Professional Documents
Culture Documents
HANDBOOK
for
LP-GAS BULK STORAGE FACILITIES
Operations & Maintenance Handbook
for
LP-Gas Bulk Storage Facilities
Notice and Disclaimer Concerning Liability ................................................................. i
Propane Education & Research Council Industry Feedback Form ........................... ii
Section 1: Introduction – Purpose, Scope and Use of Handbook ............................. 4
Background and Purpose ....................................................................................4
Scope of Handbook .............................................................................................5
Using This Handbook ..........................................................................................6
Accessibility and Review......................................................................................7
Section 2: General Facility Information ....................................................................... 8
Section 3: Emergency Procedures Plan ...................................................................... 9
Section 4: General Operations & Safety Requirements............................................ 11
Site Accessibility ................................................................................................ 11
Site Signage and Markings ................................................................................ 11
Control of Combustible Materials and Ignition Sources ...................................... 11
Combustible Materials ....................................................................................... 12
Facility Ignition Sources ..................................................................................... 14
Containers – General Requirements .................................................................. 14
Site Storage ....................................................................................................... 16
Labeling .............................................................................................................16
Container Filling ................................................................................................. 17
General Requirements for LP-Gas Transfer Operations .................................... 18
Section 5: Plant Operations Procedures ................................................................... 20
5.1 Bulk Plant Operating Procedures ................................................................. 22
5.1.1 Bulk Storage Containers ............................................................................ 22
5.1.2 Loading a Cargo Tank Motor Vehicle (CTMV) Using a Plant Pump .......... 23
5.1.3 Loading a Cargo Tank Motor Vehicle (CTMV) Using a Plant Compressor 26
5.1.4 Unloading a Cargo Tank Motor Vehicle ..................................................... 30
5.1.5 Unloading a LP-Gas Railcar Using the Plant Compressor......................... 34
5.1.6 Preparation and Transportation of DOT Cylinders ..................................... 44
5.1.7 Preparation and Transportation of ASME Containers ............................... 55
5.1.7.3 DOT Regulations Pertaining to Transporting ASME Containers ........... 59
5.1.8 Evacuation of Containers .......................................................................... 62
5.1.9 Purging of Containers ................................................................................. 76
5.1.10 Dispensing LP-Gas................................................................................... 81
5.2 Vapor Distribution Systems .......................................................................... 88
Section 6: General Maintenance and Inspection Requirements .............................. 90
Maintenance Manuals ........................................................................................ 90
Maintenance Procedures ................................................................................... 90
Maintenance Record Keeping ............................................................................ 90
Maintenance Personnel - Training ..................................................................... 91
Physical Protection of Equipment ...................................................................... 91
Container Condition ........................................................................................... 91
Corrosion Control............................................................................................... 92
Containers and Appurtenances.......................................................................... 93
Emergency Shutoff Valves ................................................................................. 94
Hose Inspection and Maintenance ..................................................................... 94
Chart 6.1 (Sample) Preventive Maintenance Records ....................................... 95
Chart 6.2 (Sample) Fixed Equipment Log Repairs, Replacements and
Unscheduled Maintenance ................................................................................ 96
Chart 6.3 (Sample) ESV & Back Check Valve Testing Log ................................ 97
Section 7: Maintenance & Inspection Checklist Procedure ..................................... 98
Section Purpose and Objectives ........................................................................ 98
Scope and Application of Section ...................................................................... 98
Content of Section ............................................................................................. 99
Maintenance and Inspection Procedural Checklist ........................................... 100
Appendix 7.1.................................................................................................... 117
Bulk Storage Containers .................................................................................. 117
Piping .............................................................................................................. 124
Liquid Pump..................................................................................................... 127
Bulkheads ........................................................................................................ 132
Tank Car Unloading Tower .............................................................................. 140
Scales.............................................................................................................. 144
Meters (For Retail Sales Only) ......................................................................... 146
Vaporizers ....................................................................................................... 148
Regulators ....................................................................................................... 148
Electrical Systems ........................................................................................... 149
Section 8: Maintenance of Fire Protection Equipment ........................................... 152
Section Purpose and Objectives ...................................................................... 152
References ...................................................................................................... 152
General Requirements ..................................................................................... 152
8.1 Portable Fire Extinguishers ........................................................................ 152
Chart 8.1 (Sample) Maintenance & Inspection Record Portable Fire
Extinguishers ................................................................................................... 155
8.2 Water-Base Fire Protection Systems ......................................................... 156
Chart 8.2 (Sample) Maintenance & Inspection Record Water-Base Fire
Protection Systems .......................................................................................... 157
Section 9: Manufacturers’ Equipment Information ................................................. 158
Appendix A: References ........................................................................................... 159
Notice and Disclaimer Concerning Liability
The Propane Education & Research Council (PERC) is a non-profit 501(c)6 trade
organization authorized by the Propane Education and Research Act of 1996 (PERA), Public
Law 104-284. PERC was created “to enhance consumer and employee safety and training,
to provide for research and development of clean and efficient propane utilization equipment,
and to inform and educate the public about safety and other issues associated with the use
of propane.”
PERC, NPGA, GPA and the industry members disclaim any liability for any personal injury,
property damage, business losses or other damages of any nature whatsoever, whether
special, indirect, consequential or compensatory, directly or indirectly resulting from the
publication, use, or reliance on this document, or any information, apparatus, method,
process, or similar item disclosed in this document. This disclaimer of liability shall apply
even if such loss or damage results, in whole or in part, from any acts or omissions of or by
any negligence on the part of PERC, NPGA, GPA or industry members or any persons who
contributed to the development of the information contained in this document. PERC,
NPGA, GPA and industry members make no warranty or guaranty as to the accuracy or
completeness of any information published in this document.
The procedures and information in this document are intended to implement the standards
set forth in the documents referenced with capabilities of the personnel and equipment
available. It does not create new standards or criteria for compliance. The order of steps in
any procedure may or may not be of importance. This material is not sold nor is it a product
of any consulting or engineering activity.
Users of this document should consult the law of their individual jurisdictions for codes,
standards and legal requirements applicable to them. This document is not intended nor should
it be construed to (1) set forth policies or procedures which are the general custom or practice in
the propane industry; (2) to establish the legal standards of care owed by propane distributors to
their customers; or (3) to prevent the user from using different methods to implement applicable
codes, standards or legal requirements.
i
Propane Education &
Research Council
Industry Feedback Form
Program
Operations & Maintenance Manual
Section Page
Action Requested
Subject
Note: The subject should clearly and accurately express the main idea of your
suggestion.
For Example: Updated Distance Requirements.
ii
Propane Education &
Research Council
Industry Feedback Form
Name:
Company:
Address:
Phone:
Email:
You will receive a response, once the Industry Feedback Form is received. If you
do not receive a response within an appropriate time, please contact PERC at
(202) 452-8975.
iii
Operations & Maintenance Handbook Section 1
for LP-Gas Storage Facilities Introduction – Purpose,
Scope and Use of Handbook
New requirements related to the operations and maintenance of bulk plant and industrial
plant LP-Gas systems were introduced in the 2001 Edition of NFPA 58, Liquefied
Petroleum Gas Code (Code) and expanded in the 2004 Edition. Specifically, in Chapter
14 of the 2004 Edition, the requirements summarily included:
These requirements also included a provision that equipment owners and operators
must make sure that the procedures are updated “… whenever a major change occurs
that affects the operation of a system and prior to its startup.”
Three important changes were subsequently made in Chapter 14 of the 2008 edition of
NFPA 58:
Because these requirements have been placed on essentially all retailers, PERC has
provided funds to develop and maintain a “tool” that contains a standardized approach
4
Operations & Maintenance Handbook Section 1
for LP-Gas Storage Facilities Introduction – Purpose,
Scope and Use of Handbook
and format for LP-Gas retailers and industrial customers to readily use in order to meet
these requirements.
This Operations and Maintenance Handbook for LP-Gas Bulk Storage Facilities is both a
template and foundation document that allows owners and operators of LP-Gas bulk
plants and industrial plants to easily establish and have available in a common location
the necessary site information, procedures, manuals and charts used by and for:
Plant personnel (employees and contractors) as ready reference for support and
guidance in emergency situations, plant operations (including startup and
shutdown), and maintenance activities.
Record keeping associated with the required inspection and maintenance
activities.
The authority having jurisdiction to verify the continuing safety of the LP-Gas
facility.
LP-Gas terminal operations (i.e., refrigerated storage, marine, pipeline and rail) are
typically mandated to meet the requirements of the OSHA Process Safety Management
(PSM) regulation under 29 CFR 1910.119 since they do not qualify for a “retail
operations” exemption to the standard. This handbook does not address the details of
those OSHA regulatory requirements.
While this handbook is not intended to be a training manual, every effort has been made
to be consistent with the procedural, technical and instructional information provided in
the Certified Employee Training Program (CETP) materials. Additionally, this handbook
does not intend to introduce, by reference or suggested best practice, any new practices
that should be considered additions to the regulatory agenda.
Scope of Handbook
Following this first introductory section, the handbook is divided into eight other sections.
Section 2, “General Facility Information,” provides the template for itemizing critical
emergency contact information for use by facility personnel, and with emergency
responders and any authority having jurisdiction. The information in this section
should be completed by the owner or operator of the facility and updated when
relevant changes occur.
5
Operations & Maintenance Handbook Section 1
for LP-Gas Storage Facilities Introduction – Purpose,
Scope and Use of Handbook
Additionally, Appendix A, “References,” has been provided which lists the documents
that are referenced throughout this handbook. These references provide further
detailed information or work procedure instructions, reference data or training
information in order to meet the intent and requirements of the Code.
The ultimate purpose of this handbook is to be a functional document for each LP-Gas
storage facility and serve (in a combined role) as your facility’s operations, maintenance
and emergency procedures manuals, consistent with the requirements of Chapter 14 of
NFPA 58-2014.
Not all the information and materials contained in this handbook apply to each facility.
Also, it is possible that special situations or operations not encountered in a typical LP-
6
Operations & Maintenance Handbook Section 1
for LP-Gas Storage Facilities Introduction – Purpose,
Scope and Use of Handbook
Gas storage facility might arise at any given site. Every effort has been made to address
the numerous scenarios that can occur in a bulk plant or large storage facility. However,
unique situations might not be included in this handbook. Therefore, each section should
be thoroughly reviewed by the owners and operators to include all applicable data,
information and procedural steps. Materials that are not applicable to your particular
facility can be removed.
At the beginning of each handbook section, the purpose and objective(s) of that section
are provided so that the readers, whether owners/operators or field personnel, can
understand the intent of the section and the scope of the regulatory subject that is being
addressed. Each section then has specific instructions regarding how to use its content
in order to achieve compliance with that regulatory requirement.
By nature of the subject matter, the sections differ in their respective approaches in
addressing each specific regulatory topic. For example, Section 5 on Plant Operations
Procedures should be considered as a “template” for the operations conducted at your
facility. Additions or deletions to these procedures might be necessary in order to
accurately reflect local operations and conditions. Section 7 provides a checklist and
guidance information for performing and documenting maintenance and inspection
activities required by the Code. Again, not all subparts will necessarily be applicable; so
those portions of the checklist can be removed. Other items might need to be added
under special circumstances.
Again, it is important to read the information at the beginning of each section so that the
information contained can be used most efficiently and effectively, especially for use by
plant and field personnel.
When the information and procedures are developed into your facility’s operating,
maintenance and emergency procedures manual(s), these procedures and manual(s)
must all be available at the facility to which they apply and accessible to all
employees and users, including any authority having jurisdiction. Per NFPA 58,
maintenance manuals for normally unattended facilities are allowed to be stored at a
location where they are accessible for maintenance personnel serving the unattended
location.
The procedures should be reviewed with all appropriate employees and users who are
expected to carry out the relevant job functions at the time when the procedures are
initially developed and again when changes to the procedures occur.
NFPA 58 requires that all operation and maintenance procedures must be updated
whenever a change occurs that effects the operations or maintenance, and prior to
startup.
7
Operations & Maintenance Handbook
for LP-Gas Storage Facilities Section 2
General Facility
Information
8
Operations & Maintenance Handbook Section 3
for LP-Gas Storage Facilities Emergency Procedures
Plan
Issue Date:
This safety data sheet and the information it contains is offered to you in good faith as accurate. This
Supplier does not manufacture this product but is a supplier of the product independently
manufactured by others. Much of the information contained in this data sheet was received from
sources outside our Company. To the best of our knowledge this information is accurate, but this
Supplier does not guarantee its accuracy or completeness. Health and safety precautions in this
safety data sheet may not be adequate for all individuals and/or situations. It is the user's obligation to
evaluate and use this product safely, comply with all applicable laws and regulations and to assume
the risks involved in the use of this product.
9
Operations & Maintenance Handbook Section 3
for LP-Gas Storage Facilities Emergency Procedures
Plan
Local Street/Highway
North
Vehicle Gate
Pedestrian Gate
Evacuation
Assembly Remote
Fire
Point Shutdown
Hydrant
P
A
R
Office and Transports and Bobtails, Only, In This Area
Retail Store K
I
N
G Loading/Unloading Station
Electrical
Panel Internal
ESV Valve
S
T 30,000
Service and O
Cylinder Delivery GWC
Cylinder Loading R
Filling Dock Trucks Only In A
This Area G
E
10
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
This section provides guidance for achieving compliance with those referenced requirements
related to general bulk plant/facility operating procedures and safety requirements, exclusive of
emergency procedures that have already been addressed in Section 3 of this handbook.
Guidance specific to startup, operation and shutdown of the transfer system and equipment are
addressed in Section 5.
Site Accessibility
Except where business activities dictate, customers and the general public should be restricted
from areas where LP-Gas is stored, transferred and handled.
Signs and other forms of markings within the site or on the equipment should provide
appropriate warnings and sufficient information for personnel onsite to work safely and perform
duties consistent with procedures and work practices.
Referring to Figure 4.1, basic fire prevention concepts demonstrate that the elimination of any
leg of the “fire triangle” will eliminate the possibility of combustion occurring.
Figure 4.1
11
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
Therefore, the control of combustible materials and ignition sources is critical to the operating
safety of any LP-Gas facility, depending on specific site conditions.
Combustible Materials
Weeds, long dry grass, wooden materials (e.g., limbs, planks, pallets) and paper products are
all examples of combustible materials (i.e., “fuel”) that need to be controlled and kept at a
sufficient distance from LP-Gas storage containers in order to reduce the potential for a fire that
could occur adjacent to the equipment. All these and similar combustible materials must be
maintained or stored such that they are no closer than 10 feet to the container. Additionally,
where single containers (constructed as portable containers) are used for temporary storage,
they must not only be placed on level and firm surfaces but they also must be kept clear of
combustible materials (as defined in this paragraph) for a minimum distance of 10 feet.
