Contractor Consultant
PREPARED BY: REVIEWED BY: VERIFIED BY:
SIGNATURE: SIGNATURE: SIGNATURE:
TABLE OF CONTENTS
Section 3 Design 15
3.1 Construction Drawing Status
3.2 Shop Drawing Status
SECTION 1:
EXECUTIVE SUMMARY
The Projek Penswastaan Lebuhraya Bertingkat Sungai Besi – Ulu Kelang (SUKE) will be on
elevated Expressway with mainline starting from the existing Shah Alam Highway (KESAS) at
Bukit Jalil in the South to Middle Ring Road 2 (MRR2) at Ulu Kelang in the north.
Our solution and implementation for the works that is intended to fulfil the stated and implied needs
and requirements based on our extensive experience in similar installations.
Our solution for the “SUPPLY, DELIVERY, INSTALLATION, TESTING, COMMISSIONING AND
MAINTENANCE OF TRAFFIC CONTROL AND SURVEILLANCE SYSTEM (TCSS) FOR
PROJECT SUNGAI BESI – ULU KELANG ELEVATED EXPRESSWAY (TCSS, SUKE)”, is based
on the best practiced TCSS solutions that have been proven locally as well as abroad.
The systems to be provided are represented by local companies who act as the local suppliers,
system integrators, distributors and installers for the overseas principals (for non-local products).
Contract Title :
NO. ISSUE
1. There is partly handover site from WPC to Turbine Technique for start work.
The contract completion date for TCSS is by end of June 2020, Extension of
Time No. 2 (EOT2) contract completion on 15th June 2021.
No. Issue
1 There is partly handover site from WPC to Turbine Technique for start
work. The contract completion date for TCSS is by end of June 2020,
Extension of Time No. 2 (EOT2) contract completion on 15th June 2021.
SECTION 2:
ORGANIZATION CHART
SECTION 3:
DESIGN
DATE
NO. DRAWING TITTLE DRAWING NUMBER REVISION
RECEIVED
Received
endorsement
Traffic Control & Surveillance
1 W/SUKE/9455/E/TCSS/DL/1.0 00 hardcopy on
System – Drawing List & General
16/10/2019
by HSSI
Traffic Control & Surveillance
2 W/SUKE/9455/E/TCSS/LE/1.0 00
System – List of Equipment
Traffic Control & Surveillance
3 System – Overall Layout Section W/SUKE/9455/E/TCSS/OL/1.0 00
A&B
Traffic Control & Surveillance
4 W/SUKE/9455/E/TCSS/SA/L/1.0-1.25 00
System – Plan Drawing Section A
Traffic Control & Surveillance
5 W/SUKE/9455/E/TCSS/SB/L/1.0-1.19 00
System – Plan Drawing Section B
Traffic Control & Surveillance
6 W/SUKE/9455/E/TCSS/SCH/2.0-2.13 00
System – Schematic Diagram
Traffic Control & Surveillance
7 W/SUKE/9455/E/TCSS/SD/3.0-3.33 00
System – Typical Drawing
Issued
endorsement
Traffic Control & Surveillance
8 W/TT/SUKE/504/TCSS/SA/DL/1.0 01 hardcopy on
