Professional Documents
Culture Documents
I
Table of Contents Page
III
List of Tabl…………………………………………………………………………………………
IV
List of Charts ……………………………………………………………………………………..
V
List of Equations ………………………………………………………………………………..
VI
Abstract …………………………………………………………………………………………….
3. A Case Study………………………………………….……………………………………… 6
3.1 Establishing The Context………………………………………….…………..
6
……... .
3.2 Risk Identification……………………………………………………….……..……….. 7
4. Conclusion………………………………………….……………………………………..….. 13
Bibliography………………………………………….………………………………………….. 14
II
List of Tables Page
Table 1, “Risks List ” ………………………………………………………. 8
III
List of Equations Page
Equation 1, “Risk Ranking ”…………….…………………………………... 9
IV
List of Charts Page
Chart 1, “High priority Risks”…………….……………………………… 11
Chart 2, “Medium Priority Risks”…………….………………………… 11
Chart 3, “Low priority Risks”…………….……………………………… 12
V
Abstract
The risk management is a key factor in construction projects. The main objective of
managing risk is to analyze and classify the risks and establish an approach to
minimize the negative risks and increase opportunities. Construction of schools in
Saudi Arabia has a particular nature, and one of the most important features is the
short period to finish the project on the specified time and within budget. Moreover,
because of this function, multiple risks may be rose starts from initiation followed by
executing and ended by handing over. These risks could affect the project negatively,
especially on the organization's economies. Even if the construction projects are
similar in its components and purposes, but just changing the place is sufficient to
make these projects differ from each other and therefore may these projects
exposed to risks. These risks can interact with each other and could affect negatively
both on the cost and the time needed to complete the projects. This paper provides
an overview of identifying risks, qualitative assessment about a real school project.
Audience:
Project managers: because they need to finish their projects according to the
necessary cost and time.
The owner: because he needs to know whether the contractor submitted his price
in a scientific manner or not.
Contractors: because they interested to know all risks related to project and they
need to analyze the risks, then they produce or put the right and competitive price.
VI
1. Introduction
The construction industry has a major effect on any country’s economy. There is an
intimate and co-connection between the construction industry and the other
economic sectors. However, there are a plenty of risks face construction and building
industry. These risks have a major effect on the progress of the projects which lead
to project delays, cost overrun, and poor quality. In this context, there are many risks
such as lack of engineer’s skills, centralization of authority, changing in design, price
risks, communications between stakeholders, inflation risks, political climate and
weather factors.
The primary goal of risk management is to analyze and classify the risks and establish
an approach to minimize the adverse risks and increase opportunities. Project
stakeholders should make the correct decisions related to risks to finish the project
and fulfill objectives.
Construction of schools is fraught with risks which face the contractor or the owner,
and it is hard to avoid or predict it unless these risks identified previously. The
contractor, owner, and other stakeholders should identify all possible risks related to
school projects and find suitable solutions to mitigate, avoid, and share risks to
complete the projects on time and within the authorized budget.
The next pages concentrate on showing an overall view of risk management
processes, factors affecting the success of the application and case study from a real
project. The case study includes risk identification, qualitative risk analysis.
2. Literature Review
The literature review of this paper covers two main topics: (1) The construction
schools, (2) Risk management and success factors.
VII
Finishing works which include all activities related to the external and internal
finishes plus MEP activities.
The PMBOK ® Guide – Fifth Edition describes the objective of the project risk
management as, "The objectives of Project Risk Management are to increase the
probability and impact of positive events and decrease the probability and impact of
negative events in the project." "Also, The The PMBOK ® Guide – Fifth Edition defines
project risk management as, Project Risk Management includes the processes
concerned with conducting risk management planning, identification, analysis,
responses, and monitoring and control on a project." "Also The The PMBOK ® Guide
– Fifth Edition states, a project risk is an uncertain event or condition that, if it
occurs, has a positive or adverse effect on a project’s objectives."
The risk is the possibility of an adverse deviation from the desired or expected, or
hoped-for result. The primary purpose of risk management is the risk measurement
for monitoring and control. Another definition of the risk is the logical process to
define, analyze, and respond to the risk of the project.
Risk management process must start early starts from project planning and go
through project execution and project closure.The project manager, team members,
stakeholders, and experts from outside the project should participate and involved in
this process and are responsible for managing risks.
