 300mm gypsum layer
147 BOG-14 Water and compact
148 BOG-14 Level check and modify
149 BOG-14 Density test
150 BOG-15 Ground prepration
151 BOG-15 Water or machean compaction
152 BOG-15 300mm gypsum layer
153 BOG-15 Water and compact
154 BOG-15 Level check and modify
155 BOG-15 Density test
156 BOG-16 Ground prepration
157 BOG-16 Water or machean compaction
158 BOG-16 300mm gypsum layer
159 BOG-16 Water and compact
160 BOG-16 Level check and modify
161 BOG-16 Density test
162 REB Ground prepration
163 REB Water or machean compaction
164 REB 300mm gypsum layer
165 REB Water and compact
166 REB Level check and modify
167 REB Density test