Ignition Sources
Smoking
Another significant fire prevention measure is the control of ignition sources. First and foremost,
smoking prohibitions for each site must be established. As minimum requirements, no person,
whether that person is an employee, contractor or site visitor, can be allowed to use or carry
lighted smoking materials under the following situations:
When he or she is on or within 25 feet of a vehicle that contains LP-Gas, liquid or vapor.
• When he or she is within 25 feet of a point of transfer while transfer operations are in
progress.
Further smoking restrictions or prohibitions may be established by the owner or operator of the
site.
Open flames and other ignition sources (such as non-explosion proof electrical equipment and
vehicles) must be controlled on an on-going basis for general fire prevention purposes. Specific
control measures that must be implemented include:
Prohibiting open flames and all other sources of ignition in pump houses, cylinder filling
rooms and other locations where the presence of LP-Gas liquid or vapor is likely.
12
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
Prohibiting open flames, cutting or welding tools, sparking hand tools, portable electric
tools (including two-way radios and cell phones) and non-explosion proof electrical
equipment within the distances specified per Section 7.2.3.2 in NFPA 58.
Installing all fixed electrical equipment and wiring within a classified area specified in
Table 6.23.2.2 in accordance with the requirements of NFPA 70, National Electric Code.
While open flames and other ignition sources are not prohibited in site locations where LP-Gas
equipment has been purged of all liquid and vapor, appropriate measures should be taken to
make sure that these locations remain gas-free.
Sources of ignition must be eliminated during all LP-Gas transfer operations, including the
periods when connections and disconnections are being made and while LP-Gas is being
vented to the atmosphere. During transfer operations the following specific precautions must be
taken:
Internal combustion engines that are within 15 feet of the point of transfer must be shut down,
except for:
Smoking or the use of open flames, sparking hand tools, portable electric tools (including
two-way radios and cell phones), non-explosion proof electrical equipment or any other
equipment that has the energy to ignite LP-Gas must be prohibited within 25 feet of the
point of transfer.
Metal cutting, grinding, oxygen-fuel gas cutting, brazing, welding, soldering or welding
(i.e., any “hot work” procedures) must be prohibited within 35 feet of the point of transfer.
Furthermore, if any of these procedures have been performed within this zone of 35 feet
prior to the transfer operation, the affected materials must be cooled to a temperature
below the ignition temperature of LP-Gas (i.e., approximately 900ºF) before starting the
transfer.
For those facilities where LP-Gas is dispensed into a vehicle container for the purpose of
using the LP-Gas as a fuel source (e.g., a recreational vehicle or a propane-fueled
vehicle), all ignition sources associated with the vehicles must be turned off. Control
measures include (but are not limited to):
13
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
(a) Shutting down the engines of the vehicle being fueled and those
waiting to be fueled; and
(b) Extinguishing pilot lights and shutting off other ignition sources
within recreational vehicles.
Survey your facility and list the ignition sources in the data box, below. Insert an additional
sheet, if necessary.
In general, stationary containers used for LP-Gas bulk plant storage must be designed,
fabricated, tested and marked in accordance with the requirements of the ASME Boiler
and Pressure Vessel Code, Section VIII or the API –ASME code if constructed prior to
July 1, 1961. The agency having jurisdictional authority (usually, that associated with
“boilers”) should be contacted for specific requirements related to compliance and
continued service use. The NFPA LP-Gas Code Handbook (2014 Edition) provides
additional background information, guidance and reference material.
For your record keeping, insert information from the data plates (nameplates) on the
ASME storage containers at your facility into Table 4.2. For additional ASME storage
containers, add another table and insert the appropriate information.
14
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
The requirements for internal valves and other valve/line closure components for liquid
and vapor openings (both inlet and withdrawal) on ASME containers over 4,000 gallons
are defined in §5.7.4.2 of NFPA 58. Alternate provisions for installation of ASME
containers, including underground and mounded tanks of 2,001 gallon through 30,000
gallon water capacity are further provided in §6.28 of NFPA 58.
Portable Cylinders
These containers are designed, fabricated, tested and marked in accordance with the
U.S. Department of Transportation (DOT). This handbook is not intended to reiterate the
DOT requirements with respect to these aspects of the regulations. For details, refer to
Title 49, Code of Federal Regulations, “Transportation”. Again, the NFPA LP-Gas Code
Handbook (2014 Edition) provides additional background information, guidance and
reference material on these containers, also.
15
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
Site Storage
A number of considerations must be taken into account when storing portable cylinders in a bulk
plant. These include:
Positioning any cylinder that has a nominal LP-Gas capacity greater than 1 lb (0.45
kg) such that the pressure relief valve is in direct comunication with the vapor space
of the cylinder.
When storing LP-Gas cylinders inside buildings (in accordance with §8.3 of NFPA
58, they cannot be located near any areas of egress (e.g., exits, entrances, and
walkways). Also, when determining the maximum quantity of LP-Gas that can be
stored indoors, each cylinder stored indoors must be considered to be a full cylinder.
In situations where a portable container is being used for temporary stationary storage in a bulk
plant, it must be placed on a firm flat surface (e.g., concrete pad, pavement or firm earth) while
in use as such.
Labeling
The representative inlet and outlet connections for both the liquid and vapor spaces
must be labeled as such. While not required, color coding of the associated piping and
valves can be used as an identification aid in addition to labeling.
Connections for gauges and pressure relief devices are not required to be labeled.
Portable Cylinders
When LP-Gas cylinders are to be stored or used at the same sites with other
compressed gases, each cylinder must be labeled to identify its contents. The labeling
should be consistent with the requirements of ANSI/CGA C-7, Guide to the Preparation
of Precautionary Labeling and Marking of Compressed Gas Containers.
16
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
Container Filling
Those cylinders in the 4 lb - 40 lb capacity range that are exempt from having a listed
OPD installed include:
Every container that is designed to be filled on a volumetric basis must be equipped with
a fixed maximum liquid level gauge in order to indicate the maximum fill level for the
service in which the container is to be filled or used.
For bulk plants or specific points of transfer that are designated as “low emission
transfer” locations (i.e., to meet environmental regulatory requirements or to take
advantage of reduced installation distances), fixed maximum liquid level gauges cannot
be used to determine the maximum filling limit. Therefore, the maximum permitted filling
limit must be determined by weight or other approved means.
Where variable liquid level gauges are also used for filling containers (usually large
capacity storage vessels), these devices must meet the following requirements to
facilitate reading the gauges:
The gauges must show the maximum liquid level (in inches, metric units or
percent capacity of the container) when installed in containers greater than 1200
gallon water capacity; and
Markings must indicate the maximum liquid level at liquid temperatures from 20ºF
to 115ºF and in increments not greater than 20ºF; and
The system nameplate and/or the gauge must have markings indicating the
various liquid levels from empty to full; and
Dials of rotary gauges or magnetic float gauges must indicate whether they are
for cylindrical containers or spheres, and if the service is aboveground or
underground; and
17
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
Dials of gauges for aboveground (only) containers that have a water capacity of
more than 1,200 gallons must be marked to note this fact.
Personnel
Individuals whose job duties are covered by NFPA 58 must be trained on proper
handling procedures specific to their duties. They must also receive training on
emergency response procedures.
Persons whose primary duties include transferring liquid LP-Gas or transporting LP-Gas
must receive training on the following:
Additionally, NFPA 58 requires that refresher training be provided every three (3) years,
and that the training be documented.
During the transfer operation, from the time of original connection through the final
disconnect, at least one qualified person must be in attendance. “In attendance” means
that the individual must have line of sight of the transfer operation and be in a position to
physically take action if required during the operation.
These persons are also responsible to make sure that the equipment and containers
used in the transfer operations are designed for the type of LP-Gas that is being filled
into the receiving container.
Prohibitions
Compressed air, oxygen or any oxidizing gases cannot be injected into containers for
the purpose of transferring LP-Gas liquid. These gases can create a flammable gas
mixture within the container.
Similarly, when evacuating containers, no liquids or gases other than LP-Gas may be
injected into the containers.
18
Operations & Maintenance Handbook Section 4
for LP-Gas Storage Facilities General Operations & Safety
Requirements
Except for cargo tank service, ASME containers of 3,000 gallons water capacity or less
used to store anhydrous ammonia must not be converted to LP-gas fuel service.
LP-Gas stored or used in systems within the scope of this code shall contain less
ammonia than the quantity required to turn the color of red litmus paper to blue. The
initial fill of LP-Gas in a transportation or storage system that has been converted from
ammonia to LP-Gas service shall be tested for ammonia contamination prior to being
used or transferred from that system.
Brass fittings are commonly used in LP-Gas service. Ammonia will damage these brass
system components by a corrosion phenomenon commonly called “season cracking” (a
form of stress corrosion cracking), potentially resulting in unanticipated and premature
failure. It is important that LP-Gas is free of ammonia. Procedures on testing LP-Gas for
ammonia contamination are in Annex A of NFPA 58 (A.4.5).
19
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
NFPA 58-2014 requires that new and existing bulk and industrial plants prepare and maintain
written operating procedures in a common location. This section provides guideline operating
procedures for bulk plant facilities and industrial plants.
While operating procedures are typically similar at LP-Gas bulk storage facilities, the equipment
can vary in size (i.e., storage capacity), design, layout, equipment complexity or function (e.g.,
rail unloading facilities, cylinder filling operations, on-site commercial dispensers).
This handbook section should be considered to be a “template” for the operations conducted at
any specific LP-Gas bulk storage facility, and additions or deletions to these procedures could
be necessary. Therefore, owners or site management and supervisors should consider site-
specific features and conditions that need to be included, modified or deleted in the information
in this section in order to accurately reflect local operations and conditions. With these
changes, operators, technicians, drivers and other site personnel can use this document as the
operating procedures required by NFPA 58.
Operating procedures for large-volume storage and vapor distribution systems at customer
locations are also addressed in this section.
Although NFPA 58 references the need for documented operating requirements with respect to
refrigerated storage, marine and pipeline LP-Gas systems, these systems (which can vary
significantly in design and complexity) also come under the authority of jurisdictions which have
very specific and detailed requirements within EPA’s Risk Management Plan, OSHA’s Process
Safety Management and US DOT’s Office of Pipeline Safety. Therefore, these systems are not
addressed in this handbook.
Content of Section
The chart below is a guide for operators to easily identify which sections are appropriate for their
specific applications. Applicable CETP modules are included in the table for easy reference to
additional instructional information and materials.
The “CETP-2014 Reference” directs the user to the related module of the training materials
having a 2014 copyright date.
For CETP-2014, the references are constructed such that the first three letters designate the
course, followed by the applicable module and lesson (e.g., BPP-7-1).
20
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
21
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Proper Personal Protective Equipment (PPE) should be worn when applicable. Check your
company policy for specific PPE required.
Startup
1. Before beginning any operation make sure the transfer equipment is in good
condition, the bulk storage container is safe to be filled, and the surrounding
area is free from hazards that may constitute a source of ignition.
2. Check to see that all the appropriate manual valves (i.e., globe, angle, or ball)
are open on the bulk storage containers.
3. If the container has manually operated internal valves, make sure that the
emergency shutdown system is operational and that internal valves are
opened.
Operation
22
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Shutdown
1. Check to see that all the appropriate manual valves (i.e., globe, angle, or ball)
are closed on the bulk storage containers.
2. If the container has remotely operated internal valves, make sure that these
valves are closed by releasing the pressure in emergency shutdown system
or by pulling the cable for the system.
5.1.2 Loading a Cargo Tank Motor Vehicle (CTMV) Using a Plant Pump
Before the filling operation, the person loading the CTMV (bobtail or transport) should be
familiar with the bulk plant layout and operating procedures.
When you first arrive at the bulk plant to load your bobtail:
• Check for hazards that might create an unsafe filling condition.
• Check to see that the liquid fill connection on the cargo tank is at least 10 ft from the
nearest bulk storage container. Always contact your supervisor to determine how to
position your bobtail at the bulkhead in a way that maximizes the shearing effect of the
hoses and piping in the event of a pull-away.
• Set the parking brake and turn off the engine.
• Chock blocks or wheel stops are required in front of and behind a rear wheel to prevent
the vehicle from rolling forward or backward.
• Remove any ignition sources within 25 ft of the transfer point. Shut down any internal
combustion engines within 15 ft of the transfer. Cease metal working operations
(grinding, welding, brazing, etc.) within 35 ft of the point of transfer.
23
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
• Check the liquid level gauges on your cargo tank and record how much propane is in the
tank before beginning the load operation.
Before connecting the hoses to begin loading operations, you must make sure all appropriate
valves are closed and hoses are in good working condition.
• Make sure the liquid fill and vapor equalizing valves on the cargo tank are closed.
• Remove the dust caps from the valves, inspect them for damage and wear, and if
necessary, replace defective gaskets.
• Make sure the bulk plant liquid and vapor hose-end valves are closed.
• Inspect the transfer hoses, couplings, valves, and connectors, including ACME threads,
to make sure they are free of defects or damage.
• Connect the plant liquid hose to the liquid fill valve on the bobtail cargo tank. Whenever
handling the hose, be sure to point the end of the hose away from your body.
• Tighten the plant liquid hose into the filler valve of the cargo tank by moving the hose
assembly up and down while turning the ACME connector. Once the connection is hand
tight, give it an additional quarter turn using a spanner wrench.
• Connect the vapor equalizing hose between the storage container and the cargo tank
and hand tighten so it doesn’t leak.
NOTE: In accordance with company policy, operate the ESVs at the loading bulkhead to be
sure they are functioning properly. If they are not operating properly, do not connect the
transfer hoses between the storage container and the cargo tank on the bulk delivery
vehicle.
Before filling the cargo tank, your company may require you to perform a sniff test and verify
product odorization.
To do this:
• Vent a small quantity of propane through the vent valve located on the plant liquid hose.
• Sniff the area immediately after the liquid vaporizes.
• If you can smell propane odorant, proceed with the loading operation.
24
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
• If you cannot smell propane odorant or smell anything unusual, do not load the cargo
tank. Contact your supervisor immediately and tell others in the area not to load until
approved by the facility manager or supervisor.
During the transfer operation, a qualified person must be in attendance at all times. This means
that you must be within 25 ft of the cargo tank and have an unobstructed view of it in order to
monitor the condition of the transfer operation, and handle any emergencies.
Be alert for signs of erratic pump operation during the transfer. If a leak or
fire develops during the transfer, close all ESVs immediately and stop the
pump, if you can do so safely. Move upwind and away from any
uncontrolled release of propane.