VIII
In our real world, some people believe in that the risks is just adverse events and
harm the person or the organization but in real risks can be a positive event too.It
can give the person opportunities to enhance his life attitude and can provide the
organization to improve their projects and gain benefits.
IX
- Comprehensive Identification.
- Explicit Identification of Opportunities.
- Multiple Perspectives.
- Risks Linked to Project Objectives.
- Complete Risk Statement.
- Ownership and Level of Detail".
X
2.2.6 Plan Risk Responses
After finishing quantitative risk analysis, the next step is to develop a plan for
responding the identified risks.This Process describes the necessary actions required
from the responsible to deal with risk.The responsible should do the action in a
proper manner and on time. Sometimes during executing phase, new risks can rise
when response plan is working.So, the project manager should review these risks,
and update the risk register.When the stakeholder response to the positive risk, he
or she can share, enhance, accept, and exploit it, but when he or she response to the
negative risk, he or she can transfer, avoid, accept or mitigate it. There are also some
factors must be considered to ensure the success of this process - as per practice
standard for project risk management, By PMI- as follows:
- "Apparently, Define Risk-Related Roles and Responsibilities.
- Communicate.
- Specify Timing of Risk Responses.
- Provide Resources, Budget, and Schedule for Responses.
- Address the Interaction of Risks and Responses.
- Ensure Appropriate, Timely, Effective, and Agreed-Upon Responses.
- Address Both Threats and Opportunities.
- Develop Strategies before Tactical Response".
XI
3. A Case Study
The following pages provide a case study for a real project in Saudi Arabia. The
project is a construction of a high school for boys.
XII
3.2 Risk Identification
No Risk Description
Excavation in undefined Excavation in Rock soil takes a long time more than excavation in
1
soil sandy soil and costs more rather than increasing costs.
Poor skills of the labors Poor skills of the labors cause decreasing in productivity and lead
2
and site engineers. to project delays.
All the team members must do all, and only the required work, if
3 Scope of the work not, the gold plating and the scope creep are going to take place
and also cost more.
Executing the activities in a bad quality lead to rework and put the
4 Poor quality
project over budget.
XIII
Design and scope Due to the design errors or scope changing, the work is going to
7
changing stop partially or wholly.
1 Inflation and prices Due to inflation and prices fluctuation, the labors, and materials
0 fluctuations are going to increase and result in excessive in the project budget.
1
Change orders Change orders can lead to an extension of the project schedule.
4
XIV
1 Delays in delivering water Any delay in delivering water supply facilities result in imposing
7 supply facilities penalties.
Throughout this process, each risk is analyzed and assessed. The range of
likelihood and impact is fall between (0 – 100) %.
The project manager, team members, and external experts participated in the
evaluations of the impact and probability of the risk list.
According to "Risk management for overseas construction projects, He Zhi,
School of Civil and Structural Engineering, Nanyang Technological University,
Singapore 2263- page 234."
R=P×I (Equation – 1)
Where:
"R" is the degree of risk, within [0,100] %.
"P" is the probability of the risk occurring, within [0,100] %.
"I" is the degree of impact of the risk, which is defined as being within [0,100] %.
The following table is presenting the ranking of risks. The table shows a variety
of ranks as risks may be high risk, medium, or low.
XV
.
XVI
14 Change orders 10 30 3 Low
15 Shortage of materials 20 20 4 Low
16 Delays in delivering
80 90 72 High
Electricity facilities
17 Delays in delivering water
90 80 72 High
supply facilities
18 Delays in delivering
70 90 63 High
sanitation facilities
19 Environmental disasters 2 80 16 Medium
20 Government changes 90 60 54 High
The next three charts represent the high risks priority, medium risk priority,
and low risks property respectively.
XVII
Poor skills of the labors and site
engineers.
Scope of the work
Poor quality
Design and scope changing
Inflation and prices fluctuations
Bribery
Environmental disasters
Site accessing
Change orders
Shortage of materials
XVIII
4. Conclusion
In general, all construction projects are linked with risks. Risk management is an
iterative process; it can starts in the planning phase and also can go through
execution phase. There are some factors must be aware of through risk management
processes to ensure the success of these processes.Schools constructions are risky
projects and must be managed to implement the project according to its
objectives.Risk management is essential for the project manager in implementing
the project; he can provide support to his organization and his project as follows:
- Savings extra costs
- Deliver the project on time
- Enhance the performance
- Obtain lessons learned
- Enhance future estimate
- Drive your company and your team members forward
XIX
Bibliography
No
. Description
XX
XXI