ig. 1 Flow
sdaotion care at
the intake of
Rellswerk dro
lant
Integration of the Rellswerk
pumped-storage plant into an
existing hydraulic scheme
.Meusburger and 6. Gékler, Vorarlberge ilwerke AG, Austria
The Relowerk puped storage plan, sheild to go chead in Austria next yea, willbe inerae win on exiting hyropoer system.
Aes sus, «mbes wee ried ig the ete Yee, 5 oy
fficency, ut oo the influence ofthe headroe
plant will increase the maximum capacity and
annual energy production of the Linersee hydro
Complex, which fas been in continuous operation
since 1958. In addition to the powerhouse, a new arti-
ficial basin with a storage volume of approximately
44.000 m? will bo built in the Rells valley at el
1450 m. The powerhouse will be equipped with one
reversible three-stage pump-turbine. The new under:
{ground headrace will connect the powerhouse to the
existing headrace tunnel of the Liinersee hydro plant,
which crosses the Salonien valley approximately 2 km
south of the new site. At the crossing point, the new
penstock will be connected to the stee-lined headrace
of the Lunersee plant in a newly built service chamber
which houses two emergency shut down ball valves;
‘The start of construction is Scheduled for the autumn
of 2014. The storage basin beside the powerhouse and
the steel-Tined penstock will probably be completed by
mid-2016. To minimize energy production losses, it
was necessary to use the general overhaul of the head-
race at the Lilnersee plant during the summer of 2013
to equip the service chamber with the ball valves and
‘new flow-optimized T-wye. The erection of the serv-
ice chamber had already begun in the summer of 2012.
The construction of the powerhouse (see photo) is @
considerable challenge in structural engineering,
because the construction pit has to be built in the
groundwater table as a vertical duct. It is planned to
Seal the shaft with an overlapping bored pile wall
which integrates into the tight ground moraine. The
powerhouse will be embedded into the downstream
reservoir embankment dam, which is approximately
15 m high. After the civil works have been finished,
the powerhouse will be covered with soil completely
‘The embankment dam is designed with an earth core,
which will be covered with a synthetic geomembrane
I: the future, the new Rellswerk pumped-storage
Nswrl eschage
Water nie vtine
Flow ml
onto)
the exiting Lanese hydric yiem
Powerhouse embedded in the embankment dam of the reservot
lew from north-east,
on the inner side of the dam to provide the watertight-
From the powerhouse, a 2.2 km-long steel-lined pen:
stock with a diameter varying between 800 and 1000
‘mm will lead to the Salonien service chamber. For
security reasons, two completely independent ball
valves are foreseen for the service chamber. Each of
them will be capable of shutting down an emergency
flow of 9 ms.
1. Hydraulic design of the pump-turbine
For the approval procedure of the Rellswerk hydro
project an environmental impact asesset as ee
Xan, and this wav conducted in 2008- July 2010
the official approval was. ranted. The hydraulic
design the machinery for Rellwerk had already
Bepun in 2006 wien it as foreseen to instal pa
(ahemative VI inthe Table) with a pumping power o
tpproximatcly [4 MW. Ths pump would have had
‘charge volume of 238 mip atthe nominal pump
Speed of 1000 rpm, resulting in am operation ime
around 2000 pump hours per year The fixed tur
Dine sped, mn, nat Shonen & 1000 rpm, tone The
pump dive was designed as fited speed synchro
foun motor generator As can be sen in Fig witha
pump discharge volume of 2-38 ms the pump would
Be able to empiy ie storage basin vith actorge vol
te, Varo Ot round 44 000 nP within about 12
hous, even the intake flow were ats maximum of
133 milo Therefore, with tis hydraulic avout he
rarsimu operational exit of the compet pow
Cxplan cou be ensured, because itis lvays posible
{eroperte the machine in reverse as.a turbine fi
Should become necesary beens of» lack of eeer-