System : Drawing & Legend
February
2020 to HSSI
Traffic Control & Surveillance
9 W/TT/SUKE/504/TCSS/SA/LE/1.0 01
System : List of Equipment
Traffic Control & Surveillance
10 System : Overall Layout Section W/TT/SUKE/504/TCSS/SA/OL/1.0 01
A
Traffic Control & Surveillance
11 System : CH.0.000m to W/TT/SUKE/504/TCSS/SA/1.1 – 1.22 01
CH.10700.00m Section A
Traffic Control & Surveillance
12 System : Index Plan Drawing for W/TT/SUKE/504/TCSS/SB/L/1.0 01
Section B
Traffic Control & Surveillance
13 System : CH110290.833m to W/TT/SUKE/504/TCSS/SB/L/1.1-1.19 01
CH.23812.627m Section B
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
LATEST
NO. DRAWING TITTLE DRAWING NUMBER REVISION DATE STATUS
SUBMITTED
SECTION 4:
Progress (%)
As Final
III. COMMUNICATION SYSTEM 1.30% 0.00 % 0.00 % 0.00 %
Measurement
IV. VMS SYSTEM 10 4.60% 0.00 % 0.00 % 0.00 %
V. DRS SYSTEM – HARDWARE USING
10 2.33% 0.00 % 0.00 % 0.00 %
VMS
VI. CCTV SYSTEM 40 5.45% 0.00 % 0.10 % 0.43 %
VII. ET SYSTEM 22 0.84% 0.00% 0.01 % 0.01%
VIII. VIDS SYSTEM 44 2.85% 0.00 % 0.16 % 0.16 %
IX. HIS & TRIS SYSTEM 1 - rate only 0.00% 0.00 % 0.00 % 0.00 %
X. CONTROL CENTRE & CENTRAL
1 0.51% 0.00 % 0.00 % 0.01 %
COMPUTER SYSTEM (CCS)
XI. VIDEOWALL SYSTEM 4x4 0.62% 0.00 % 0.00 % 0.00 %
E) PROVISIONAL SUM 4.49 % 0.00 % 0.00% 0.00 %
F) PROJECT COMPLETION & HANDING
8.81 % 0.00 % 0.00% 0.00 %
OVER
TOTAL 100.00% 42.03%
~REFER ATTACHMENT A~
SUKE/TCSS-EOT2-JUNE2.7 DELAY EVENT SITE HANDOVER 428 21-Jan-20 30-Jun-21 428 21-Jan-20 A 15-Nov-21 0% 0% -126 15-Nov-21, SUKE/TCSS-EOT2-JUNE2.7 DELA
SUKE/TCSS-EOT2-JUNE2.2 PRELIMINARIES 231 21-Jan-20 31-Oct-20 231 21-Jan-20 A 23-Jul-21 100% 90% -177 23-Jul-21, SUKE/TCSS-EOT2-JUNE2.2 PRELIMINARIES
A1040 SUBMISSION FOR MATERIAL/EQUIPMENT APPROVAL 231 21-Jan-20 31-Oct-20 231 21-Jan-20 A 23-Jul-21 100% 90% -177 SUBMISSION FOR MATERIAL/EQUIPMENT APPROVAL
SUKE/TCSS-EOT2-JUNE2.3 PROCUREMENT & LOGISTIC 408 12-May-20 25-Sep-21 408 12-May-20 A 25-Sep-21 100% 50.39% -105 25-Sep-21, SUKE/TCSS-EOT2-JUNE2.3 PROCUREM
SUKE/TCSS-EOT2-JUNE2.3.01 COMMUNICATION SYSTEM 46 19-Dec-20 13-Feb-21 46 19-Dec-20 A 29-Jul-21 100% 40% -139 29-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.01 COMMUNICATION
SUKE/TCSS-EOT2-JUNE2.3.02 POWER SUPPLY SYTEM 48 26-Jun-21 23-Aug-21 48 26-Jun-21 A 29-Jul-21 100% 40% -152 29-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.02 POWER SUPPLY
SUKE/TCSS-EOT2-JUNE2.3.03 VARIABLE MESSAGE SIGN (VMS) 146 12-May-20 06-Nov-20 146 12-May-20 A 22-Jul-21 100% 50% -143 22-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.03 VARIABLE MESSA
