DATE DEPTH OPERATION AT DRILLED MUD

20/09/98 3200 RUN LAST 0 12


21/09/98 3200 DIS-ASSEMBLE 0 12
22/09/98 3200 WAIT ON SPARE 0 12
' 23/09/98 3200 RIH W/ CT TO 0 12
24/09/98 3200 SHUT IN AT 0 12
25/09/98 3200 POOH W/ PLT 0 12
OPERATIONS
Continued to R/U Schlumb. Lubricator,Run PLT to 1002 m,tool failure,POOH and back up string,RIH to end
POOH w/PLT and lay down same,R/D Schlumb.,open well on 24/64" choke,divert flow to separator for
Dis-assemble flow line and replace all 3" WECO seals,Test CT BOP,well head and surface lines,Repaired CTU
Wait on spare parts for CTU from Haliburton Jakarta,replaced Reel Motor chain,checked injector,replaced
Cont'd RIH with CT to straighten out Reel Pump and fill tubing with water,stop above LPRN,pressure up
R/U Schlumb, Run :PLT No.2,Schl repair short in PLT tool,Continued to R/U pressure equipment,RIH w/ PLT