When the loading operation is complete, do the following to prepare the bobtail for
travel:
• Bleed down and disconnect the plant liquid hose from the bobtail liquid fill connection.
• Bleed down and disconnect the vapor equalizing hose from the vapor equalizing
connection on the bobtail.
• Replace the dust caps on the bobtail liquid fill and vapor equalizing connections.
• Replace the dust caps on the plant liquid and vapor hoses and store them as required.
• Walk around the bobtail and check for any obstacles that may be in its path.
• Remove the chock blocks and stow them in their travel compartment or holders.
• Move the vehicle, but only after it has been determined the path is clear and the
discharge of propane has dissipated.
25
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
5.1.3 Loading a Cargo Tank Motor Vehicle (CTMV) Using a Plant Compressor
Identifying Steps for Propane Transfer Using the Plant Compressor to Fill the Bobtail
Note: Procedures for filling bobtails are based on practices commonly used in the propane
industry, manufacturers’ instructions, and provisions in NFPA 58. Before the filling operation, be
sure to see your supervisor for a copy of your plant layout, including bulk plant equipment,
piping functions, and company operating procedures.
Step 1:
Position the bobtail.
• Position the bobtail at the loading bulkhead, with the fill connection on the cargo tank at
least 10 feet from the nearest bulk storage container.
• Set the vehicle parking brake.
• Shut down the engine.
• Place chock blocks in front and behind a rear wheel to prevent movement of the vehicle.
Step 2:
Examine the plant piping and flow control valves.
Determine how vapor will move from the cargo tank to the suction side of the
compressor and on to the bulk storage tank(s).
Step 3:
Set the liquid level gauges on the bobtail.
• Before connecting the hoses from the bulk propane storage tank to the bobtail,
determine the maximum permitted filling level. This is determined by obtaining the
specific gravity of your propane from shipping papers and observing the liquid propane
temperature on the thermometer located either in the cargo tank or in the storage
container at the plant.
• When a storage container is filled by volume, the filling stops when the volume of the
liquid inside the container reaches a certain percent of the container’s water capacity.
The maximum permitted volume is indicated by a fixed maximum liquid level gauge. The
gauge extends inside the container and measures the level of the liquid. The gauges
most often used on bobtails are the fixed maximum liquid level gauge and the variable
liquid level gauge.
If either the temperature or the specific gravity is not known, the float gauge cannot be
used to determine the correct set point and therefore, the maximum permitted filling level
of the cargo tank cannot be determined. In that case, the fixed maximum liquid level
gauge must be used to determine the maximum filling level.
26
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Step 4:
Inspect the compressor and check the crankcase oil level in the sight glass, or by using the
dipstick
Step 5:
Connect the liquid fill and compressor vapor hoses to fill the cargo tank.
• Before connecting the transfer hoses, make sure all sources of ignition within 25 ft of the
transfer point are removed. Internal combustion engines within 15 ft of the point of
transfer must be shut down while transfer operations are in progress, with exceptions as
listed in NFPA 58. Cease metal working operations (grinding, welding, brazing, etc.)
within 35 ft of the point of transfer.
• Carefully inspect the liquid and vapor transfer hose assemblies. If any defect is found,
discontinue the operation, notify your supervisor and do not resume loading until the
hose defect has been eliminated. If another loading bulkhead is available, move to it
after notifying your supervisor and ensuring that a warning notice is placed on the
defective hose.
• Check to see that the fill and vapor equalizing valves on the bobtail are closed. Remove
the dust covers from the valve connectors. Inspect the valve connectors for damage and
wear and if necessary, replace any defective O-ring or flat gasket.
• Check to see that the liquid and vapor hose-end valves are closed. In accordance with
company policy, operate the emergency shut-down valves (ESVs) at the loading
bulkhead to be sure they are functioning properly. CAUTION: If the ESV’s do not operate
properly, do not connect the transfer hoses.
• Connect the liquid plant hose-end valve to the fill valve on the bobtail. Carry it in the
palm of your hand pointed away from your body. Tighten the plant hose-end valve into
the filler valve of the bobtail by gently moving the hose-end valve up and down while
turning the ACME connector. Once the connector is hand-tight, turn the connector an
additional 1/8 to 1/4 turn using a spanner wrench, tapping the handle of the spanner
wrench with the palm of a gloved-hand.
• Slightly open the liquid hose-end valve and check for leakage. If leakage exists, close
the hose-end valve and disconnect the ACME adapter after the connection has bled
down and is de-pressurized. Examine the condition of the O-ring or flat gasket in the
cargo tank filler adapter and replace as needed.
• Examine the ACME threads on the hose-end adapter and the bobtail filler connection. If
either is excessively worn so the connection leaks with a new O-ring or gasket, replace
the worn fitting or adapter before proceeding with the loading operation.
• Connect the vapor equalizing hose between the storage container and the bobtail.
Follow the procedures used when connecting the plant liquid transfer hose with the
exception of the use of the spanner wrench.
Step 6:
Sniff test to verify propane odorization.
27
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Step 7:
Open the vent on the compressor’s liquid trap to verify that liquid is not present in the vapor
hose and suction line; it may severely damage the compressor and ultimately produce leaks at
the head gasket or oil sump.
Step 8:
Verify the 4-way valve is in the proper position for loading the bobtail and check all in-line valves
and bulk tank valves for their proper open or closed position.
Step 9:
Check to see that all shutoff valves are open in the liquid transfer, vapor suction and vapor
discharge lines.
Step 10:
Start the compressor in accordance with manufacturer’s instructions.
• Vapor compressors remove vapor from the receiving tank, compress the vapor to a
higher pressure, and move it through piping into the supply tank. The higher pressure
vapor in the supply tank forces liquid to move to the receiving tank where the pressure
has been reduced by the action of the vapor compressor.
Step 11:
Verify the proper filling limit set for the cargo tank, using the thermometer reading and the liquid
level gauge index.
Step 12:
Monitor the cargo tank filling and stop the compressor when the proper liquid level is reached,
or if any abnormal operating condition is noticed.
Step 13:
Close all valves in the transfer hoses.
Step 14:
Close all valves in both the suction and discharge vapor piping circuits. Close the ESV(s) at the
transfer bulkhead and the appropriate liquid and vapor valves in the bulk storage tank(s), if
applicable.
28
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Step 15:
Disconnect the transfer hoses and prepare the bobtail for travel.
• Bleed down the gas trapped between the cargo tank filler valve and the transfer hose-
end valve and disconnect the liquid hose from the Bobtail fill valve.
• Bleed down the gas trapped between the vapor return valve and the vapor equaling
hose-end valve and disconnect the vapor hose from the vapor equalizing valve on the
bobtail.
• Replace the dust caps on the fill and vapor equalizing valves.
• Replace the dust caps on the liquid and vapor hose-end valves. Store the hoses as
required.
• If applicable, stamp or print the loading ticket.
• Fill out any company inventory forms and process them as required.
• Before removing the chock blocks, walk around the Bobtail and check for any obstacles
that may be in its path.
• Move the truck only after it has been determined the path is clear and any discharge of
propane has dissipated.
• If for any reason the transfer operation is interrupted, or the attendant must leave the
area, the compressor must be shutdown and transfer hoses disconnected as outlined in
steps (12)-(14). DO NOT leave transfer hoses connected to a Bobtail while unattended.
29
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Procedures for liquid transfer operations at LP-Gas bulk storage tanks from transports are
based on common industry practices, manufacturer’s instructions, provisions listed in NFPA 58-
2014 and U. S. Department of Transportation (DOT) cargo tank unloading regulations.
Furthermore, the major steps in the unloading procedures will vary according to the emergency
discharge system used on the CTMV.
These procedures are designed to be as universal as possible, and are to be used as a guide
only. They do not replace company policies or federal, state and local codes. Be sure to check
company policy and state and local codes before beginning the unloading operation. Before
performing the unloading operation, you should review bulk plant layout and operating
procedures. Make sure you are familiar with the bulk plant equipment, piping functions, and
company operating procedures.
U.S. DOT requirements for drivers and operators unloading cargo tank motor
vehicles (CTMV) are set out in several sections of the Code of Federal
Regulations. The principal requirements can be found in the following
references:
• Unloading Attendance Requirements – 49 CFR 177.834
• CTMV Safety Check – 49 CFR 177.840(m)
• Unloading Procedures* – 49 CFR 177.840 (q)
• Emergency Discharge Control – 49 CFR 178.337-11, 173.315(n)
* for cargo tanks with capacities larger than 3500 water gallons, and
cargo tanks in other than metered delivery service
3. The qualified person attending the unloading operation must be alert and
remain within 25 feet of the cargo tank when the CTMV internal self-
closing stop valve is open.
30
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
New transport cargo tanks placed into service after July 1, 2001, must be
equipped with either a passive emergency shutdown system or, if the transport is
used in metered delivery service, a remote (radio frequency) shutdown system
with a query feature for unloading operations lasting more than 5 minutes. Cargo
tanks that are used in both metered and non-metered service must have both
types of emergency shutdown systems.
Startup
1. Inspect the transfer area, before giving the driver the signal to enter the plant
area.
2. Spot the CTMV (most commonly, a “transport”) and guide it into position at
the unloading bulkhead. To prevent unnecessary wear on the PTO (power
take-off) drive shaft and the pump during unloading, the centerlines of the
tractor and trailer should coincide.
4. Place chock blocks or wheel stops at the front and back of one of the tractor
drive wheels.
31
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Operation
2. Review and follow company procedures for checking the operation of the
ESVs and pull-a-way protection installed in the plant. If the ESVs will not
operate properly, do not continue the transfer operation. Notify the bulk
plant’s manager or supervisor.
3. Check the manual shutoff valves on the transport liquid and vapor
connections to be sure they are fully closed. Slowly remove the dust caps.
4. Remove the dust caps from the connectors on the transfer hoses. Check the
connectors to be sure they are clean. Check the O-rings on the valve
connectors to be sure they are in good condition. If necessary, clean the
connectors with a rag and replace worn, flattened, or damaged O-rings
before making connections to be transport.
6. Connect hoses between the transport and the bulkhead. When using ACME
connectors, spin on the connectors until they are hand-tight. While tightening
the connectors, move the hose or hose end valve up and down slightly to
prevent the threads from seizing. When each connection is hand-tight,
tighten it to “wrench tight” with a spanner wrench. Never bang on the
connector with the dust cap, a hammer, or other device.
7. Check each connection for leaks by isolating it from the system and charging
it with LP-Gas. If any connection leaks, close all valves and retighten the
connection. If the leak persists, examine the condition of connection o-rings
or gaskets, and replace them if they are defective.
8. Verify that the LP-Gas being delivered to the bulk plant is odorized by
conducting a sniff test or other means, and document the results.
32
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
9. When all valves are fully open, start the pump by engaging the PTO. Listen
carefully for sounds of erratic pump behavior and check the sight gauge or
flow indicator to be sure liquid is flowing through the system.
[Note: If an excess-flow valve slugs shut, stop the pump; then, reopen the
excess-flow valve by equalizing pressure across the valve before continuing.]
10. Unload the transport tank. Remember that a qualified person must be
present during the entire transfer operation to handle emergencies and
monitor the condition of the transfer system. Monitor the liquid level gauges
in the plant storage tanks carefully during the operation. If possible, equalize
pressure between the transport and the plant storage tank.
11. When a tank reaches its maximum permitted filling level, stop the pump and
adjust the valves in the plant piping to route the remainder of the load to
another tank.
Shutdown
1. When the plant storage tank reaches its maximum permitted filling level or
the transport tank is empty, stop the pump and immediately close all liquid
and vapor lines involved in the transfer operation.
2. Bleed down and disconnect the hoses. Store them away as necessary.
Caution: Never disconnect any hose until the LP-Gas trapped in the
connection has been safely bled off. This should be done through
either the bleeder valve on the hose-end valve or a pipe-away
adaptor in the transport or bulkhead connections.
3. Replace all caps on hose-end valves and on transport and plant liquid and
vapor connections.
4. Complete the plant unloading form, any necessary accounting forms, and the
return bill of lading.
6. Before removing the chock blocks, walk around the CTMV and check for any
obstacles that may be in its path. When determined to be clear, remove the
chock blocks and store them on the vehicle.
7. Move the truck only after it has been determined the path is clear and any
discharge of LP-Gas has dissipated.
33
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Procedures for liquid transfer operations at LP-Gas bulk storage tanks from a
railcar are based on common industry practices, manufacturer’s instructions, and
provisions listed in NFPA 58 and U.S. DOT regulations. These procedures are
designed to be as universal as possible, and are to be used as a guide only.
They do not replace company policies or federal, state and local codes. Check
company policy and state and local codes before beginning the unloading
operation.
Before the unloading operation, you should review bulk plant layout and
operating procedures. Make sure you are familiar with the bulk plant equipment,
piping functions, and company operating procedures.
DOT regulations require employers to train and test every employee directly
involved in the transportation of hazardous materials, including personnel who
inspect, load or unload pressurized railcars used in LP-Gas transportation.
34
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Startup
2. Climb the unloading riser and lower the platform to gain access to the dome
and tank car openings.
3. Be sure the platform is properly seated and secured before crossing over to
the tank car. Exercise caution when climbing or working on the riser,
especially in wet or icy weather.
4. Before opening the dome, be sure that all sources of ignition have been
removed from the area as outlined in Section 4. Also, avoid creating sparks
when opening or working in the dome.
Caution: If one of the fittings is leaking, the dome might be filled with
LP-Gas vapor.
35
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
8. Rail Car contents must be verified with Shipping Paper before making hose
connections.
9. Gauge the contents of the railcar by using the slip tube gauge. First, open
the bleeder valve at the top of the gauge and raise or lower the tube until a
white plume of mist vents out of the bleeder orifice indicating that the slip tube
is in contact with liquid LP-Gas. A series of graduated markings on the slip
tube indicates the distance in inches and feet from the top of the tank to the
surface of the liquid, also known as the "outage" of the railcar.
The slip tube is always under high pressure and can cause serious
injuries if it springs up quickly or unexpectedly. Therefore, always
exercise caution when working around the slip tube gauge by
standing to the side of the slip tube gauge before releasing the brake
or safety catch.
10. Once the outage of the railcar is read, convert the outage to gallons by using
the outage table (sometimes called a “strapping chart”) furnished by the
shipper or railcar manufacturer.
Even a relatively small error in reading the slip tube gauge can make
a large difference in calculating the number of gallons in the tank.
Therefore, it is important to measure the railcar outage at least twice
to be sure of getting an accurate reading.