SUKE/TCSS-EOT2-JUNE2.3.04 CLOSED CIRCUIT TELEVISION (CCTV) 1 12-May-20 12-May-20 1 12-May-20 A 25-Jun-21 0% 0% -177 25-Jun-21, SUKE/TCSS-EOT2-JUNE2.3.04 CLOSED CIRCUIT TEL
SUKE/TCSS-EOT2-JUNE2.3.05 EMERGENCY TELEPHONE SYSTEM (ETS) 405 12-May-20 22-Sep-21 405 12-May-20 A 22-Sep-21 100% 0% -124 22-Sep-21, SUKE/TCSS-EOT2-JUNE2.3.05 EMERGE
SUKE/TCSS-EOT2-JUNE2.3.06 VEHICLE INCIDENT DETECTION SYSTEM (VIDS) 143 13-May-20 04-Nov-20 143 13-May-20 A 16-Aug-21 100% 70% -177 16-Aug-21, SUKE/TCSS-EOT2-JUNE2.3.06 VEHICLE INCID
SUKE/TCSS-EOT2-JUNE2.3.07 CENTRAL COMPUTER SYSTEM (CCS) 397 13-May-20 13-Sep-21 397 13-May-20 A 13-Sep-21 100% 0% -162 13-Sep-21, SUKE/TCSS-EOT2-JUNE2.3.07 CENTRAL
SUKE/TCSS-EOT2-JUNE2.3.08 VIDEO WALL SYSTEM 45 14-Sep-20 06-Nov-20 45 14-Sep-20 A 10-Jul-21 100% 70% -44 10-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.08 VIDEO WALL SYSTE
SUKE/TCSS-EOT2-JUNE2.3.09 149TIME
DYNAMIC ROAD INFORMATION SYSTEM (DRS) & TRAVEL 13-May-20 11-Nov-20
SIGNBOARD (TTS) 149 13-May-20 A 24-Jul-21 100% 50% -142 24-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.09 DYNAMIC ROAD IN
SUKE/TCSS-EOT2-JUNE2.3.10 TCSS CONTROL CENTRE 407 13-May-20 25-Sep-21 407 13-May-20 A 25-Sep-21 100% 0% -172 25-Sep-21, SUKE/TCSS-EOT2-JUNE2.3.10 TCSS CO
SUKE/TCSS-EOT2-JUNE2.9 CENTRAL COMPUTER SYSTEM (CCS) 561 12-Feb-20 29-Dec-21 561 12-Feb-20 A 29-Dec-21 100% 10.09% -163 29-Dec-21, SUKE/TCSS-EOT2-JUNE2.9
SUKE/TCSS-EOT2-JUNE2.9.1 ANALYSIS 6 12-Feb-20 18-Feb-20 6 12-Feb-20 A 25-Jun-21 100% 90% -147 25-Jun-21, SUKE/TCSS-EOT2-JUNE2.9.1 ANALYSIS
SUKE/TCSS-EOT2-JUNE2.9.2 DESIGN 408 04-Mar-20 16-Jul-21 408 04-Mar-20 A 16-Jul-21 100% 16% -147 16-Jul-21, SUKE/TCSS-EOT2-JUNE2.9.2 DESIGN
SUKE/TCSS-EOT2-JUNE2.9.3 DEVELOPMENT 60 25-Mar-20 09-Jun-20 60 25-Mar-20 A 12-Aug-21 100% 62.14% -147 12-Aug-21, SUKE/TCSS-EOT2-JUNE2.9.3 DEVELOPMENT
SUKE/TCSS-EOT2-JUNE2.9.4 DEPLOYMENT 218 03-Mar-21 25-Nov-21 218 25-Nov-20 A 25-Nov-21 100% 20% -163 25-Nov-21, SUKE/TCSS-EOT2-JUNE2.9.4 DE
SUKE/TCSS-EOT2-JUNE2.9.5 QUALITY ASSURANCE LIBRARY 199 17-Mar-21 16-Nov-21 199 25-Nov-20 A 16-Nov-21 100% 34.27% -163 16-Nov-21, SUKE/TCSS-EOT2-JUNE2.9.5 QUA
SUKE/TCSS-EOT2-JUNE2.9.6 QUALITY ASSURANCE TEST 24 16-Nov-21 14-Dec-21 24 16-Nov-21 14-Dec-21 100% 0% -163 14-Dec-21, SUKE/TCSS-EOT2-JUNE2.9.6
SUKE/TCSS-EOT2-JUNE2.9.8 INTEGRATION WITH MHA 27 01-Oct-21 02-Nov-21 27 01-Oct-21 02-Nov-21 100% 0% -163 02-Nov-21, SUKE/TCSS-EOT2-JUNE2.9.8 INTEG
SUKE/TCSS-EOT2-JUNE2.9.7 TRAINING 12 14-Dec-21 29-Dec-21 12 14-Dec-21 29-Dec-21 100% 0% -163 29-Dec-21, SUKE/TCSS-EOT2-JUNE2.9.
