Hours

Total 41
1 Modelling framework
1a Read papers, relevant articles and analyze data 3
1b Evaluate possible modelling Options 2
1c Link Price of Bitcoin to the Valuation model 5

2 Incorporate
2a Halving effect of mining 4
2b Mining Difficulty/Competition 4

3 Build Out CashFlow model


3a Income projection for 5Year 2.5
3b Cost Projection (Capital Investment , Replacement rate , Electricity Cost) for 5Y 2.5

4 % Net Return , ROIC, FCFF 2

5 Scenario Analysis
5a Valuation sensitivity from Bitcoin Price change 3.5
5b Valuation sensitivity from Mining difficulty 3.5

6 Testing , Validation and Presentation 3

7 Difference between Mining investment return and direct bitcoin investment return 6
Available Bandwidth per day Project Duration
3 14 Approx 2 weeks

← This one will require a Bitcoin Pricing model , which I am not sure of the moment. This is just indicative