μ= 74.

33
VE= 4.28
σ= 2.07
find out the probability that the project will finish:

(a) in the expected duration  


       
Y= 74.33    
       
Z=Y-μ/σ 0.00    
       
FOR Z= 0    
P= 0.50    

(B) at least 2 days early  


       
Y= 72.33    
Z= -0.97    
       
P AT 0.97 0.8340    
P @-0.97 = (1-0.8340)    
  0.1660    

(C) at least 4 days late      


(D) on TE          
(E) Find the of completion with at least 93 percent confidence