SUKE/TCSS-EOT2-JUNE2.4 SITE WORKS 339 25-Nov-20 13-Jan-22 339 25-Nov-20 A 13-Jan-22 100% 3.85% -175 13-Jan-22, SUKE/TCSS-EOT2-JUNE2.
SUKE/TCSS-EOT2-JUNE2.4.9 CIVIL WORKS 203 25-Nov-20 30-Jul-21 203 25-Nov-20 A 30-Jul-21 100% 73.8% -39 30-Jul-21, SUKE/TCSS-EOT2-JUNE2.4.9 CIVIL WORKS
SUKE/TCSS-EOT2-JUNE2.4.1 COMMUNICATION SYSTEM 130 25-Jun-21 30-Nov-21 130 25-Jun-21 30-Nov-21 100% 0% -150 30-Nov-21, SUKE/TCSS-EOT2-JUNE2.4.1 C
SUKE/TCSS-EOT2-JUNE2.4.2 POWER SUPPLY & SURGE PROTECTION SYSTEM 157 25-Jun-21 01-Jan-22 157 25-Jun-21 01-Jan-22 100% 0% -177 01-Jan-22, SUKE/TCSS-EOT2-JUNE2.4.
SUKE/TCSS-EOT2-JUNE2.4.3 VARIABLE MESSAGE SIGN (VMS) 136 25-Jun-21 07-Dec-21 136 25-Jun-21 07-Dec-21 100% 0% -145 07-Dec-21, SUKE/TCSS-EOT2-JUNE2.4.3 V
SUKE/TCSS-EOT2-JUNE2.4.4 CLOSED CIRCUIT TELEVISION (CCTV) 131 25-Jun-21 01-Dec-21 131 25-Jun-21 A 01-Dec-21 100% 3.61% -146 01-Dec-21, SUKE/TCSS-EOT2-JUNE2.4.4 C
SUKE/TCSS-EOT2-JUNE2.4.5 EMERGENCY TELEPHONE SYSTEM (ETS) 111 25-Jun-21 08-Nov-21 111 25-Jun-21 A 08-Nov-21 100% 1.06% -126 08-Nov-21, SUKE/TCSS-EOT2-JUNE2.4.5 EME
SUKE/TCSS-EOT2-JUNE2.4.6 VEHICLE INCIDENT DETECTION SYSTEM (VIDS) 166 25-Jun-21 13-Jan-22 166 25-Jun-21 A 13-Jan-22 100% 1.66% -177 13-Jan-22, SUKE/TCSS-EOT2-JUNE2.
SUKE/TCSS-EOT2-JUNE2.4.7 135
DYNAMIC ROAD INFORMATION SYSTEM (DRS) & TRAVEL 25-Jun-21
TIME 06-Dec-21
SIGNBOARDS (TTS) 135 25-Jun-21 06-Dec-21 100% 0% -144 06-Dec-21, SUKE/TCSS-EOT2-JUNE2.4.7 D
SUKE/TCSS-EOT2-JUNE2.4.8 CONTROL CENTRE 133 31-Jul-21 10-Jan-22 133 31-Jul-21 A 10-Jan-22 100% 1.49% -172 10-Jan-22, SUKE/TCSS-EOT2-JUNE2.4
SUKE/TCSS-EOT2-JUNE2.5 TESTING AND COMMISSIONING 38 01-Dec-21 15-Jan-22 38 01-Dec-21 15-Jan-22 100% 0% -177 15-Jan-22, SUKE/TCSS-EOT2-JUNE2
SUKE/TCSS-EOT2-JUNE2.6 HANDING OVER 130 12-Aug-21 17-Jan-22 130 12-Aug-21 17-Jan-22 100% 0% -178 17-Jan-22, SUKE/TCSS-EOT2-JUNE2
Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: Critical.