cal power in he gd
Hydropower & Dame. tesue Five, 2013The hydraulies of the machines which were studied,
‘V2 and V3 in Table 1, are units with reduced impeller
diameters and thus reduced pumping and turbine
power. Both were planned with synchronous speed
Grives. But in contrast ro V2, which was planned with
‘nominal speed, npc, of 1000 rpm similar, to altema-
tive V1, V3 was designed for a rotation speed of 1500
‘pm in both the pump and turbine directions. The main
advantage of alternative V2 compared with V1 is the
Tower suction head required, resulting in a higher set
ting level, sain, of el. 1437. But because of the high-
er Speed of alternative V3, this pump needs a higher
on head and therefore the lowest setting ofall the
‘options analysed. Although the machine V3, with a
rotational speed of 1500 rpm, is smaller and hence
cheaper than the other alternatives, the cost saving of
the machine is consumed by the Tower machine s&
ting, Hsin Of el. 1418, which thus has sigr
increased structural construction costs
From a hydraulic point of view, version VILA in the
‘Tuble is similar, only the drive speed varies, to VI as
‘V2.A is V2, Compared with the original alternatives
in these cases a variable speed drive with pump rota-
tinal speeds from 961 < nyu < 1045 rpm (945 < ny <
1027 rpm) was planned. In both cases the turbine oper
ation was planned with a constant non-synchronous
‘speed, ty, Of 900 rpm. The variable speed drive of the
pump gives the opportunity to control the pumping
power and to enlarge the operating range which is lim-
ited by the instability point of the pump head curve at
part load and by cavitation phenomena at overload.
‘Although the control range of the pump power, which
is related to the speed range, to the power of three, of
the impeller (inthis case -3.9 10 44.5 per cent, and -5.5
to 42.7 per cent, respectively), is comparatively small,
4 speed-controlled pump can become useful the more
the water level in the upper storage basin varies in rela-
tim to the rated pump head.
‘The weakness of these two variations is that at the
Rellswetk project a variable speed pump is not really
nocessary, but a variable speed turbine could be useful,
providing the possibility to control the proposed tur-
bine operation of the non-regulated three-stage pump in
the reverse direction. Therefore, alternative VILB with
able speed in both the pump and turbine directions
has been developed. Because of the increased pump
speed of 1070 < ney < 1125 epm, it was possible to
reduce the impeller diameter, while still having a high-
ce discharge compared with the alternatives V2. and
V2.A. The smaller impeller diameter option, VIB,
offers a considerably higher efficiency of more than 13
per cent in turbine operation than variant VLA, where
2s the pump efficiency is comparable,
The last column, Vi4, in the Table, gives the main
ump parameters of a quite unusual machinery layout
for a hydro powerplant. This alternative describes the
performance of a two-flood, three-stage pump com-
‘monly used. in industrial water supply systems ot
refineries (this pump has two suction pipes). To achieve
the required plant discharge, two pump units installed in
parallel in the powerhouse were necessary, Besides the
additional high and especially low head manifolds
because of the tw0-flood design ofthese pumps, and the
additional shut-off devices, the efficiency loss during
turbine operation is the main disadvantage of this sol
tion. As one can clearly see in the Table, with the
expected turbine efficiency the turbine power is reduced
by about 40 per cent compared with altemative V1.B,
cven if the reduced discharge of alternative V4 is taken
ly
Hydropower & Dams esue Five, 2013
The arias pos eh po bine hus eed
vi v2 V3 VIA V2A
vis
va
No. of unis fea ge tis 1
Imp.dia Dstm) [1.125 107 09 107
Novofstgss | 3 32 3 3
No. of flods er 1
Heyl) 97
1
1432 432
1
1.002
3
1
Mat
2
Mas
‘Pump operation
ev ta WC)
On")
es opm)
Pro (NW)
son
23816
io
Be 9090 12.