11. Determine the maximum amount of LP-Gas that can be transferred to the
plant bulk storage tanks. To avoid accidentally overfilling the tank, calculate
the maximum amount of LP-Gas that can be safely added.
Even if the plant has more than one storage tank, determine how much LP-
Gas can be safely added to each tank. If a single tank will not hold the entire
load, use calculations to distribute the load and notify the bulk plant manager
36
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
or supervisor.
Gauge the contents of the plant storage tank with the rotary or float gauge
installed in the tank head. Record the reading on the company form or on a
worksheet.
If there is more LP-Gas in the railcar than the plant tank(s) will hold safely,
notify the bulk plant manager or supervisor.
12. Before connecting the liquid and vapor transfer hoses between the railcar and
the unloading riser check the manual shutoff valves on the railcar liquid and
vapor connections to make sure they are fully closed. Then, carefully remove
the plugs.
LP-Gas may vent around the plug threads for a short time. Wear
safety gloves throughout the operation. Keep face and other parts
of the body away from the valve opening. If LP-Gas continues to
vent around the plug threads, the manual shutoff valve may be
faulty. Retighten the plug and notify the bulk plant manager or
supervisor.
13. Install the ESVs in the liquid and vapor valves. It may be necessary to install
stubs (schedule 80 pipe nipples) before installing the ESVs. Thread the
ESVs into the valve opening until they are hand tight. Then, tighten them
37
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
with the appropriate wrench until they are securely seated. Once installed,
open the ESVs in accordance with company procedures.
14. Remove the dust caps from the connectors on the riser hoses. Check the
connectors to be sure they are clean. Check the O-rings on the ESV or
unloading stub to be sure they are in good condition. If necessary, clean the
connectors with a rag and replace worn, flattened, or damaged O-rings.
15. Connect the hoses to the railcar stubs or ESVs (whichever is applicable) by
spinning on the ACME connectors until they are hand tight. As the
connectors are tightened, move the hose or hose-end valve up and down
slightly to prevent the thread from seizing. When each connection is hand
tight, tighten it an additional 1/8 turn with a spanner wrench.
16. Check the ESVs at the riser by opening and closing them according to plant
test procedures. Be sure the remote operators are working properly and that
all fusible links are intact. If the ESVs will not operate properly, do not
continue the transfer operation. If possible, correct the problem. Otherwise,
notify the bulk plant manager or supervisor.
17. Check each connection for leaks by opening and closing the manual shutoff
valve at the railcar to charge the connection with LP-Gas.
18. If using ESVs instead of unloading stubs, open the ESV to charge and test
the hose connection. If there are any connection leaks, close all valves and
retighten the connection. If the leak continues, notify the bulk plant manager
or supervisor.
Operation
A qualified person must be present at all times during the entire transfer
operation to monitor the condition of the transfer system and to handle
emergencies. Otherwise, the operation must be shut down and hoses
disconnected.
If a release or fire develops at any time during the operation, close all ESVs
immediately and stop the compressor. Refer to Section 3 of this handbook and
company procedures to address the situation.
1. Open the vapor valves at the railcar riser. Then, open all valves in the liquid
line, starting at the manual shutoff valves on the railcar and working toward
the plant storage tank(s). Allow as much liquid as possible to drift between
the two tanks. Open the remaining valves in the vapor line. Open all valves
38
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
2. Check to be sure the four-way valve and the plant valves have been set so
that the compressor will remove vapor from the plant storage tank and
discharge it into the railcar. Figures 5.1.5b and 5.1.5c illustrate the
compressor 4-way valve and piping positions for unloading in a typical bulk
plant. Plant piping might vary. Verify the proper valve positions and
operating procedures for each bulk plant.
3. Open the vent on the compressor’s liquid trap to verify that liquid is not
present in the vapor hose and suction line. Liquid may severely damage the
compressor and ultimately produce leaks at the head gasket or oil sump.
4. Start the compressor and check the pressure gauges for excessively high
exhaust or excessively low intake pressure. If either occurs, stop the
compressor and correct the problem before continuing. Check the sight glass
or flow indicator to make sure liquid is flowing through the system.
5. When the plant storage tank reaches its maximum permitted filling level or
the railcar is empty, close all valves in the liquid line and stop the
compressor.
6. Reverse the four-way valve and adjust the plant piping manifold so the
compressor will withdraw vapor from the railcar and force it through the liquid
space of the plant storage tank (refer to Figures 5.1.5b and 5.1.5c). Restart
39
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
the compressor and check the pressure gauges for excessively high
discharge or excessively low intake pressure. If either occurs, shut down the
compressor and correct the problem before continuing.
Shutdown
1. At the end of the vapor recovery operation, close all valves in the vapor line
and shut down the compressor.
[Note: Some plants shut down the compressor when the discharge pressure
rises to four times the intake pressure. Others stop vapor recovery
operations when the intake pressure drops to 50 psi in the summer or 30 psi
in the winter. Under some conditions plants will also shut down their
compressors, if the intake pressure drops less than 10 psi during 15 minutes
of operations. Check with your supervisor for the proper guidelines to follow.]
2. To make sure that the railcar is totally unloaded, open the sampling valve. If
liquid escapes, it might not be fully unloaded. Resume unloading operations
until the railcar is totally unloaded.
3. Close all railcar discharge valves, ESVs, and transfer hose-end valves.
4. Vent the LP-Gas trapped between valves, stubs and hose couplings. When
the connections are fully de-pressurized, disconnect the transfer hoses.
5. Remove the railcar unloading nipples (or “stubs”) that are screwed into the
railcar valve outlets.
8. Check to be sure there is no liquid left in the railcar by partially opening the
sampling valve.
9. Bleed down and disconnect the hoses at the riser. Never disconnect any
hose until the LP-Gas trapped in the connection has been safely bled off.
40
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
11. Remove the unloading stubs or ESVs from the railcar, and replace the plugs
in the liquid and vapor valve openings.
12. If any railcar defects were found during the unloading operation, complete a
“Bad Order Tag” (see Figure 5.1.5d) and attach it to one of the sampling
valves.
14. Stow all transfer hoses and fittings and raise the unloading riser platform to
its stored position.
15. Remove and store the warning signs, chock blocks and reset the derail from
the derailing position.
Do not release the hand brake on the railcar. This will be done by
railroad personnel when the railcar is picked up.
41
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
17. Take an extra look around the railcar and unloading site to make sure
everything is safe and secure.
18. Complete a Railcar Return Instructions Form and deliver the form to the rail
carrier representative (see sample form in Figure 5.1.5e). This form must be
prepared, signed and presented to the rail carrier representative for their
signature before the railcar is released.
42
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
43
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
This section provides general guidance for the preparation of DOT cylinders
being shipped from a bulk plant. For complete details and procedures that fully
describe the associated regulatory requirements, refer to 49 CFR 173, the
Compressed Gas Association publication CGA-6 (Standard for Visual Inspection
of Steel Compressed Gas Cylinders, 1993), CFR 49 section 180 subpart c
(Requalification and maintenance of packaging) and ANSI/CGA C-6.3
(Guidelines for Visual Inspection and Requalification of Low Pressure Aluminum
Compressed Gas Cylinders, 1991).
Cylinder Inspection
Prior to filling cylinders at the bulk plant, cylinders that have been in service must
be inspected to determine their fitness for continued service. Specifically, DOT
regulations stipulate that no individual is allowed to fill a cylinder that is overdue
for periodic requalification with a hazardous material and then offer it for
transportation.
Before each filling of a cylinder, the individual filling the cylinder must visually
inspect the outside of the cylinder. Cylinders sleeves must be removed to
facilitate the exterior visual inspection. A cylinder that has any of the following
characteristics cannot be filled and offered for transportation:
• A crack or leak.
• Bulging.
• A defective valve.
• A leaking or defective pressure relief device.
• Evidence of physical abuse.
• Fire or heat damage.
• Detrimental rusting or corrosion.
Requalification of Cylinders
Any cylinder that is due for requalification cannot be refilled and offered for
transportation until it is requalified using methods prescribed by DOT. In
jurisdictions that have adopted NFPA 58-2001 (without exceptions or
modifications to §2.2.1.5), there is no distinction between cylinders that are
transported in commerce and those that are not with respect to the cylinder
requalification requirement. Beginning with the 2004 edition, cylinders that are in
stationary service and filled on-site are permitted to undergo a visual inspection
(§5.2.3) instead of requalification.
44
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Requalification Methods
There are three ways to requalify a cylinder. The specific method used is
indicated on the date stamped on each cylinder.
Three requalification methods are used to verify DOT cylinder fitness for
continued service. The method used determines when the cylinder is next
due for requalification.
o The 4 character RIN will have a letter and a number above the
Requalification Date and 2 numbers under the Requalification
45
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
A1
05 04 x
32
Where:
“05” is the month of requalification;
“A123” is the RIN;
“04” is the year of requalification
(2004);
“X” represents the symbols
described in paragraphs (f)(2)
through (f)(7) of 49 CFR 180.213.
{Note: Characters not to scale in
size.}
V100001
0504 E -or-
0504 E
V100001 -or-
V100001 0504 E
46
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Only facilities with a Requalification Identification Number issued by the Pipeline and
Hazardous Materials Safety Administration are allowed to perform a DOT specification
cylinder requalification. Check with your supervisor.
Cylinders should be arranged so that any cylinder can be accessed in the event
of a service valve or other leak. Proper valve protection should be maintained at
all times. Also, cylinders should be stored so that cylinder relief valve discharges
are not directed at the service valves of adjacent cylinders in order to limit the
extent of damage and the hazards to persons and property in the event of a relief
valve discharge and fire.
LIQUEFIED
PETROLEUM
GAS
UN 1075
47
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
48
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
For cylinders manufactured after October 1, 2007, a cylinder must have its valves
protected by one of the following methods:
49
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
During loading…
• Place cylinders so that the weight remains evenly distributed on the
service bed. An ideal load places most of the weight on the front and rear
axles, and evenly distributes it, both side-to-side and front to back. An
unbalanced load is very dangerous, and can make the vehicle hard to
handle or even overturn.
• Load cylinders in a suitable rack or frame on the service bed.
• Securely restrain cylinders in an upright, vertical position to keep them
from shifting, falling, or being ejected from the truck.
• Position cylinders so that their relief valves are in direct communication
with the vapor space at all times. Secure them in this position with binders
or straps
The vehicle must be properly placarded before leaving the bulk plant. DOT
regulations require any vehicle transporting more than 1,000 pounds of LP-Gas,
including the weight of the cylinders, to be placarded on the front, rear, and on
both sides. Placards must indicate the hazard class name and hazard class
50
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
If permanent shipping papers are used, the date and number of cylinders loaded
at the beginning of the delivery route must be recorded on the permanent
shipping paper, typically with a wax pencil marker (see Figure 5.1.6d on next
page).
Shipping Papers
sequence of information provided on shipping papers has been changed by the DOT. The industry
will have until January 1, 2013 to comply with the new format.
51
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
If permanent shipping papers are used for cylinder delivery vehicles, the date and number of
cylinders loaded at the beginning of the delivery route must be recorded (typically with a wax pencil
marker). If single-trip shipping papers are used, they should be completed according to company
procedures.
52
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
53
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
You must carry emergency response information along with the hazmat shipping
papers in your CMV. You must keep this information readily available for emergency
responders, enforcement authorities, and company personnel, in the event of an
incident.
The emergency response information must also be available at LP-gas transfer and
storage facilities in case of emergency.
Each state may have different requirements. Be sure to follow your company’s policy
and state requirements, as well as DOT regulations.
At a minimum, the emergency response information must include the
following:
Description of the hazardous material.
Immediate precautions to take in the event of an incident.
Risks of fire or explosion and immediate methods for handling small and
large fires.
Initial methods for handling spills or leaks in the absence of fire.
Immediate hazards to health and preliminary first aid measures.
Emergency response telephone numbers.
This information must be either on the shipping papers or kept with the shipping
papers.
54
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
The following items (as a minimum) should be checked on each tank transported
from the bulk plant to a customer location:
There are at least 19 welds on a typical ASME tank used for LP-Gas storage.
In addition, threaded fittings installed in the tank represent at least 11
additional places where leaks could occur. Each of these welds and
threaded connections should be checked for leakage with the tank
pressurized, using a suitable leak detection solution or leak detection device.
• Verify that any tank over 125 gallons water capacity contains 5% or less LP-
Gas in liquid form.
If more than 5% liquid is present in a tank larger than 125 water gallons
capacity, the excess liquid must be evacuated before the tank can be
transported on public roadways.
• Check the condition of the tank coating to be sure that it is proper for the tank
installation, whether it is for underground or aboveground service.
The protective coatings used on both types of tank installations are important
to maintaining structural integrity and protecting the container from loss of
wall thickness due to corrosion. The coating for underground tanks is an
integral part of the tank’s corrosion protection system. If the protective
coating of a tank is damaged, the tank coating should be repaired or another
tank selected for installation. Coating touch-up materials should be
55
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
transported with the tank to make any needed final repairs to tank coatings at
the installation site.
Check to see that weather caps are in place on filler valves, relief valves, and
the vapor equalizing valve. Verify that the metal plug is in place and sealed on
the liquid withdrawal valve. If the tank is a new tank and not vacuum-sealed by
the manufacturer, be sure that the container is properly purged of air before it
is transported to the customer location. Older tanks that have been open to
the atmosphere must be purged as well (see subsection 5.1.9 of this
handbook).
• Verify that the tank is properly marked and labeled for transportation.
ASME data plate markings or ASME certification stampings in the tank head
or shell must be legible.
56
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
After the condition of the ASME tank has been determined to be satisfactory, the
tank and any required installation materials should be readied for loading.
Secure installation items, such as masonry foundation blocks, since they are also
considered cargo that must be secured as any other cargo transported under
DOT regulations.
When two or more people are involved in any task, efficiency and safety are
dependent on planning and clear communications. Handling and setting tanks
requires a coordinated effort. Before the tank is lifted, transported, and placed in
its new location, pre-job planning that includes everyone who will be involved
should be conducted and should address the following:
• A detailed tank loading or unloading plan along with a description for each
person’s responsibilities in the operation.
• The locations of trucks and other equipment being used to make sure that
crane lifts, swings, and other movements are completed safely.
57
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
structures and overhangs, and slopes or terrain hazards that could lead to
truck or crane overturn.
After the pre-job planning session, the crane truck should be located on
level ground so that the ASME tank can be lifted and positioned within
safe working limits of the crane. The vehicle parking brakes should be
set, and chock blocks placed in front of and behind the vehicle’s rear
wheels. The crane outriggers should be fully extended and locked into
position. Outriggers should be adjusted to level the crane structure in
accordance with manufacturer’s operating instructions. Crane outriggers
(where provided by the manufacturer) are used to prevent damage to the
truck chassis and maintain stability.
