DETAILED ESTIMATION FOR REAR ELEVATION

For CHB
Total Area Covered by CHB= 39.896 sq.m.

"Total # of 6"" CHB= 39.896 sq.m. x 13 pcs/sq.m."


=518.648 pcs
Consider 3% wastage for CHB
= 518.648 (1.03)
= 534.20744 pcs, say 535 pcs

Total # of bags = 535 x 0.0734


= 39.269 say 40 bags

Total cu.m. of Sand= 535 x 0.0059


= 3.15 cu.m.
Consider 3% wastage for SAND
= 3.15 + (1.03)
= 3.25 cu.m.

For Plastering
Total Area covered with plastered cement= 50.096 sq.m.
(including columns, beams,)

Total # of bags=48.096 sq.m. x 0.2 bags/ sq.m.


= 9.6192 say 10 bags

Total cu.m. of SAND= 48.096 sq.m. X 0.02 cu.m.


= 0.96192 cu.m.
Consider 3% wastage for SAND
= 0.96192 (1.03)
= 0.99077say 1 cu.m.