5303
246
961-1045
158
0s
156
75.97
sina
178
96-108
sx
os
945-1027 1070-1125 1490
49
[ ertin preton
fron)
Jou” [aan ar tas
| mecpm 000 ton0 1300
[PoiMwy 93 56 56
4545 4764 4764 45214747
255187
900 900
wo 65
io account, However, one has to bear in mind that the
efficiency curve used for the evaluation was estimated,
and not based on model or prototype measurement,
Based on the findings of the preliminary studies with
these different hydraulic layouts for the machinery, a
further economic analysis was done, taking imo
account the energy losses of the required frequency
‘converter for the Variable speed solutions. As a result,
the actual layout of the pump-turbine which finally was
tendered was established. Technically it is based on
variant VIB. However, it was decided to operate the
‘pump with a synchronous speed, yc. of 1000 rpm, to
climinate the losses of the frequency converter during
‘pumping operation, which were estimated to be around
2 per cent, To obtain the desired pump discharge Ory of
about 2.3 nls, the pump impeller was inereased t0 D:
1.105 m compared with altemative VI-B. With this
impeller diameter, turbine flows of around about 2.5
2.7 mvJs_can be expected with rotation speeds of
between 785 < my < 835 rpm. The evaluated turbine
power varies between about 9 < Pry < about 11.5 MW.
‘Compared with a fixed turbine speed of 1000 rpm, the
annual mechanical energy produetion of the variable
‘peed solution will increase by about 3 per cent. Taking
into account the losses ofthe frequency converter, there
‘will sill be an efficiency gain of around 1 per cent
1.1 Machine startup
‘To start the machine in the pumping mode, the fr
{queney converter will be used. Regarding the chosen
hydraulic layout for the machine, the frequency con-
verter must be designed at least for the maximum tur-
bine power of about 11.5-12 MW and the O-discharge
power of the pump with the given diameter and rota-
tional speed should be around 7.5 MW. No blow down
‘equipment is required for the start-up of the pump-tur-
bine in the pumping mode. After the rotor of the
machine has’ reached the synchronous speed, the
motor-generator can be coupled directly to the grid
tnd the ball valve will be opened.
AAs an alternative, a smooth start of the pump could
be achieved if the power of the frequency converter
was increased to the maximum power of the pump of
about Paaru ~ 13.5 MW, In this ease, the ball valve
could be opened at a rotation speed of the rotor of
about 900 rpm, when the pressure difference at the
valve is balanced. After the ball valve has atleast part-
4692
217
9001930
1497
ama
069
1490
17Ball vale i the
‘Solonien service
‘chamber
Fig. 2 Hydraulic
‘em ofthe
Linerse plant
the Relewerk
scheme
Unt tow eds BE er
sabbtbecsees:
ina
ly opened, the frequency converter could accelerate
the rotor up to synchronous speed before coupling to
the grid, This smooth start-up would preserve not only
the machine itself, but also the shut-off valve.
‘To start the machine in the turbine mode, a bypass 10
the shut-off valve is planned. This bypass pipe will be
equipped with a control valve, and should be able to
accelerate the rotor tothe designated turbine speed. In
addition, the frequency converter can be used to start
the turbine, especialy if the trbine hydraulics demon-
sirate unstable behaviour atthe speed-no-load point.
2. The Solonien service chamber
‘As mentioned in the introduction, the Salonien service
chamber, at the junction point t0 the Ltinersee head-
race, was constructed between late 2012 and mid.
2013. During the planned service break of the
with Liinersee plant for maintenance work in the headrace,
and to replace the shut-off valves directly at Lunersee.
the new flow-optimized T-junction, as well as the serv
oe ob oF
a
‘ye? ngage
Unit vais of pomp
INIT Une spond aad BE af pimp
Fig. 3 The pump characterise curves analysed
ice ball valve, were mounted inthe service chamber
between April and August 2013,
Both the normal shutoff valve and the overha shut-
oi valve are installed in the same way, The valves ae
designed to shutoff thre times the nominal low of
(Oxar = 9 ms in case of an emergency.