Remaining Work Milestone © Oracle Corporation
SUKE TRAFFIC CONTROL AND SURVEILLANCE SYSTEM (TCSS) EOT2 ATTACHMENT B 09-Jul-21 12:00
Activity ID Activity Name BL1 BL1 Start BL1 Finish Original Start Finish Schedule % Performance Total Float 2020 2021 2022
Duration Duration Complete % Complete
A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
SUKE/TCSS-EOT2-JUNE2.1 START OF PROJECT 522 08-Aug-19 15-May-21 522 08-Aug-19 A 15-May-21 A 0% 0% 15-May-21 A,SUKE/TCSS-EOT2-JUNE2.1 START OF PROJECT
SUKE/TCSS-EOT2-JUNE2.7 DELAY EVENT SITE HANDOVER 560 08-Aug-19 30-Jun-21 560 08-Aug-19 A 15-Nov-21 0% 0% -126 15-Nov-21, SUKE/TCSS-EOT2-JUNE2.7 DELA
SUKE/TCSS-EOT2-JUNE2.2 PRELIMINARIES 363 08-Aug-19 31-Oct-20 363 08-Aug-19 A 23-Jul-21 100% 96.87% -32 23-Jul-21, SUKE/TCSS-EOT2-JUNE2.2 PRELIMINARIES
A1030 SUBMISSION OF SHOP DRAWINGS 231 21-Jan-20 31-Oct-20 231 21-Jan-20 A 31-Dec-20 A 100% 100% SUBMISSION OF SHOP DRAWINGS
A1040 SUBMISSION FOR MATERIAL/EQUIPMENT APPROVAL 231 21-Jan-20 31-Oct-20 231 21-Jan-20 A 23-Jul-21 100% 90% -177 SUBMISSION FOR MATERIAL/EQUIPMENT APPROVAL
A1050 SUBMISSION OF CONTRACTUAL DOCUMENTS 15 08-Aug-19 26-Aug-19 15 08-Aug-19 A 26-Aug-19 A 100% 100% SUBMISSION OF CONTRACTUAL DOCUMENTS
SUKE/TCSS-EOT2-JUNE2.3 PROCUREMENT & LOGISTIC 408 12-May-20 25-Sep-21 408 12-May-20 A 25-Sep-21 100% 64.34% -105 25-Sep-21, SUKE/TCSS-EOT2-JUNE2.3 PROCUREM
SUKE/TCSS-EOT2-JUNE2.3.01 COMMUNICATION SYSTEM 226 12-May-20 13-Feb-21 226 12-May-20 A 29-Jul-21 100% 40% -139 29-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.01 COMMUNICATION
SUKE/TCSS-EOT2-JUNE2.3.02 POWER SUPPLY SYTEM 382 12-May-20 23-Aug-21 382 12-May-20 A 29-Jul-21 100% 40% -152 29-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.02 POWER SUPPLY
SUKE/TCSS-EOT2-JUNE2.3.03 VARIABLE MESSAGE SIGN (VMS) 146 12-May-20 06-Nov-20 146 12-May-20 A 22-Jul-21 100% 50% -143 22-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.03 VARIABLE MESSA
SUKE/TCSS-EOT2-JUNE2.3.04 CLOSED CIRCUIT TELEVISION (CCTV) 155 12-May-20 18-Nov-20 155 12-May-20 A 25-Jun-21 100% 100% -143 25-Jun-21, SUKE/TCSS-EOT2-JUNE2.3.04 CLOSED CIRCUIT TEL
SUKE/TCSS-EOT2-JUNE2.3.05 EMERGENCY TELEPHONE SYSTEM (ETS) 405 12-May-20 22-Sep-21 405 12-May-20 A 22-Sep-21 100% 0% -124 22-Sep-21, SUKE/TCSS-EOT2-JUNE2.3.05 EMERGE