Safety Inspections
Before lifting the tank, the crane should be inspected thoroughly. If the
tank contains more than 5% liquid, the tank’s lifting lugs or “eyes” should
not be used. Instead a “basket lift” should be made using slings or chains
with adequate load ratings.
Lifting Operations
After inspecting the sling(s), the crane operator must determine how the
tank will be lifted, how the sling(s) will be arranged, and if additional slings
or other equipment is needed for the load. The slings being used should
have load ratings well in excess of the weight of the tank and its contents.
58
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
The primary regulatory requirements for transporting ASME tanks used for LP-
Gas are found in 49 CFR 173.315(j). To highlight these requirements for
awareness purposes, ASME containers used for LP-Gas service and intended
for stationary installation on consumer premises may be shipped by private motor
carrier from a bulk plant only under the following conditions:
The DOT regulatory reference for checking the security of cargo on commercial
vehicles is found in 49 CFR 392.9. These regulations prohibit a driver from
operating a commercial motor vehicle unless the cargo is properly distributed and
secured in compliance with DOT requirements. Of most importance, the driver
must:
• Inspect the cargo and the devices used to secure the cargo within the first
50 miles after beginning a trip, and make necessary adjustments; and
59
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
• Re-examine the cargo and devices that secure the load, making
necessary adjustments whenever:
• ASME containers (or tanks), which are designed for the storage of LP-Gas, are installed
at bulk plants or customer locations in what are referred to by NFPA 58 as a “stationary”
or “permanent” installations. As mentioned previously, ASME tanks with water
capacities 125 gallons or more cannot be legally transported from a bulk plant after they
have been filled with liquid LP-Gas to more than 5% of their water capacity.
• DOT specification portable tanks and intermodal tanks are designed to be transported
while being filled to their maximum permitted filling density. These tanks have structural
protection for valves and fittings that is not provided on stationary ASME storage tanks.
Of course, DOT regulations for securing the load and protection against shifting
and falling cargo always apply, whether or not the vehicle is required to be
placarded.
The DOT has specific requirements for placarding (49 CFR Part 172.504) and
marking (49 CFR Part 172.302) bulk packages (DOT Portable Tanks and ASME
containers greater than 120 gallons). Each bulk package is required to be have
a marking and/or placard with the hazardous material identification number (1075
for LP-gas) and the hazard class (2) or hazard class division (2.1) on a red
colored diamond as follows:
• On each side and each end if the ASME container or the DOT portable
tank has a water capacity of 1,000 gallons or more
• On two opposing sides if the ASME container or the DOT portable tank
has a water capacity less than 1,000 gallons
60
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
solid line
hazard inner border
0.3 in. 0.2 to 0.25 in.
high from edge
hazard class
0.25 to 0.5 in. 3.9 inches
high each side
Plus
OR
2.1
For either portable DOT tanks or ASME containers, if the identification number
on the portable tank or ASME container is not visible, the transport vehicle itself
must be marked with the identification number on each side and each end of the
vehicle
To comply with DOT regulations (per 49 CFR 392 & 393, Subpart I), ASME tanks
should be secured with at least 2 cargo straps and binders (or chains and
binders) having sufficient working load limit ratings for the tank(s) being
transported (see Figure 5.1.7g).
Additional cargo straps or chains should be used for each additional 10-foot
length of tanks longer than a typical 1,000 gallon ASME tank or where two
restraints do not meet minimum working load requirements for heavier loads.
61
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Prop a ne in Ta nk–
120 -999 ga ls.
Minim um –
Ship p ing La b els
2 Tie -d o wns
Both Sid es; 1,000
g a ls. & Larg er Both
Sid es & Eac h End
Propane Service
DOT 654321
1075
2.1
DOT regulations prohibit the display of hazardous material placards if the vehicle
is not transporting cargo containing hazardous materials. Therefore, vehicle
placards must be removed or covered during the return trip after ASME tanks are
delivered.
The area around the evacuation operations must be maintained free of any
ignition sources. For example, operating internal combustion engines should be
at least 15 feet away from the point of transfer. Additionally, smoking, open
flame, portable electric tools and extension lights should not be permitted within
25 feet of the transfer point.
62
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Re c e iving
ASME Ta nk Eleva ted Doc k or Pla tform
63
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
• The vapor lines that connect the compressor to the two tanks are
opened and the liquid line is closed.
Cylinders designed for liquid service (liquid service valve with dip tube)
are very easily emptied using a scavenger tank. The following is a typical
procedure:
• A LP-Gas liquid hose, with a shutoff valve on each end, is
connected between the cylinder and the scavenger tank.
• When the compressor is turned on, the higher pressure in the
cylinder will force liquid to flow up the dip tube in the cylinder and
into the scavenger tank.
• When the liquid level in the cylinder reaches the bottom of the dip
tube, liquid can no longer be removed.
If the cylinder must be totally evacuated, the remaining contents must be
flared or carefully vented.
Cylinders designed for vapor service are not as easy to evacuate. Since
a vapor service valve does not utilize a dip tube, the cylinder must be
64
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
inverted (i.e., bottom side up) so liquid can be withdrawn through the
vapor service valve (see Figure 5.1.8b).
65
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
2. Select the proper site for flaring the LP-Gas. If a designated area
for flaring does not exist, select a site with your supervisor that
meets the company and code requirements.
66
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
4. Lay out and assemble the flaring equipment, including all the
necessary hoses, fittings, supports and burner to flare the
remaining LP-Gas in the container.
67
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
68
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
The liquid transfer hose connected between the two tanks should
have the following features (see Figure 5.1.8e):
69
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Vapor Hoses
Adapters
70
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
moving operator stem pushes open the back checks in the filler
valve so the liquid can be removed from the container.
All tanks built after 1963 are spray-filled and should be equipped
with a separate actuated liquid withdrawal excess flow valve to
evacuate liquid from the tank (Figure 5.1.8g). As long as the valve
remains closed, it acts as a back check and prevents any gas
from escaping into the atmosphere. Once the valve is opened,
the valve disc can move up and down freely on the operator stem,
automatically changing it to an excess overflow valve.
Figure 5.1.8g
Actuated Liquid Withdrawal Excess Flow (Evacuation) Valve
71
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Install a transfer valve with a 3/4" NPT inlet and a 1 3/4" ACME
hose connector in the outlet. Use the machined adapter supplied
by the evacuation valve manufacturer.
72
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
and provisions in NFPA 58. Check your company procedures and state
and local codes for any other requirements that apply.
On most LP-gas containers larger than 125 water gallon capacity and
manufactured prior to July 1, 1961, a liquid withdrawal (evacuation)
internal dip tube was attached to the bottom of the filler valve by the
manufacturer and extended to the bottom of the container. Since 1961,
container manufacturers have installed a separate valve, called an
actuated liquid withdrawal excess flow valve, for liquid evacuation of
domestic containers.
• The tank being used to receive the liquid from the stationary
tank being evacuated is a bulk delivery vehicle cargo tank.
73
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Figure 5.1.8i
Evacuating ASME Tank Using a Portable Compressor
74
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
5. Lay out the liquid transfer hose between the stationary tank and the
cargo tank.
6. Connect one end of the liquid transfer hose to the outlet of the transfer
valve and the other end to the fill connection located on the cargo tank
of the delivery vehicle.
• Close all valves in the line and make repairs if any leaks are
detected.
75
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
• Fully open the transfer valve and allow LP-Gas to flow through
until the excess-flow check valve "slugs" shut.
11. Once the pressure has been reduced, the withdrawal valve must be
serviced before the ASME tank is returned to service.
The following procedures apply to new containers designed and used for storing
LP-Gas (propane) at capacities up to and including 2,000 gallons water capacity,
including both ASME and DOT containers. Only personnel who have been
properly trained and qualified in the procedures related to container vapor
purging and methanol injection should perform the tasks outlined in this section.
Purpose
76
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
ASME tanks and DOT cylinders are usually purged of air at the bulk plant using
LP-Gas vapor regulated to 15 psig. Note that purging may sometimes be done
through an electrically grounded purging stack (see Figure 5.1.9a).
To purge a container:
1. Open the service valve to bleed any air from the tank.
2. Attach the vapor hose end valve to the service valve with the
appropriate adapter.
4. Close the valve on the vapor hose and bleed off the vapor using the
adapter on the filler valve.
A final vapor charge of 15 psig should be retained in the container before filling
with liquid LP-Gas.
77
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
In order to avoid air entering the tank during the methanol transfer, the
hose in the methanol container must extend to the bottom of the container
and the service valve on the tank should be closed before the methanol
level gets to the level of the hose opening.
After the methanol is transferred into the tank, the tank is pressurized with
LP-Gas vapor (see Figure 5.1.9c). All valves should be closed after the
tank is pressurized. The manufacturer’s applied shrink-wrap plastic
should then be removed from the tank valves to indicate that the tank is
pressurized with LP-Gas.
78
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
79
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
1. Inspect the short hose that will be used to inject the methanol and be
sure it is free of defects that would require it to be removed from
service.
3. Attach the female ACME adapter of the short hose to the filler valve of
the receiving container and tighten to seal the connection.
4. Fill the short hose section with methanol, holding the hose end up and
being careful not to spill or splash the methanol.
5. Attach the male ACME adapter to the delivery hose end valve adapter
and seal it to make sure methanol and LP-Gas will not leak out under
pressure when the delivery hose end valve is opened.
6. Slowly open the delivery hose end valve. If there is not sufficient LP-
Gas pressure in the hose to open the receiving container filler valve,
use the CTMV pump to transfer a few gallons of LP-Gas into the
receiving container.
7. Close the hose end valve and partially loosen the short hose section
from the container filler valve, allowing the LP-Gas to vent until and
the hose is de-pressurized.
8. Remove the short hose section from the filler valve and the delivery
hose end valve.
9. Inspect the short hose section and the portion of the delivery hose
deployed for the transfer.
10. Properly stow and secure the hoses and the methanol container.
80
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
While the dispensing equipment at a LP-Gas bulk plant will vary in size and
design (e.g., storage capacity, integrated with the bulk storage tank versus stand-
alone, manual versus automatic shut-off devices), the basic procedures to follow
are typically the same. Prior to any operation, one should review and be familiar
with the dispensing equipment, piping functions, and company operating
procedures. Detailed information is provided in CETP Module 3.3 and in PERC’s
Dispensing Propane [Safely] training materials.
The following procedures apply to filling DOT cylinders and vehicle mounted
ASME containers. Only personnel who have been properly trained and qualified
in the procedures related to dispensing LP-Gas should perform the tasks outlined
in this section. All personnel handling LP-Gas should read and understand the
Safety Data Sheets (SDS) for each material prior to handling.
Operating a dispenser to fill DOT cylinders with LP-Gas requires the operator to
know the regulations that apply and the characteristics of manual or automatic
filling equipment.
• Before filling each cylinder, the person filling the cylinder must
visually inspect the outside of the cylinder.
81
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
NFPA 58 allows cylinders of less than 200 pounds water capacity that are
not subject to DOT jurisdiction to be filled by the volumetric method.
Operating a Dispenser
Startup
82
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Operation
83
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
1. Place the cylinder to be filled on the platform scale and set the
balance beam scale to the proper filling weight of the cylinder.
12. Check the weight of filled cylinder after filling connector has
been disconnected. If overfilled, bleed off excess LP-Gas in a
safe location.
13. Check the cylinder valves, especially the relief valve for leaks.
84
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
[Note: Cylinders that are less than 200 lb water capacity and
not subject to DOT jurisdiction, such as non-commercial
customers transporting their own cylinders, can be filled
volumetrically. Refer to you company’s policy and check with
your supervisor before filling a cylinder by the volumetric
method.]
Shut-down
85
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
to the outside of the vehicle so that all propane vapor is discharged into the
atmosphere.
NOTE: If filling a motor fuel tank on an RV, be sure to turn off all appliance pilot lights and
electronic ignition systems.
The label is required to be located on an exterior vertical surface on the lower right rear of the
vehicle (such as the trunk lid), but not on the bumper.
1. Follow these steps to fill mobile and motor fuel tanks correctly.
Customers are restricted from the immediate area around the
liquid propane transfer operation. Make sure there are no
internal combustion engines operating within 15 of the point of
transfer, ignition sources within 25 feet of the point of transfer,
or metal working operations (including grinding, oxygen-fuel
86
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
3. Open the vent valve on the fixed maximum liquid level gauge
and check for flow. If vapor appears, continue the filling
process. If liquid appears, stop the filling process because the
tank is full.
4. Start the pump and slowly open the valve on the hose.
5. When a steady white mist or fog is first emitted from the fixed
maximum liquid level gauge vent valve, this indicates the
maximum permissible fill has been reached.
9. Check the valve for leaks and replace the dust cap.
10. For mobile ASME fuel tanks, inform the operator that the
service valve will need to be returned to the fully open position
and appliance pilots re-lit after the vehicle has been moved
from the LP-Gas transfer area. If it is not your company’s
policy to light customer pilot lights, advise the customer to
have a professional service company or gas distributor light
the pilot lights, that if the customer does this without
professional help he/she must carefully follow the
manufacturer’s instructions.
Shutdown
87
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
The following sections contain guidelines for operating procedures specific to industrial
plants using a vapor distribution system. These facilities will have some operating
procedures that are similar to those at a bulk storage facility. Therefore, refer to the
appropriate subsections under Section 5.1 that apply to the normal operations of a large
volume vapor distribution system.
While the equipment at a large volume customer operating off of a vapor distribution
system will vary in size (i.e., storage capacity, meters, regulators), the basic procedures
to follow are usually much the same as for the bulk storage tank. Prior to any operation,
one should review and be familiar with its design, layout, equipment, piping functions,
and company operating procedures. CETP Modules 4.1 & 4.2 provide detailed
supporting information.
Startup
3. Ensure that all of the appropriate manual valves (i.e., globe, angle, or ball)
are open on the bulk storage containers.
4. If the container has manually operated internal valves, make sure that the
Emergency Shutdown system is operational and that internal valves are
opened.
d. For cable operated systems, make sure that all cables are operational
88
Operations & Maintenance Handbook Section 5
for LP-Gas Storage Facilities Plant Operations
Procedures
Operation
Shutdown
3. Check to see that all of the appropriate manual valves (i.e., globe, angle, or
ball) are closed on the bulk storage container(s).
4. If the container has manually operated internal valves, make sure that these
valves are closed by releasing the pressure in Emergency Shutdown System
(pneumatic) or pulling the manual cable for the system.