‘To close the oilhydraulicaly opened ball valves,
closing weights were mounted on both sides of the
walves (4e photo, ight side). A special feature i hat
the complet ball valves are made of forged steel. No
‘welds of cast iron were used forthe ball self or the
hovsing. Moreover, several main pars such a the ball
and the sealing rings and the cover plates ofthe hous-
ing were rade of stainless steel (14313)
Downstream. force balanced stuffing box connects
the shut-off bal valves with the anchor pipe which is
{embeded inthe conerete fixed point behind the ser\=
ice chamber wall. To ensure aeration of the pipe it
tase of an emergency shutdown of the valves, at
futomatic aeration and ventilation valve is mounted
dovinsream of the ball valves,
3. Transient waterhommer analysis
In ation to the economic analysis of the various
drut atematives, the influence on the existing
hycrallc system was analysed using 2 one-dimen
Sonal waterhamncrealulauon. For this aera
ter analyiyacaltion ri as shown in Fis 2 Was
red. In This network, the complet waterway ofthe
Liners hy pan including te sane tank ed the
mach nery ofthe powerhouses modeled. The length
and diameter, as well a the ftion lose soothes,
tree caloulied tased on dwigs of Ihe existing
Readce and potoypetestThe five high hea ste
age pumps insaled inthe powerhouse were modelled
tiLing into account the full pump characte cures
as show for te Reiswerk nor fefated pump.
Bine in Fig. 3, The junction point betwee the now
Relowerk pipeline and te henace of the Linersoe
plans shown in Fig. 2. was modeled a the aca
fistance, to represent the pipe inertia of the two
bramcbes to the ge tank aswell sf te Lineree,
‘The ppe duct to the Rellswerk plat was modeled as
an underground steel pipe witha length of approxi
mately 2300 m-The al aves the service chamber,
Ewell ay the ball valve in the powerhouse and the
pomp-trbine, considering the complete four quadrant
Pump characte curves aa sboWwa in Fig. 3, Were
Ml nthe numerical model.
For te one-dimensional watertammer program of
verte the pump characterise curves for it ow
And unitiogueovee th nit sped are eae othe best
efficiency point inthe pumping mode In contest the
Sign convention of te TEC: Nor TEC. 1999", the
pup tore is negative; as shown in Fig. 3 To model
{he pump behavior sl four operated guaran a
‘pes Wasformaton ofthe pur charac ay
‘Pied by Mader (2006s wed
Powe
“The most influential boundary condition to be fulfilled
for the integration of the Reliswerk plant into the
Linersoe hydraulic system is the maximum allowable
pressure inthe steel-lined part ofthe Lunersee headrace.
‘As shown in Fig. 2, the junction point is located in the
(ight) eastern part of the valley bottom, the so-called
Salonien ‘dive culver’. This dive culver: was built in
Da
feoue Five, 2018
Mydropower & Damsthe second half of the 1950s, and consists of a western
and eastern penstock connected by an underground steel
pipe. The penstocks were dimensioned with considera
tion for the supporting contribution of the rock, where-
as the underground steel pipe is self-supporting.
“To find the maximum pressure in the dive culvert, a
seties of some 100 loud cases were calculated during
the course of the hydraulic pre-study. The maximum
pressure, as shown in Fig. 4, appears in case of a load
rejection of the pump at the maximum level in the
Lnersce reservoir, when the ball valve in the power-
house closes. This very much depends on the pump
‘characteristic curves and, as anticipated, on the
assumed pump inertia. In Fig. 4, the total energy prop-
‘gation is drawn as calculated, with a typical storage
pump characteristic curve (pump type 1 in Fig. 3) and
4 pump inertia of 15 tm. The maximum total energy
head was computed to el. 1996.18. The amount of
wwaterhammer of the storage pump load rejection is
around 15 mWC in contrast to the waterhammer ofthe
process pump analysed (pump type 2 in Fig. 3), which
‘only contributes about 9 mWC. This different behay
jour results from the smaller plugging of the process
pump, compared with the storage pump which has
lighter and longer flow channels, especially in the
stayvane ring, and also the larger impeller diameter.
To minimize the waterhammer in case of a load
rejection of the pump, the closing time of the ball
valve in the powerhouse was adjusted to the transient
behaviour of the pump. This closing time of the ball
valve must not be too short, so as not to increase the
saterhammer of the pump caused by closure of the
impeller. Therefore the optimal closing time of the ball,
valve with a bended closing law was calculated to be
around 30 s. The closing velocity of the valve changes
after the first 20 sat a remaining opening of around 15
per cent. In Fig. 4it can be seen that with this closing
sequence of the ball valve, the pressure propagation in
the existing headrace of the Liinersee plant is quite
similar for the load rejection of the pump with and
‘without failure of the shut-down valve.
