Professional Documents
Culture Documents
Management
Initiate and Plan Project
Release 10
3. Oracle disclaims any warranties or representations as to the accuracy or completeness of any Materials. Materials are provided "as is" without warranty of any kind, either express,
implied or statutory, including without limitation the implied warranties of merchantability, satisfactory quality, fitness for a particular purpose, accuracy, timeliness and non-infringement
of third-party rights. The information contained herein is subject to change without notice.
4. Under no circumstances shall Oracle be liable for any loss, damage, liability or expense incurred or suffered which is claimed to have resulted from use of these Materials. As a condition of
use of the Materials, Partner agrees to indemnify Oracle from and against any and all actions, claims, losses, damages, liabilities and expenses (including reasonable attorneys' fees) arising
out of Partner’s use of the Materials.
Disclaimer:
This document is for informational purposes only and is intended solely for use in connection with the internal pre-production evaluation and testing of the Software. This is not a
commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or
functionality, and inclusion or not thereof in the commercially available version of the Software, if any, is always at Oracle’s sole discretion. This document is not considered part of the
applicable program documentation.
Due to the nature of the product architecture, it may not be possible to safely include all features described in this document without risking significant destabilization of the code.
Student Activity
Navigator > Setup and Maintenance > Implementation Projects tab > your implementation project >
Project Financial Management > Define Project Control Configuration
Manage Spread Curves Specify how quantity, cost and revenue amounts are automatically distributed across a range of
accounting or project accounting periods.
Use predefined spread curves or create new ones based on requirements.
Manage Resource Classes: Spread Review and update resource classes to specify the spread curve to be used.
Curves
Define Project Resource Define resource breakdown structures used for project planning, billing, and reporting.
Breakdown Structures
Manage Project Plan Types Specify default planning options that cascade down to the template and project levels.
Manage Project Templates Manage templates to quickly create projects that share common features, attributes, and options.
A default planning resource breakdown structure is created automatically for each project unit.
You cannot create or delete these billing resource breakdown structures. You can edit the resource formats and specify the associated billing resources to meet
the needs of your enterprise.
Overview
• Create project plan types to define default information
used when:
• creating a project plan
• capturing progress
• Associate one project plan type to a project template.
• Projects created using the template inherit setup and
planning option values.
• Revise setup or planning options at each level to match
specific planning requirements.
Setup
• Will project managers enter amounts in multiple
currencies?
• Will project managers perform scheduling activities in an
external scheduling application?
Plan Settings Define amount types included in version, planning level, and how periods are entered and
displayed
Task Settings Decide how task and task assignment dates are entered and calculated
Currency Settings Define attributes for converting transaction currency amounts to project and project ledger
currencies
Rate Settings Define sources of rates for planning resources
Progress Settings Decide how physical percent complete, Estimate to Complete, and other progress values are
calculated
Budget Generation Options Define are versions are generated from another source
Additional Information Capture custom information using descriptive flexfields
Plan Settings
• Enable cost for project plan: Used if you intend to plan costs on
tasks and task assignments. If not enabled then physical percent
complete values are calculated based only on effort.
• Calendar Type: Plan by period (accounting or project accounting)
or plan duration of resource assignment.
• Period Profile: Display amounts planned by period into summary
groupings, where appropriate.
Task Settings
• Use task planned dates as task assignment dates: Controls
whether resources on tasks can have different dates than the task
dates.
• Automatically roll up task planned dates: Determine if planned
dates for lowest-level tasks roll up to summary tasks. If you select this
option, then summary task dates are not editable.
Note: Planned date options are disabled if you decide to use third-
party scheduling.
• Synchronize task transaction dates with planned dates: Uses the
planning dates to determine when a task can be charged to with a
buffer.
• Specify a date adjustment buffer: Specify a Lag (positive) or lead
(negative) time between task planned dates and task transaction
dates.
Rate Settings
• Assign Business Units
• Select Use planning rates to specify which rate schedules you
want to use
Progress Settings
• Physical Percent Complete Calculation Method:
Cost, Effort, or Manual Entry. Selecting Cost or Effort automatically
calculates Physical Percent Complete as Actual Amount / Estimate at
Complete (EAC) Amount * 100. Manual uses progress from prior
progress cycle
• ETC Method:
Remaining Plan, or Manual. Remaining Plan uses the formula: ETC
Cost = Current Planned Cost – Actual Cost.
• Allow negative ETC calculation:
If actual amounts are greater than the plan, and you are using the
Remaining plan ETC method, this allows the calculation and display of
negative ETC amounts.
Progress Settings
• Update planned quantity with EAC quantity
Decide whether to update the project plan (planned quantity)
using the progress update i.e. changing the plan based on the
latest progress/estimate.
• Automatically generate forecast version:
As part of publication of progress you can also automatically
generate a Forecast.
• Primary Physical Percent Complete Basis
Determines whether the rolled-up physical percent complete for
summary tasks is based on cost or effort. This physical percent
complete value is used in project forecasting, reporting, and
revenue generation
Project Templates
Project templates enable you to quickly create projects that share common
features, attributes, and options.
Projects created from a project template or another project inherit the
attributes from the source project template or project as follows:
• Always copied: Resource breakdown structures, currency conversion
attributes, and KPI’s are automatically copied to the new project.
• Optionally copied: Select certain attributes, including tasks and task
assignments, to copy to the new project.
• Copied if not overridden in project details: Project attributes such as team
members, and class categories and codes are not copied if you can specify
them in the project details for the new project.
• Not copied: Transactions and project progress are never copied.
• Project Unit: Determines the options available for selection such as project and financial plan
types, and planning resource breakdown structures.
• Project-owning Organization: The organization that will own projects created from this
template; list of organizations is filtered using the specified business unit and project unit.
• Legal Entity: Defaulted to the legal entity associated with specified business unit; you can
select a different legal entity.
• Project Type: Determines options for projects created from this template to inherit.
• Initial Project Status: Define initial status for projects created from this template.
• From and To Dates: The beginning and end of the date range when the project template is
available to use.
• Project Space Template: This is the basis for automatically created project spaces for projects
created from this template.
Copy Options
When you use a project or template to create a project you can
indicate if the project creation process copies:
• Team Members on the project or project task.
• Attachments on the project or project task.
• Descriptive flexfields on the project or project task.
• Project space template.
• Specific project plan information such as project tasks and task
assignments, including resource types.
• Financial plans, transaction controls, and costing overrides.
Project Options
Implementation Decisions
• What is the project type?
• Is the project going to be used to create task assignments,
planning amounts, and capture progress, or just for costing and
billing?
• Will a dedicated project space for storing project documents be
required?
Capitalization Options
Cross-Charge Options
Cross-Charge Transactions