Vaporizers
The types of vaporizers and their respective startup, operating and shutdown
procedures vary considerably. Therefore, it is not possible to provide generic
operating procedures or guidelines for this equipment.
89
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
This section of the handbook is intended to provide owners or operators of propane systems
the information necessary to comply with the general requirements of NFPA 58, Chapter 14
for maintaining the mechanical integrity of an LP-Gas bulk plant through maintenance
procedures (§14.3.1) and maintenance manuals (§14.3.2).
A checklist approach for the development of procedures specific to the maintenance of the
transfer system and plant equipment is provided in Section 7. Also, refer to Section 8 of this
handbook for maintenance requirements and guidelines for bulk plant fire protection
equipment.
Maintenance Manuals
Maintenance Procedures
Maintenance records provide the tracking and documented verification that the facility is
being properly maintained and in a safe condition in accordance with NFPA 58.
• Record Storage - Maintenance records for all fixed equipment used to store and
transfer LP-Gas must be kept at each facility. For unattended facilities, these
records can be maintained at the unattended facility or another designated location.
90
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
• Retention – Maintenance records must be retained for the life of the equipment.
Sample charts for preventive maintenance record keeping (see Chart 6.1) and for logging
equipment repairs (see Chart 6.2) are provided at the end of this section.
The following bulk plant equipment must be physically protected against damage due to
impact from vehicles or to prevent accidental releases of LP-Gas:
• Dispensers.
Container Condition
91
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
Corrosion Control
Aboveground Containers
• For mounded containers, the mounding material (e.g., earth, sand, fillers)
must be a non-combustible and non-corrosive material. Control measures
must be used to prevent possible erosion of mounding materials.
92
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
vehicle barrier protection for the fitting housing, container connections and
piping. Protection must conform to the requirements of NFPA 58, § 3.3.79
and § A.3.3.79.
• Steel containers that have been involved in a fire and show no signs of distortion
must be requalified before being placed back in service.
o ASME containers must be retested using the hydrostatic test procedure that
was applicable at the time of the original fabrication.
o For both DOT and ASME containers involved in a fire, the appurtenances
must be replaced by qualified personnel.
• Aluminum DOT cylinders that have been involved in a fire must be permanently
taken out of service.
• DOT stationary cylinders that are filled at the customer’s location must be:
• Gaskets for container appurtenances and the system piping must be resistant to the
action of LP-Gas. Furthermore, gaskets must be replaced whenever a flange is
opened. Other detailed gasket requirements are defined in §5.7.1.4. of NFPA 58.
• Pressure Relief valves and discharge piping must be protected to minimize the
entrance of water or extraneous materials through the use of rain caps or any other
effective means that do not affect their operability.
93
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
• Emergency valves must actuate when a hose pull away occurs that causes a break
in the fixed piping system.
• Emergency shutoff valves (ESVs) and backflow check valves that are required by the
Code must be tested annually for their functionality. ESVs must be specifically
tested for:
The results of these tests must be documented (see sample Chart 6.3 at the end of
this section). The Code does not set requirements for the retention and maintenance
of these test results. Therefore, you should check with established company policy
for the manner in which and the length of time that these records should be kept.
• Temperature-sensitive elements (i.e., thermal links) cannot be painted nor have any
ornamental finishes applied after they have been manufactured.
Hose assemblies must be inspected prior to each use for leakage or damage that could
impair their integrity. Hoses must be inspected at least annually.
The Code does not set requirements for the documentation, retention and maintenance of
hose inspection results. Therefore, you should check with established company policy.
94
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
Propane Inspect belts; change oil & filter Insert Per Mfg.
Compressor Recommendations
Hoses Inspect for cracks, cuts, gouges, wear and Insert Per company
other damage policy
Others, etc.
95
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
96
Operations & Maintenance Handbook Section 6
for LP-Gas Storage Facilities General Maintenance and
Inspection Requirements
Bobtail #2
Bobtail #3
Transport Unloading
Transport Loading
Railcar Unloading
Railcar Loading
Bulk Storage #1
Bulk Storage #2
Bulk Storage #3
Others, etc.
* Based on visual inspection of thermal link (no paint), manual shutoff from remote location,
manual shutoff at installed location, and/or positive shutoff by back check valve
97
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
NFPA 58 requires that bulk plants and industrial plants have maintenance procedures that are
documented and readily available (§14.3.1 and 14.3.2). This section provides guideline
maintenance and inspection procedures that will provide the basis for maintaining the
mechanical integrity of LP-Gas Systems.
While maintenance and inspection procedures are typically similar at LP-Gas Bulk Plants and
Industrial Plants, the equipment can vary in size (i.e., storage capacity), design, layout,
equipment complexity or function (e.g., rail unloading facilities, cylinder filling operations, on-site
commercial dispensers). Similar to the operating procedures in Section 5, this handbook
section should be considered to be a “template” for the maintenance and inspection activities
conducted at any specific LP-Gas storage facility. Additions, modifications or deletions to these
procedures could be necessary. Therefore, owners or site management/supervisors should
consider site-specific features and conditions that need to be included, modified or deleted in
the information in this section in order to accurately reflect local operations and conditions. With
these changes, operators, technicians, drivers and other site personnel can use this document
as the maintenance procedures required by NFPA 58.
Although NFPA 58 references the need for documented maintenance and inspection
requirements with respect to refrigerated storage, marine and pipeline LP-Gas systems, these
systems (which can vary significantly in design and complexity) come under the authority of
other jurisdictions which have very specific and detailed requirements.
IMPORTANT: All bulk plant maintenance and inspections should conform to equipment
manufacturers’ instructions as they apply to specific equipment installation and maintenance
procedures.
Manufacturer's literature provides the recommended procedures for maintenance and repair of
equipment specific to your facility. Owners and managers/supervisors must obtain that
information and include it in Section 9 of this handbook (“Manufacturers’ Equipment
Information”) for use by operators, technicians, drivers and other personnel in carrying out their
responsibilities. Review the information provided to determine the appropriate action to take for
inspections, maintenance and repairs.
98
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Content of Section
The chart below is a guide to easily identify which equipment in the facility is subject to
maintenance and inspection requirements. Applicable CETP modules are included in the table
for easy reference to further instructional information and materials.
The “CETP-2014 Reference” directs the user to the related module of the training materials
developed by PERC, having a 2014 copyright date.
For CETP-2014, the references are constructed such that the first three letters designate the
course, followed by the applicable module and lesson (e.g., BPP-7-1).
CETP-2014 Check
Topic Reference (If Applicable)
Bulk Storage Containers BPP-7-1
Piping -
Liquid Pumps -
Bulkheads BPP-7-1
Vapor Compressor -
Tank Car Unloading Tower BPP-7-1
Scales -
Meters (Retail Sales Only) -
Vaporizers -
Regulators -
Electrical Systems -
99
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
This section provides a bulk storage facility maintenance and inspection checklist detailing
some of the many preventative maintenance and inspection steps that can be conducted in
typical bulk storage facility and large volume vapor distribution systems.
This checklist is based on the 2014 Edition of NFPA 58. If your facility is not equipped with an
item on this checklist, refer to the edition of NFPA 58 that was applicable at the time of
installation. If the edition in effect did not require the item on the checklist, mark the “N/A” (not
applicable) box and note the referenced edition in the “Comments” section.
To use this checklist for guiding and documenting your maintenance and inspection activities,
simply take the actions as directed by the questions and check the appropriate column (i.e., yes,
no, not applicable). If the “no” box is checked, comments describing the corrective action steps
that have been taken must be documented. If additional space is required, separate sheets can
be attached to the checklist.
Refer to Appendix 7.1 at the end of this section for additional guidance for completing
the checklist.
100
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
101
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
102
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
103
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
104
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
105
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
107
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
108
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
109
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
110
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
111
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
112
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
113
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
114
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
115
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
116
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Appendix 7.1
These guidelines are based on the 2014 Edition of NFPA 58. Check with your supervisor if your
facility or equipment was constructed or installed under a previous Code edition. If the item on
the checklist is not subject to the requirements of the 2014 Edition, refer to the applicable Code
edition for guidance.
For use in propane service, stationary tanks must have a minimum working
pressure of 250 psig (200 psig for some specific ASME tanks built before 1950).
Check with your supervisor if the minimum working pressure is something other
than 250 psig.
117
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
External visual inspection of the shell and heads of the container should
indicate that no loss of wall thickness has occurred on the container, either
generally or locally. If there is any question regarding the potential loss of
wall thickness, a qualified inspector can be employed using appropriate non-
destructive testing techniques.
Are all container markings and decals in accordance with NFPA 58?
See the first item regarding requirements for the manufacturer’s data plate.
Additionally, all ASME containers that contain unodorized LP-Gas must be
marked “NOT ODORIZED” in letters 4 inches high with a contrasting
background, surrounded by a ½ inch rectangular border.
C. CONTAINER FOUNDATIONS
The parts of the ASME container in contact with the saddles or foundations
must be coated or protected in some manner to minimize corrosion. No signs
of rust bleeding should be apparent.
The pads should show no signs of excessive deterioration and should have adequate
weather sealing to prevent moisture from accumulating and causing corrosion on the
container.
D. CONTAINER FITTINGS
Are all container openings (except relief valve connections) equipped with
proper fixed restriction, back check, or internal valves and shutoff valves?
Check with your supervisor and refer to the Code edition applicable for your installation
for specific requirements.
118
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Labels or color codes are permitted to be on valves. Connections for pressure relief
devices, liquid level gauges and pressure gauges are not required to be labeled.
Are all fittings that are subject to container pressure rated for at least 250
psig working pressure?
Possible exception: The requirement could be 200 psig associated with some specific
ASME tanks built before 1950. Check the container nameplate and discuss with your
supervisor if other than 250 psig rating.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
E. CONTAINER GAUGES
Are pressure gauges in good condition and suitable for 250 psig service
(such as 0 - 400 psig)?
The gauges must be readable, functioning and leak-free. They must be attached directly
to the container opening or to a valve or fitting that is directly attached to the container
opening.
Are liquid level gauges arranged and installed so that the liquid level can
be accurately determined?
The gauging devices must be either fixed maximum liquid level gauges or variable
gauges of the slip tube, rotary or float types.
Bulk storage containers must be equipped with a fixed maximum liquid level gauge to
indicate the maximum filling level.
ASME containers must have permanently attached markings showing the percentage of
capacity that is indicated by that gauge. These markings must be attached to the
container, immediately adjacent to the fixed maximum liquid level gauge or on the
container nameplate.
119
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Each pressure relief valve must be plainly and permanently marked with the following
information:
Is the relief valve marked for use with LP-Gas and labeled by an
independent testing agency?
Underwriters Laboratory (UL) or other testing agency markings must be legible on the
valve.
Self-explanatory.
Are relief valves on underground containers > 2,000 gallons water capacity
equipped with vent stacks of proper diameter and length?
The diameter of the vent stack piping must be large enough so as not to restrict
discharge flow.
The relief valve discharge must be piped upward to a point at least seven (7) feet above
the ground.
Check with your supervisor if there is any question regarding the installation of vent
stacks.
Do relief valves or vent stacks have loose-fitting protective caps or
closures to prevent entry of foreign matter?
Rain caps or other protective devices must be provided to minimize the possibility of
water or other foreign matter from entering into the relief device or any discharge piping.
Where accumulation of water is anticipated, means for drainage must be provided.
The rain cap or other protective device must be designed to remain in place, except
during discharge, and not restrict discharge flow.
120
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Are weep holes for moisture drainage open and is gas impingement of the
container prevented?
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should appear. Listen and smell for possible leaks.
The cable should be free to move through its entire range without binding.
The cable should fully open and completely close the valve.
Check the operators to make sure proper functioning (typically, through release of air or
nitrogen pressure and then repressurizing).
The system should be checked for leaks by pressurizing the system and checking all
connections with an ammonia-free leak testing (soap) solution. For the leak test
solution, no bubbles should form. Listen and smell for possible leaks.
The operator should fully open and completely close the valve.
Check the operators to make sure proper functioning (typically, through release of
pressure and then repressurizing).
The operator should fully open and completely close the valve.
121
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Test (operate) the closing feature to make sure that it will close and open the valve.
Check operating cables to make sure they can move through their entire range without
binding.
Make sure the cable tension is not too tight since that might prevent the valve
from latching properly, or vibration or jarring could cause inadvertent closure during
normal transfer operations.
Check the operators to make sure proper functioning (typically, through release of air or
nitrogen pressure and then repressurizing).
The system should be checked for leaks by pressurizing the system and checking all
connections with an ammonia-free leak testing (soap) solution. For the leak test
solution, no bubbles should form. Listen and smell for possible leaks.
The operator should fully open and completely close the valve.
Are remote emergency shutoff devices between 25 and 100 feet from the
ESV and within the path of egress?
Self-explanatory.
Signs should be visible from the point of transfer and have the words “Propane-
Container Liquid Valve Emergency Shutoff” in block letters at least 2 inches high using
contrasting colors.
122
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Are valves located so that they can be easily reached during normal
operations and in an emergency?
Check that valves are located so that they can be accessed and operated without the
use of additional tools or equipment.
Check for leakage at all body seams and the stems/packing, plus the connections to the
piping and hose. Check each fitting using a gas detector calibrated for LP-Gas or an
ammonia-free leak testing (soap) solution. No gas should be detected. For the leak test
solution, no bubbles should form. Listen and smell for possible leaks.
Some manual shut-off valves have a small hydrostatic relief valve installed in them. If a
relief valve is present, be sure the outlet is clear and unrestricted. Be sure the rain cap
is in place.
Do valves have the proper service pressure rating, equal to or greater than
the maximum allowable working pressure of the container?
Check to make sure that the pressure rating stamped on the valve is no less than 250
psig. Again the possible exception is that the requirement could be 200 psig associated
with some specific ASME tanks built before 1950. Check the container nameplate and
discuss with your supervisor if other than 250 psig rating.
J. CONTAINER – CATWALKS AND STAIRWAYS
Check anchor bolts to make sure they are firmly attached and have not experienced
excessive corrosion. Supports and handrails are in place and stable.
Per OSHA standards ( §1910.23), a standard railing consists of a top rail, middle rail,
and posts, and has a height of 42 inches from the upper surface of the top rail to the
123
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
platform floor. The top rail must be smooth for the entire length.
Check that the railings are in place, properly anchored, stable and free of excessive
corrosion in order to provide fall protection for workers.
Self-explanatory.
Is the area within 10 feet of the container(s) free of weeds, long grass, rags,
paper, wood or other loose or piled combustible debris?
Self-explanatory.
Crash protection must be in place where LP-Gas storage equipment can be subjected to
vehicular traffic.