SUKE/TCSS-EOT2-JUNE2.3.06 VEHICLE INCIDENT DETECTION SYSTEM (VIDS) 143 13-May-20 04-Nov-20 143 13-May-20 A 16-Aug-21 100% 70% -177 16-Aug-21, SUKE/TCSS-EOT2-JUNE2.3.06 VEHICLE INCID
SUKE/TCSS-EOT2-JUNE2.3.07 CENTRAL COMPUTER SYSTEM (CCS) 397 13-May-20 13-Sep-21 397 13-May-20 A 13-Sep-21 100% 0% -162 13-Sep-21, SUKE/TCSS-EOT2-JUNE2.3.07 CENTRAL
SUKE/TCSS-EOT2-JUNE2.3.08 VIDEO WALL SYSTEM 146 12-May-20 06-Nov-20 146 12-May-20 A 10-Jul-21 100% 70% -44 10-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.08 VIDEO WALL SYSTE
149TIME
SUKE/TCSS-EOT2-JUNE2.3.09 DYNAMIC ROAD INFORMATION SYSTEM (DRS) & TRAVEL 13-May-20 11-Nov-20
SIGNBOARD (TTS) 149 13-May-20 A 24-Jul-21 100% 50% -142 24-Jul-21, SUKE/TCSS-EOT2-JUNE2.3.09 DYNAMIC ROAD IN
SUKE/TCSS-EOT2-JUNE2.3.10 TCSS CONTROL CENTRE 407 13-May-20 25-Sep-21 407 13-May-20 A 25-Sep-21 100% 0% -172 25-Sep-21, SUKE/TCSS-EOT2-JUNE2.3.10 TCSS CO
SUKE/TCSS-EOT2-JUNE2.9 CENTRAL COMPUTER SYSTEM (CCS) 609 12-Dec-19 29-Dec-21 609 12-Dec-19 A 29-Dec-21 100% 20.47% -163 29-Dec-21, SUKE/TCSS-EOT2-JUNE2.9
SUKE/TCSS-EOT2-JUNE2.9.1 ANALYSIS 54 12-Dec-19 18-Feb-20 54 12-Dec-19 A 25-Jun-21 100% 99.17% -147 25-Jun-21, SUKE/TCSS-EOT2-JUNE2.9.1 ANALYSIS
SUKE/TCSS-EOT2-JUNE2.9.2 DESIGN 420 19-Feb-20 16-Jul-21 420 19-Feb-20 A 16-Jul-21 100% 53.33% -147 16-Jul-21, SUKE/TCSS-EOT2-JUNE2.9.2 DESIGN
SUKE/TCSS-EOT2-JUNE2.9.3 DEVELOPMENT 60 25-Mar-20 09-Jun-20 60 25-Mar-20 A 12-Aug-21 100% 62.14% -147 12-Aug-21, SUKE/TCSS-EOT2-JUNE2.9.3 DEVELOPMENT
SUKE/TCSS-EOT2-JUNE2.9.4 DEPLOYMENT 218 03-Mar-21 25-Nov-21 218 25-Nov-20 A 25-Nov-21 100% 20% -163 25-Nov-21, SUKE/TCSS-EOT2-JUNE2.9.4 DE
SUKE/TCSS-EOT2-JUNE2.9.5 QUALITY ASSURANCE LIBRARY 199 17-Mar-21 16-Nov-21 199 25-Nov-20 A 16-Nov-21 100% 34.27% -163 16-Nov-21, SUKE/TCSS-EOT2-JUNE2.9.5 QUA
SUKE/TCSS-EOT2-JUNE2.9.6 QUALITY ASSURANCE TEST 24 16-Nov-21 14-Dec-21 24 16-Nov-21 14-Dec-21 100% 0% -163 14-Dec-21, SUKE/TCSS-EOT2-JUNE2.9.6
SUKE/TCSS-EOT2-JUNE2.9.8 INTEGRATION WITH MHA 27 01-Oct-21 02-Nov-21 27 01-Oct-21 02-Nov-21 100% 0% -163 02-Nov-21, SUKE/TCSS-EOT2-JUNE2.9.8 INTEG
SUKE/TCSS-EOT2-JUNE2.9.7 TRAINING 12 14-Dec-21 29-Dec-21 12 14-Dec-21 29-Dec-21 100% 0% -163 29-Dec-21, SUKE/TCSS-EOT2-JUNE2.9.
SUKE/TCSS-EOT2-JUNE2.4 SITE WORKS 339 25-Nov-20 13-Jan-22 339 25-Nov-20 A 13-Jan-22 100% 6.46% -175 13-Jan-22, SUKE/TCSS-EOT2-JUNE2.
