CONSTRUCTION SEQUENCE OF PILE

STEP 1 Location Survey STEP 2 Temporary steel casing driving STEP 3 1. Setting up Rig STEP 4 Drilling STEP 5 Cleaning bucket
- Pile center marking using vibro hammer with power 2. Initial drilling - Polymer slurry circulation
pack process
- Get soil sample for borehole log
verification

GPS (RTK) Slurry Tank Slurry Tank


Survey
Power Pack

STEP 6 1. Rebar cage insertion STEP 7 Casting concrete with tremie pipe STEP 8 Temporary steel casing retraction using vibro hammer

Power Pack