‘To reduce the highest pressure in the dive culver,
some additional surge protection devi
Besides the variation in the pump inert
in the powerhouse of the Rellswerk plant and. also a
pressure release valve in the Salonien service chamber
‘were investigated in the hydraulic study. Although the
pressure in the dive culvert could be reduced signfi-
cantly by these measures, an increase inthe rotor inertia
still seems to be the most economical and also reliable
‘option to stabilize the internal pressure
4. Conclusions
During the course of the feasibility study for the
Rellswerk hydro plant, sumerous analyses were carried
‘out. Besides the economics of various machinery types,
the influence on the existing headrace of the Llinersee
hydro plant was investigated. To evaluate the machin-
ery options, the estimated gains in terms of the eff-
ciency in the pump and turbine modes, the appropriate
‘operating time, as well as the anticipated installation
costs were all taken into account. Moreover, a quite
‘unconventional type of machine was included in the
preliminary study, involving a two machine arrange-
‘ment with three-stage and two-flood process pumps.
‘The outcome of all the investigations conducted was
that a tailor-made three-stage storage pump best suis the
requirements of this hydro project. This type of machine
Hydropower & Dams Issuo Five, 2018
EaSSEidaesaaaazaeaaay
‘can be adjusted precisely to the possible limitations of
the electrical power, as well a the flow intake at the des-
‘ignated position. Beside the best pump efficiency, this
solution offers excellent efficiency in turbine operation
Although the Rellswerk plant is designed to be operated
mainly as a pumping station, it will also be operated in
the turbine mode at peak load times.
‘Transient waterhammer analysis was carried out, tak-
ing into account the whole hydraulic scheme of the
LLinersee plant and the machinery in its powerhouse
‘The storage pumps at Lunersee, as well as the pump-
turbine for Rellswerk, were simulated with respect to
the full four-quadrant characteristic curves. The maxi-
‘mum pressure in the dive culvert, where the new under-
‘ground pipe of the Rellswerk plant will be connected 10
the headrace of the Liinersee plant in a newly built
service chamber, was calculated for the case of load
rejection of the pump-turbine when the shut-down
valve in the powerhouse closes. So as not to increase
the waterhammer caused by the impeller plugging, the
closing time ofthe ball valve was optimized and adapt
ed precisely to the pump-turbine hydraulics. °
References
1, TEC, Noo 60193: 1999: “Hydraulic Turbines, Storage
Pumps and. Pump-turbines — Model Acceptance Tests"
Intemational Electrotechnical Commission: 1999.
2, Mader, R., "Kops I Pumpeacharakteristit in der
DrucksioGrechoung” in: “Stauhaltungen und Speicher ~ Von
ddr Tradition zur Moderne’. Vl. 46/2. Puliestion of the
‘Technical University of Griz, Aus 2006,
| Peter Mleusburger graduated in Mechanical Engineering from
the Technical Unversity of Graz, Ansa. He hen worked as
2m Assistant Professor atthe Depurtnent of Hydraulic Fd
Machinery at the same university, where he finshed his
‘Sectoral stein Mechanical Engineering June 2009 with
' Doctor of Tehnial Sciences. Since 2008 he as worked as
fn expert for 3D fi hydaulis and waterharmer
‘aloulatons at VrrborgerIlerke AG. In 2012 he became
Head ofthe Mechanical Enginceing Depart
Gotttied Galler gratustd in Civil Engnccrng fom the
‘Tecnica University of Graz, Austra. He then worked as an
Assistant Professor a the Department of Hydric Structures
and Water Resources Management atthe sme university.
Since 2002 he his worked as an exper Tor hydravlics and
hydra structures at VorrbergerMverke AG. During the
‘esign, planning and construction phases he wa
representative Project Manager of the Kops I pumpe-stoage
Plann 2009 he became Head of the Design Department, and
Fince 2011 he has been Head ofthe Civil Engineering
Services Department at VorabergerIlleeks AG.
Vorartergerllwerke AG, engineering Serviees,
Balloggtrsse 36, A.6780 Schur, Aust,
Fig. 4 Total energy
head over tne in
the case of oud
jection a he
Rellwerk plant
P Menbarer|