SUKE/TCSS-EOT2-JUNE2.4.9 CIVIL WORKS 203 25-Nov-20 30-Jul-21 203 25-Nov-20 A 30-Jul-21 100% 79.64% -39 30-Jul-21, SUKE/TCSS-EOT2-JUNE2.4.9 CIVIL WORKS
SUKE/TCSS-EOT2-JUNE2.4.1 COMMUNICATION SYSTEM 130 25-Jun-21 30-Nov-21 130 25-Jun-21 30-Nov-21 100% 0% -150 30-Nov-21, SUKE/TCSS-EOT2-JUNE2.4.1 C
SUKE/TCSS-EOT2-JUNE2.4.2 POWER SUPPLY & SURGE PROTECTION SYSTEM 157 25-Jun-21 01-Jan-22 157 25-Jun-21 01-Jan-22 100% 0% -177 01-Jan-22, SUKE/TCSS-EOT2-JUNE2.4.
SUKE/TCSS-EOT2-JUNE2.4.3 VARIABLE MESSAGE SIGN (VMS) 136 25-Jun-21 07-Dec-21 136 25-Jun-21 07-Dec-21 100% 0% -145 07-Dec-21, SUKE/TCSS-EOT2-JUNE2.4.3 V
SUKE/TCSS-EOT2-JUNE2.4.4 CLOSED CIRCUIT TELEVISION (CCTV) 131 25-Jun-21 01-Dec-21 131 25-Jun-21 A 01-Dec-21 100% 7.93% -146 01-Dec-21, SUKE/TCSS-EOT2-JUNE2.4.4 C
SUKE/TCSS-EOT2-JUNE2.4.5 EMERGENCY TELEPHONE SYSTEM (ETS) 111 25-Jun-21 08-Nov-21 111 25-Jun-21 A 08-Nov-21 100% 1.06% -126 08-Nov-21, SUKE/TCSS-EOT2-JUNE2.4.5 EME
SUKE/TCSS-EOT2-JUNE2.4.6 VEHICLE INCIDENT DETECTION SYSTEM (VIDS) 166 25-Jun-21 13-Jan-22 166 25-Jun-21 A 13-Jan-22 100% 5.53% -177 13-Jan-22, SUKE/TCSS-EOT2-JUNE2.
SUKE/TCSS-EOT2-JUNE2.4.7 135
DYNAMIC ROAD INFORMATION SYSTEM (DRS) & TRAVEL 25-Jun-21
TIME 06-Dec-21
SIGNBOARDS (TTS) 135 25-Jun-21 06-Dec-21 100% 0% -144 06-Dec-21, SUKE/TCSS-EOT2-JUNE2.4.7 D
SUKE/TCSS-EOT2-JUNE2.4.8 CONTROL CENTRE 142 21-Jul-21 10-Jan-22 142 21-Jul-21 A 10-Jan-22 100% 1.58% -172 10-Jan-22, SUKE/TCSS-EOT2-JUNE2.4
SUKE/TCSS-EOT2-JUNE2.5 TESTING AND COMMISSIONING 38 01-Dec-21 15-Jan-22 38 01-Dec-21 15-Jan-22 100% 0% -177 15-Jan-22, SUKE/TCSS-EOT2-JUNE2
SUKE/TCSS-EOT2-JUNE2.6 HANDING OVER 130 12-Aug-21 17-Jan-22 130 12-Aug-21 17-Jan-22 100% 0% -178 17-Jan-22, SUKE/TCSS-EOT2-JUNE2
Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
SUPPLY, DELIVERY, INSTALLATION, TESTING, COMMISSIONING AND MAINTENANCE OF TRAFFIC CONTROL AND SURVEILLANCE SYSTEM (TCSS) FOR PROJECT SUNGAI BESI – ULU
KELANG ELEVATED EXPRESSWAY (SUKE)
60.00% 65.27%
45.13%
50.00% 42.80% 42.90% 43.32% 43.65%
37.99% 39.65%
40.00% 31.34% 32.54%
30.00% 23.35% 23.35% 23.35%
18.60% 19.25% 32.05%
20.00% 13.34% 15.43%
10.45%
10.00% 4.10% 5.35%
0.00% 0.00% 0.50% 1.00% 2.00%
Nov-19
Dec-19
Jun-20
Aug-20
Nov-20
Dec-20
Jun-21
May-20
May-21
Sep-19
Jan-20
Sep-20
Jan-21
Oct-19
Feb-20
Apr-20
Oct-20
Feb-21
Apr-21
Jul-19
Jul-20
Mar-20
Mar-21
0.00%
M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23
2019 2020 2021
MONTH
Jul- Aug Sep Oct- Nov Dec- Jan- Feb- Mar- Apr- May Jun- Jul- Aug Sep Oct- Nov Dec- Jan- Feb- Mar- Apr- May Jun-
19 -19 -19 19 -19 19 20 20 20 20 -20 20 20 -20 -20 20 -20 20 21 21 21 21 -21 21
Rev.02
(Revised
WP 0.00 3.07 3.29 3.29 3.29 3.29 3.38 3.95 4.59 5.30 5.85 6.46 7.12 7.69 8.28 8.90 9.02 10.3 32.0 65.2 79.1 84.2 88.2 100.
