WORK SCHEDULE 1 OF 1 TAPAZ WTP - Work Status (LGU)

Subject: Tapaz WTP Work Schedule Phase 1


Date: June 14 - 30, 2021

JUNE 2021
ITEM ACTIVITIES
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 FABRICATION OF TAPPING CHAMBER CONCRETE COVER


2 SITE LAY OUT AND SETTING OFOR ROAD WORKS
3 PLASTERING OF EXTERNAL WALL (BUILDING EXTENSION)
4 SKIM COAT OF EXTERNAL WALL (BUILDING EXTENSION)
5 SKIM COAT OF INTERNAL WALL (BUILDING EXTENSION)
6 POLISHING OF PROCESS TANKS
7 PRIMER PAINTING OF PROCESS TANKS
8 TOP COAT PATING OF PROCESS TANKS
9 POLISHING OF INTERCONNECTING PIPEWORK
10 PRIMER PAINTING OF INTERCONNECTING PIPEWORK
11 TOP COAT PATING OF INTERCONNECTING PIPEWORK
12 CHLORINE CONTACT TANK FABRICATION
13 TESTING OF ELECTRICAL DEVICES (CAPELCO)
14 INSTALLATIONS OF ELECTRICAL DEVICES
15 TESTING OF ELECTRO-MECHANICAL EQUIPMENT