When inspecting the components of the tank that are visible aboveground, check those
portions of the coating system (e.g., paint) for damage.
When taking a tank-to-soil voltage reading, a minimum -0.85 voltage reading must be
measured and maintained.
Piping
Piping should have paint and coatings systems in place that are not damaged and
provide protection against external corrosion.
Check for excessive rust or corrosion that would indicate metal loss on the piping.
Particular attention should be given to the areas around supports for localized corrosion.
124
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check for dents or gouges that could reduce the wall thickness of the pipe.
Check that supports are in place so that the piping is not bending or flexing in a manner
that would appear to cause stress on the piping and subsequently cause leakage.
Crash protection must be in place where piping can be subjected to vehicular traffic.
B. PIPE FITTINGS
Are all flanges and fittings properly sized for the pressure rating, equal to
or greater than the maximum allowable working pressure of the system?
Piping, flanges and fittings that can contain liquid LP-Gas, and that can be isolated by
valves and require hydrostatic relief valves, must be designed for an operating pressure
of 350 psig or a pressure that is equivalent to the maximum discharge pressure of any
pump or any source feeding the piping system if it is greater than 350 psig.
Otherwise, the minimum pressure rating is 250 psig for LP-Gas liquid or vapor at
operating pressure over 125 psig and at or below container pressure.
The minimum pressure rating is 125 psig for LP-Gas vapor at operating pressure of 125
psig or less.
Are all stainless steel flex connectors in good working condition (i.e.,
reinforcement braid is not damaged)?
Are all flow indicators and sight checks in proper working condition and
leak-free?
Where installed, sight flow indicators must be either the simple observation type or be
combined with a backflow check valve.
125
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
The sight indicators should be sufficiently clean and clear to see the flow upon liquid
transfer.
Check using a gas detector calibrated for LP-Gas or an ammonia-free leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should form. Listen and smell for possible leaks.
Check the piping and fittings using a gas detector calibrated for LP-Gas or an ammonia-
free leak testing (soap) solution. No gas should be detected. For the leak test solution,
no bubbles should appear. Listen and smell for possible leaks.
Self-explanatory.
Hydrostatic relief valves should be fitted with rain caps to prevent moisture and debris
from accumulating inside the valve.
Are the hydrostatic relief valves approved for use with LP-Gas
Do the hydrostatic relief valves have pressure settings between 400 - 500
psig?
Hydrostatic relief valves designed to relieve pressure in sections of liquid piping between
closed shut-off valves must have pressure settings not less than 400 psig and not more
than 500 psig unless installed in systems designed to operate above 350 psig. In this
case, the settings must be not less than 110% or more than 125% of the system design
pressure.
Are valves located so that they can be easily reached during normal
operations and in an emergency?
Check that valves are located so that they can be accessed and operated without the
use of additional tools or equipment.
126
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check for leakage at all body seams and the stems/packing, plus the connections to the
piping and hose. No gas should be detected through normal leak testing techniques.
Some manual shut-off valves have a small hydrostatic relief valve installed in them. If a
relief valve is present, be sure the outlet is clear and unrestricted. Be sure the rain cap
is in place.
Do valves have the proper service pressure rating, equal to or greater than
the maximum allowable working pressure of the container?
Check to make sure that the pressure rating stamped on the valve is no less than 250
psig. Again, the possible exception is that the requirement could be 200 psig associated
with some specific ASME tanks built before 1950. Check the container nameplate and
discuss with your supervisor if other than 250 psig rating.
E. UNDERGROUND PIPING
When inspecting the portions of the underground piping system that that are visible
aboveground, those portions of the coating system (e.g., paint) are not damaged.
When taking a pipe-to-soil voltage reading, a minimum -0.85 voltage reading must be
measured and maintained.
Liquid Pump
A. GENERAL
Check for excessive external corrosion or mechanical damage to the casing and drive
assemblies.
They should be free of excessive cracking or significant loss of the supporting materials.
They should be level and stable, positioned so that there is no misalignment with the
piping system.
127
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Are base plate bolts in place and properly securing the pump to that
foundation?
Self-explanatory.
Lubrication will vary depending on the type of LP-Gas pump. Check the equipment
manufacturer’s instructions for specific lubricants and frequency of lubrication.
Are the strainers in good working condition (i.e., strainer screens free of
debris) and leak-free?
Isolate the strainer from the transfer system, bleed off the trapped LP-Gas, and remove
the cylinder and filter screen to inspect and clean to clear of particles and heavy ends.
Check the inlet and outlet connections, using a gas detector calibrated for LP-Gas or an
ammonia-free leak testing (soap) solution. No gas should be detected. For the leak test
solution, no bubbles should form. Listen and smell for possible leaks. Be sure to also
check that the cover is gas tight.
Are the hydrostatic relief valves installed in the appropriate location and in
good working order?
Self-explanatory.
Hydrostatic relief valves should be fitted with rain caps to prevent moisture and debris
from accumulating inside the valve.
Are all stainless steel flex connectors in good working condition (i.e.,
reinforcement braid is not damaged)?
Flexible connectors should not be used to compensate for misalignment with the piping
or to take the place of elbows.
Note: Check with your supervisor regarding company policies or state/local regulations
to make sure compliance before installing or servicing flexible connectors.
Check the piping and fittings using a gas detector calibrated for LP-Gas or a leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should appear. Listen and smell for possible leaks.
128
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
This should be done when lubrication is scheduled. Check manufacturer’s literature for
additional information.
Check alignment of the drive shaft, motor ad gear box. Check the mounts and securing
bolts.
The gearbox and U-joints should be lubricated per the manufacturer’s instructions.
Self-explanatory.
C. PUMP GAUGES
An automatic bypass valve and piping circuit is required; a manual bypass circuit is
optional.
If the bypass valve or recirculating device is equipped with a shut-off valve, a secondary
device is required and designed to do one of the following:
129
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check the piping and fittings using a gas detector calibrated for LP-Gas or a leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should appear. Listen and smell for possible leaks.
The bypass valve should be set at least 15 - 20 psig below the pump’s internal relief
valve setting.
The bypass valves should not be set for a pressure higher than the differential pressure
rating of the pump or higher than the maximum 125 psig differential pressure typically
recommended by the manufacturer.
Are valves located so that they can be easily reached during normal
operations and in an emergency?
Check that valves are located so that they can be accessed and operated without the
use of additional tools or equipment.
Check for leakage at all body seams and the stems/packing, plus the connections to the
piping and hose. No gas should be detected through normal leak testing techniques.
Some manual shut-off valves have a small hydrostatic relief valve installed in them. If a
relief valve is present, be sure the outlet is clear and unrestricted. Be sure the rain cap
is in place.
Do valves have the proper service pressure rating, equal to or greater than
the maximum allowable working pressure of the system?
130
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check to make sure that the pressure rating stamped on the valves is consistent with the
maximum design pressure of other components in the pump discharge and bypass
system.
131
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Bulkheads
A. General
Crash protection must be in place where LP-Gas transfer equipment can be subjected to
vehicular traffic.
Bulkheads are normally made from steel beams and reinforced concrete. Check for
excessive corrosion of the steel and mechanical damage to the concrete or rebar.
Are pipe nipples and couplings that are attached to the bulkhead in good
working condition and free of excessive wear?
Check for leakage using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Are all flanges and fittings properly sized for the pressure rating, equal to
or greater than the maximum allowable working pressure of the system?
Piping, flanges and fittings that can contain liquid LP-Gas, and that can be isolated by
valves and require hydrostatic relief valves, must be designed for an operating pressure
of 350 psig or a pressure that is equivalent to the maximum discharge pressure of any
pump or any source feeding the piping system if it is greater than 350 psig.
Otherwise, the minimum pressure rating is 250 psig for LP-Gas liquid or vapor at
operating pressure over 125 psig and at or below container pressure.
The minimum pressure rating is 125 psig for LP-Gas vapor at operating pressure of 125
psig or less.
Are all stainless steel flex connectors in good working condition (i.e.,
reinforcement braid is not damaged)?
132
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Are all flow indicators and sight checks in proper working condition and
leak-free?
Sight flow indicators must be either the simple observation type or be combined with a
backflow check valve.
The sight indicators should be sufficiently clean and clear to see the flow upon liquid
transfer.
Check using a gas detector calibrated for LP-Gas or an ammonia-free leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should form. Listen and smell for possible leaks.
Hydrostatic relief valves are designed to relieve pressure in sections of liquid piping
between closed shut-off valves, and must have pressure settings not less than 400 psig
and not more than 500 psig unless installed in systems designed to operate above 350
psig. In this latter case, the settings must be not less than 110% or more than 125% of
the system design pressure.
Hydrostatic relief valves should be fitted with rain caps to prevent moisture and debris
from accumulating inside the valve.
Check the piping and fittings using a gas detector calibrated for LP-Gas or a leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should appear. Listen and smell for possible leaks.
Self-explanatory.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
133
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Test (operate) the closing feature to make sure that it will close and open the valve.
Check operating cables to make sure they can move through their entire range without
binding.
Make sure the cable tension is not too tight since that might prevent the valve from
latching properly, or vibration or jarring could cause inadvertent closure during normal
transfer operations.
Check the operators to make sure proper functioning (typically, through release of air or
nitrogen pressure and then repressurizing).
The system should be checked for leaks by pressurizing the system and checking all
connections with an ammonia-free leak testing (soap) solution. For the leak test
solution, no bubbles should form. Listen and smell for possible leaks.
The operator should fully open and completely close the valve.
Are remote emergency shutoff devices between 25 and 100 feet from the
ESV and within the path of egress?
Self-explanatory.
D. BULKHEADS – HOSES
Self-explanatory.
134
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Self-explanatory.
Are hoses free of soft spots when not under pressure, show no bulging
under pressure, and have no loose outer coverings?
Self-explanatory.
Inspect each coupling for slippage, evidenced by misalignment of the coupling on the
hose end, and/or if it is scored or exposed.
Are the ACME threads, O-rings, or gaskets in good working condition (i.e.,
showing little sign of wear)?
Check the threads on the hose end adapter or the CTMV filler connection for excessive
wear to the point that the connection leaks with a new O-ring or gasket (see sketch
below). The worn adapter or fitting must be replaced.
Are valves located so that they can be easily reached during normal
operations and in an emergency?
Check that valves are located so that they can be accessed and operated without the
use of additional tools or equipment.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Some manual shut-off valves have a small hydrostatic relief valve installed in them. If a
relief valve is present, be sure the outlet is clear and unrestricted. Be sure the rain cap
135
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
is in place.
Do valves have the proper service pressure rating, equal to or greater than
the maximum allowable working pressure of the system?
Check to make sure that the pressure rating stamped on the valves is consistent with the
maximum design pressure of other components in the pump discharge and bypass
system.
Vapor Compressor
A. GENERAL
Check for excessive external corrosion or mechanical damage to the casing, drive
assembly, suction and discharge piping, liquid trap, strainer and motor.
Check the cooling systems fins. They must be kept clean and the flywheel must be kept
free of obstructions to allow sufficient air flow and cooling.
Note: To prevent damage to the piping network from vibration, the compressor must be
bolted to a solid, level foundation that will fully support both the compressor and its drive
system. This is especially important with large units where heavier vibrations can be
expected.
They should be free of excessive cracking or significant loss of the supporting materials.
They should be level and stable, positioned so that there is no misalignment with the
piping system.
Are base plate bolts in place and securing the compressor to that
foundation?
Lubrication could vary depending on the compressor design and manufacturer. Check
the equipment manufacturer’s instructions for specific lubricants and frequency of
lubrication.
Before starting the compressor, check the crankcase for leaks, especially around the
flywheel-end of the crankshaft, the dipstick, and the breather valve assembly. When
checking the breather valve assembly, be sure that it is clear and free of any dirt or
136
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check the oil level in the crankcase before each operation. If the oil level is low, check
the manufacturer's instructions for the type of oil to use and the amount to add.
Check the oil pressure gauge frequently during every compressor operation. If the oil
pressure is unusually high or low, shut down the compressor and notify your supervisor.
Self-explanatory.
Are strainer elements in good working condition (i.e., strainer screens free
of debris) and leak-free?
Note: Compressor strainers usually have coarser screens than pump strainers.
However, they must be opened and cleaned on a regular basis to prevent them from
being clogged and restricting flow to the compressor.
While the compressor is not operating, isolate the strainer, bleed off any trapped LP-Gas
and remove the cylinder and filter screen to inspect and clean.
Check that the connections and the cover are gas tight by using a gas detector
calibrated for LP-Gas or an ammonia-free leak testing (soap) solution. No gas should be
detected. For the leak test solution, no bubbles should form. Listen and smell for
possible leaks.
Are pressure relief valves installed in the appropriate location and in good
working order?
The discharge line of most compressors is equipped with a discharge relief valve to
protect the compressor system from damage due to excessively high pressure.
Check the discharge relief valve regularly for leaks and be sure the inside of the valve is
free from corrosion and debris that would prevent the valve from opening and closing
properly.
CAUTION: When inspecting relief valves, use an inspection mirror to check the inside of
the valve. Never look directly into the outlet of any pressure relief valve.
137
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Flexible connectors should not be used to compensate for misalignment with the piping
or to take the place of elbows.
Note: Check with your supervisor regarding company policies or state/local regulations
to make sure compliance before installing or servicing flexible connectors.
Are all back check valves in proper working condition and leak-free?
Check to see that back check is completely shutting off any and all reverse flow.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Check the piping and fittings using a gas detector calibrated for LP-Gas or a leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should appear. Listen and smell for possible leaks.
Are drive belts properly aligned, tension properly set and in good working
condition?
138
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
For direct drive compressors, are shaft couplings properly aligned and in
good working condition?
Self-explanatory.
C. COMPRESSOR GAUGES
Are pressure gauges (suction and discharge) in good condition (i.e., 0 - 400
psig)?
Are valves located so that they can be easily reached during normal
operations and in an emergency?
Check that valves are located so that they can be accessed and operated without the
use of additional tools or equipment.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Some manual shut-off valves have a small hydrostatic relief valve installed in them. If a
relief valve is present, be sure the outlet is clear and unrestricted. Be sure the rain cap
is in place.
Do valves have the proper pressure rating, equal to or greater than the
required working pressure of the system?
Check to make sure that the pressure rating stamped on the valves is consistent with the
maximum design pressure of other components in the compressor suction and
discharge systems.
139
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
They should be free of excessive cracking or significant loss of the supporting materials.
The footings should be level and stable, positioned so that no shifting of the tower has
occurred.
Are all flanges and fittings properly sized for the pressure rating, equal to
or greater than the maximum allowable working pressure of the system?
