QUESTION 2

Four employees must be assigned to four projects. Only one employee can be assigned to each
project, and all projects must be completed. The cost of each employee completing each project is
shown below. Determine which employee should be assigned to which project to minimize total
project completion cost.

Compute the total project completion cost.

Project
Employee 1 2 3 4
Al $300 $325 $500 $350
Ben 400 525 575 600
Cal 350 400 600 500
Dan 400 350 450 450