BACKGROUND OF SELF MONITORING
REPORT
Page 1 of 25
ONLINE SELF-MONITORING REPORT
SYSTEM
▪ Paperless transactions
▪ Less hassle and time consuming which will help to prevent delays.
▪ They have lower labor cost than manual submission on both the
industries as well as the LLDA.
Page 3 of 25
PROCEDURES IN USING THE ONLINE SELF-
MONITORING REPORT SYSTEM
(Step by Step)
Step 3. For new user, click the “Not Yet Registered” button and then
proceed to the user’s registration process.
Page 4 of 25
Step 4. Simply fill-up those needed information. Make sure that use the
registered Establishment ID indicated to your Discharge Permit.
Page 5 of 25
➢ Make sure to fill-up all those with *
Step 5. Verification email was already sent on the email used during
registration.
Page 6 of 25
Step 6. Check your inbox, and you’ll have this kind of email.
Page 7 of 25
Click the “Verify Email Address” button, and then you will be redirected to the
next process.
Page 8 of 25
Again, fill-up those needed information. Make sure that it is correct and
updated.
For registration
process compliance,
you also need to
provide some of your
company’s general
information.
Page 9 of 25
“Uploaded
Successfully” will
appear after clicking
the “Save Page”
button
Page 10 of 25
Step 8.
Page 11 of 25
Step 9. Fill-up now the Wastewater Treatment Plant (WTP) Record.
Step 10. For the first part, just click the check box which indicates the day of
the Month.
Page 12 of 25
Tick the Checkbox to
Group Selection and
then click button
“Group Selection”
Step 11. Input also the Effluent Flow Rate after clicking the group selection
button.
Be sure to input
the Effluent Flow
Rate and click “Ok”
button.
Page 13 of 25
Step 12.
Page 14 of 25
Step 13. The first month’s data was already saved. Proceed now to the
following more months of your WTP Record.
Page 15 of 25
After completing all the
data for 3 months WTP
Record, click the “Save and
Next” button to proceed to
the next page of the
system.
Page 16 of 25
Make sure that “SMR –
Waste Treatment Plant
Record is successfully
saved” will appear after
clicking the “Save and
Next” button.
Page 17 of 25
Same procedure,
simply click the “+”
button to add data on
the next report for SMR
Sample format in
providing Parameter
Name & Unit
Page 18 of 25
Data was saved
already. Proceed to the
next data needed.
Page 19 of 25
“SMR – Report of Wastewater
Characteristics is successfully
updated” will appear if saved
and updated
Page 20 of 25
Step 15. Next report will be, Monthly Report of Wastewater Characteristics
(Other Pollutants). The same procedure on the previous report for
conventional pollutants they only differ on the data that will be
provided.
Page 21 of 25
“SMR – Report of
Wastewater Characteristics
is successfully updated” will
appear if saved and updated
Step 16. Next report, will be the Sources of Wastewater during this Quarter.
All procedures will still be the same. They only vary on the data that
will encode.
Page 22 of 25
After filling-up those
needed information, you
can now click the “Save
and Next” button.
Step 17. After filling-up the last report needed for SMR, you can now finally
submit your report and it will be automatically listed on the
“Submitted Reports” as shown on Step 7.
Page 23 of 25
Step 18. You can now select the file that you will attached together with the
SMR.
Page 24 of 25
As seen on this
picture, your SMR is
now listed on the
Submitted Reports.