Piping, flanges and fittings that can contain liquid LP-Gas, and that can be isolated by
valves and require hydrostatic relief valves, must be designed for an operating pressure
of 350 psig or a pressure that is equivalent to the maximum discharge pressure of any
pump or any source feeding the piping system if it is greater than 350 psig.
Otherwise, the minimum pressure rating is 250 psig for LP-Gas liquid or vapor at
operating pressure over 125 psig and at or below container pressure.
The minimum pressure rating is 125 psig for LP-Gas vapor at operating pressure of 125
psig or less.
Are all stainless steel flex connectors in good working condition (i.e.,
reinforcement braid is not damaged)?
Are all flow indicators and sight checks in proper working condition and
leak-free?
Where installed, sight flow indicators must be either the simple observation type or be
combined with a backflow check valve.
The sight indicators should be sufficiently clean and clear to see the flow upon liquid
transfer.
140
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check using a gas detector calibrated for LP-Gas or an ammonia-free leak testing
(soap) solution. No gas should be detected. For the leak test solution, no bubbles
should form. Listen and smell for possible leaks.
Check sections of liquid lines between shut-off valves for the presence of these valves.
Check regularly for leaks and inspect to make sure the valve is free from corrosion and
debris that could prevent the valve from opening and closing properly.
Hydrostatic relief valves designed to relieve pressure in sections of liquid piping between
closed shut-off valves must have pressure settings not less than 400 psig and not more
than 500 psig.
Hydrostatic relief valves should be fitted with rain caps to prevent moisture and debris
from accumulating inside the valve.
Check the piping and fittings using a gas detector calibrated for LP-Gas or an ammonia-
free leak testing (soap) solution. No gas should be detected. For the leak test solution,
no bubbles should appear. Listen and smell for possible leaks.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Test (operate) the closing feature to make sure that it will close and open the valve.
Are ESVs and/or back checks (including thermal release) on riser ends of
the liquid hoses in good working condition?
Operate the closing feature to make sure that it will close and open the ESV.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
141
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Are ESVs and/or back checks (including thermal release) on riser ends of
the vapor hose in good working condition?
Operate the closing feature to Check to see that it will close and open the ESV.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Check the operators to make sure proper functioning (typically, through release of air or
nitrogen pressure and then repressurizing).
The system should be checked for leaks by pressurizing the system and checking all
connections with an ammonia-free leak testing (soap) solution. For the leak test
solution, no bubbles should form. Listen and smell for possible leaks.
The operator should fully open and completely close the valve.
Are remote emergency shutoff devices between 25 and 100 feet from the
ESV and within the path of egress?
Self-explanatory.
142
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Self-explanatory.
Self-explanatory.
Are hoses free of soft spots when not under pressure, show no bulging
under pressure, and have no loose outer coverings?
Self-explanatory.
Inspect each coupling for slippage, evidenced by misalignment of the coupling on the
hose end, and/or if it is scored or exposed.
Are the ACME threads, O-rings, or gaskets in good working condition (i.e.,
showing little sign of wear)?
Check the threads on the hose end adapter or the CTMV filler connection for excessive
wear to the point that the connection leaks with a new O-ring or gasket (see sketch
below). The worn adapter or fitting must be replaced.
See equipment manufacturer’s instructions for the proper lubricant(s) and the frequency
of lubrication.
See equipment manufacturer’s instructions for the required guards and check to make
sure they are in place.
143
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Are valves located so that they can be easily reached during normal
operations and in an emergency?
Check that valves are located so that they can be accessed and operated without the
use of additional tools or equipment.
Check for leakage at all body seams, plus the connections to the piping and hose.
Check each fitting using a gas detector calibrated for LP-Gas or an ammonia-free leak
testing (soap) solution. No gas should be detected. For the leak test solution, no
bubbles should form. Listen and smell for possible leaks.
Some manual shut-off valves have a small hydrostatic relief valve installed in them. If a
relief valve is present, be sure the outlet is clear and unrestricted. Be sure the rain cap
is in place.
Do valves have the proper pressure rating, equal to or greater than the
required working pressure of the system?
Check to make sure that the pressure rating stamped on the valves is no less than 250
psig.
Scales
A. GENERAL
Check with your supervisor regarding the frequency of checking the scale(s).
The certified or standard dead weight should be approximately equal to the typical tare
weight of the cylinders being filled plus the LP-Gas contents of one of these cylinders.
Is the scale(s) properly calibrated and been certified by the proper authority
having jurisdiction?
In most states and jurisdictions, scales must bear current certification decals from
weights and measures officials.
144
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Note: Do not use oil on scale parts unless instructed to do so by the scale manufacturer.
Check for accumulation of snow, ice, leaves and other debris that could cause the scale
platform to bind and produce an inaccurate scale reading.
Are all actuators and control valves leak-free and in good working
condition (i.e., proper fluid levels and proper alignment with scale)?
Self-explanatory.
Also check scale manufacturer’s instructions for any specific or unique requirements and
instructions.
Are all sensing lines leak-free and in good working condition (i.e., free of
kinks and proper alignment with the scale)?
Self-explanatory.
C. HOSES
Self-explanatory.
Self-explanatory.
Are hoses free of soft spots when not under pressure, show no bulging
under pressure, and have no loose outer coverings?
Self-explanatory.
Inspect each coupling for slippage, evidenced by misalignment of the coupling on the
hose end, and/or if it is scored or exposed.
145
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Inspect for loose or missing bolts or fastenings on bolted hose coupling assemblies.
Are the ACME threads, O-rings, or gaskets in good working condition (i.e.,
showing little sign of wear)?
Check the threads on the hose end adapter or the CTMV filler connection for excessive
wear to the point that the connection leaks with a new O-ring or gasket (see sketch
below). The worn adapter or fitting must be replaced.
A. GENERAL
The responsible agency places a seal on the meter when it has been proved and found
to be accurate.
Note: Many state and local codes require companies to recalibrate meters on a regular
basis. Generally, this is accomplished by filling a volumetric prover (a tank of certified
capacity) through the meter being tested. The reading on the meter is then compared to
the quantity of LP-Gas in the prover and the meter adjusted accordingly. Only personnel
who are properly trained and qualified to prove meters should do so.
Check to see that the seal is not broken. If broken, the meter must be proved again and
resealed before it is placed back into service.
Be alert for erratic meter operation, obvious over or under registration, increasingly noisy
operation and excessively low delivery rates.
146
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Check the seal that is either on the input or the output shaft of the gear train to prevent
the LP-Gas from leaking out of the meter body and entering the register. The seal is
usually a U-shaped packing or O-ring that fits around the drive shaft and is designed to
be replaceable in case it begins to leak.
B. HOSES
Self-explanatory.
Self-explanatory.
Are hoses free of soft spots when not under pressure, show no bulging
under pressure, and have no loose outer coverings?
Self-explanatory.
Inspect each coupling for slippage, evidenced by misalignment of the coupling on the
hose end, and/or if it is scored or exposed.
Are the ACME threads, O-rings, or gaskets in good working condition (i.e.,
showing little sign of wear)?
Check the threads on the hose end adapter or the CTMV filler connection for excessive
wear to the point that the connection leaks with a new O-ring or gasket (see sketch
below). The worn adapter or fitting must be replaced.
Check that the breakaway device is UL 567 approved (Standard Pipe Connectors for
Flammable and Combustible Liquids and LP-Gas) and is capable of retaining liquid on
both sides of the breakaway point. If this not the case, check with your supervisor and
determine whether there is a device in place that provides equivalent protection and has
been approved by the authority having jurisdiction.
147
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
Vaporizers
A. GENERAL
The specific inspection steps will vary depending on the type of device being used to
heat the liquid LP-Gas and the manufacturer’s design. Refer to the equipment
manufacturer’s instructions for inspection requirements and procedures.
Refer to the equipment manufacturer’s instructions for the frequency and instructions for
inspecting and cleaning pilots.
On a periodic basis, have all strainers been cleaned at the inlet side of the
vaporizer(s)?
Refer to the equipment manufacturer’s instructions for the instructions and suggested
frequency for inspecting and cleaning strainers.
Refer to the equipment manufacturer’s instructions for the instructions and suggested
frequency for cleaning heavy ends from the vaporizer.
Self-explanatory.
Vaporizing burners must be installed outside of buildings, per NFPA 58. The minimum
separation distance between a vaporizing burner and container having >2,000 gallons
water capacity is 50 feet. The minimum distance between a burner and container ≤500
gallons is 10 feet, and 25 feet for containers in the 501 – 2,000 gallon range.
Regulators
A. GENERAL
148
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
manifolded vaporizers?
Self-explanatory.
Are all regulators that are outside of buildings installed and protected so
that their operation will not be affected by environmental elements (e.g.,
freezing rain, sleet, snow, ice, mud or debris) or insects?
The regulator must be installed such that the vent is protected against water
accumulation in the form of rain, sleet, snow, mud or ground water. Typically, vents and
pipe-aways are pointed downward and the opening protected with a screen.
Self-explanatory.
Self-explanatory.
Electrical Systems
A. GENERAL
Are all electrical components and wiring in compliance with Table 6.23.2.2
(Electrical Area Classification) in NFPA 58?
149
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
When classifying the extent of a hazardous area, consider the possible variations in the
spotting of railroad tanks cars and CTMVs at the unloading points.
The designated color (by OSHA) for the off (or stop) position is red.
Is the electrical emergency shutdown located not more than 20 feet (but
less than 100 feet) from any dispensing devices, and prominently labeled?
The markings for the switches (or breakers) must be visible at the point of liquid transfer.
Are all seal-off fixtures filled with suitable putty and installed in the
appropriate locations?
A conduit seal-off fixture filled with a suitable putty must be installed within 18 inches of
any spark producing device within a Hazardous Classified Location, unless the
enclosure is outfitted with a factory seal at the conduit connection.
A conduit seal-off fixture filled with a suitable putty must be installed where a conduit is
entering or leaving a Hazardous Classified Location (i.e., between the Hazardous
Classified Location dispenser area and the main electrical supply) in order to prevent
150
Operations & Maintenance Handbook Section 7
for LP-Gas Storage Facilities Maintenance & Inspection
Checklist Procedure
151
Operations & Maintenance Handbook Section 8
for LP-Gas Storage Facilities Maintenance of
Fire Protection Equipment
This section of the Handbook provides owners or operators of LP-Gas bulk plants with
an introduction and general guidance for complying with the requirements of NFPA 58
for maintaining fire protection equipment as defined in Chapter 14 (§14.3.3).
References
• NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based
Fire Protection Systems, 2014 Edition
General Requirements
Facilities must prepare and implement a program for all plant fire protection equipment.
Maintenance activities of fire protection equipment must be scheduled so that a
minimum of equipment is taken out of service at any time and is returned to service in a
reasonable time period. NFPA has not defined what “minimum” and “reasonable” mean
in terms of number and length of time. Therefore, site management should make every
effort to meet the intent of the requirement.
Portable fire extinguishers must be maintained in accordance with NFPA 10, Standard
for Portable Fire Extinguishers.
152
Operations & Maintenance Handbook Section 8
for LP-Gas Storage Facilities Maintenance of
Fire Protection Equipment
a) Where cylinders of 1000 lb water capacity or less are stored and are
awaiting use, resale or exchange, the following fire protection
requirements apply:
153
Operations & Maintenance Handbook Section 8
for LP-Gas Storage Facilities Maintenance of
Fire Protection Equipment
h) Each location must provide training to all employees upon initial hiring
and at least annually thereafter to familiarize them with the general
principles and proper operation of the fire extinguisher.
154
Operations & Maintenance Handbook Section 8
for LP-Gas Storage Facilities Maintenance of
Fire Protection Equipment
Qualified
Individual or
Extinguisher Inspection or Certifying Signature
(# or Location) Maintenance Performed Corrective Action Date (Owner Rep.)
Company
(Monthly / Annual)
Name
(as applicable)
155
Operations & Maintenance Handbook Section 8
for LP-Gas Storage Facilities Maintenance of
Fire Protection Equipment
The following information and material are provided for those plants where water-
base fire protection systems have been installed due to jurisdictional
requirements.
Summary of Requirements
156
Operations & Maintenance Handbook Section 8
for LP-Gas Storage Facilities Maintenance of
Fire Protection Equipment
Qualified
Individual or
Equipment Procedure Performed
Certifying Date Signature
Description (Owner Rep.)
Company
Name
157
Operations & Maintenance Handbook Section 9
for LP-Gas Storage Facilities Manufacturers’ Equipment
Information
Section Purpose
Owners and managers/supervisors must obtain that information and include it within this
section of this handbook for ready reference and use by operators, technicians, drivers
and other personnel in carrying out their responsibilities.
Plant personnel should review this information to determine the appropriate action to
take when operating equipment or performing equipment inspections, maintenance and
repairs.
► ACTION ◄
158
Operations & Maintenance Handbook Appendix A
for LP-Gas Storage Facilities References
Appendix A: References
The documents or portions of them, that are listed in this appendix are referenced in or
used to perform the procedures noted in one or more sections within this handbook.
American Petroleum Institute, API-ASME Code for Unfired Pressure Vessels for
Petroleum Liquids and Gases, Pre-July 1, 1961.
Compressed Gas Association, CGA C-6, Standard for Visual Inspection of Steel
Compressed Gas Cylinders, 2007.
Compressed Gas Association, CGA C-3, Guidelines for Visual Inspection and
Requalification of Low Pressure Aluminum Compressed Gas Cylinders, 2005.
National Fire Protection Association, NFPA 10, Standard for Portable Fire
Extinguishers, 2013 Edition.
National Fire Protection Association, NFPA 25, Standard for the Inspection,
Testing and Maintenance of Water-Based Fire Protection Systems, 2014 Edition.
National Fire Protection Association, NFPA 58, Liquefied Petroleum Gas Code,
2014 Edition.
National Fire Protection Association, NFPA 58, Liquefied Petroleum Gas Code,
2011 Edition.
National Fire Protection Association, NFPA 58, Liquefied Petroleum Gas Code,
2008 Edition.
159
Operations & Maintenance Handbook Appendix A
for LP-Gas Storage Facilities References
National Fire Protection Association, NFPA 58, Liquefied Petroleum Gas Code,
2004 Edition.
National Fire Protection Association, NFPA 58, Liquefied Petroleum Gas Code,
2001 Edition.
National Fire Protection Association, NFPA 58, Liquefied Petroleum Gas Code,
1995 Edition.
National Fire Protection Association, NFPA 70, National Electric Code®, 2014
Edition.
U.S. Government Publication, Title 21, Code of Federal Regulations, “Food and
Drugs”, Chapter I, Part 184.1655.
160