EOT2) % % % % % % % % % % % % % % % % % 0% 5% 7% 6% 4% 2% 00%
PLANNE
D%
Rev.02
(Proposal
WP 0.00 3.07 0.22 0.00 0.00 0.00 0.09 0.57 0.64 0.71 0.55 0.61 0.66 0.57 0.59 0.62 0.12 1.28 21.7 33.2 13.8 5.08 3.98 11.7
EOT2) % % % % % % % % % % % % % % % % % % 5% 2% 9% % % 8%
INCREME
NTAL %
ACTUAL 0.00 0.00 0.50 1.00 2.00 4.10 5.35 10.4 13.3 15.4 18.6 19.2 23.3 23.3 23.3 31.3 32.5 37.9 39.6 42.8 42.9 43.3 43.6 45.
% % % % % % % % 5% 4% 3% 0% 5% 5% 5% 5% 4% 4% 9% 5% 0% 0% 2% 5% 13%
INCREME 0.00 0.00 0.50 0.50 1.00 2.10 1.25 5.10 2.89 2.09 3.17 0.65 4.10 0.00 0.00 7.99 1.20 5.45 1.66 3.15 0.10 0.42 0.3 1.4
NTAL % % % % % % % % % % % % % % % % % % % % % % % 3% 8%
MONTHLY PROGRESS REPORT TCSS NO. 021
SUPPLY, DELIVERY, INSTALLATION, TESTING, COMMISSIONING AND MAINTENANCE OF TRAFFIC CONTROL AND SURVEILLANCE SYSTEM (TCSS) FOR PROJECT SUNGAI BESI – ULU
KELANG ELEVATED EXPRESSWAY (SUKE)
80.00%
72.47%
60.00%
54.08%
40.00%
36.53%
20.00%
17.41%
4.62% 6.46%
0.76% 1.72% 2.07% 2.49% 2.93% 3.12%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.72% 0.72% 0.73%
4.21%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.39% 0.39% 0.94%
Aug-19
Nov-19
Dec-19
Feb-20
Apr-20
Aug-20
Nov-20
Jun-20
Dec-20
Feb-21
Apr-21
Jun-21
Sep-19
Mar-20
May-20
Mar-21
May-21
Jan-20
Sep-20
Jan-21
Oct-19
Oct-20
Jul-19
Jul-20
M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23
2019 2020 2021
MONTH
Jul- Aug Sep Oct- Nov Dec Jan- Feb- Mar- Apr- May Jun- Jul- Aug Sep Oct- Nov Dec Jan- Feb- Mar- Apr- May Jun-
19 -19 -19 19 -19 -19 20 20 20 20 -20 20 20 -20 -20 20 -20 -20 21 21 21 21 -21 21
Rev.02
(Revised
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.39 0.39 0.94 4.21 17.4 36.5 54.0 72.4 90.7 100.
WP EOT2)
% % % % % % % % % % % % % % % % % % 1% 3% 8% 7% 4% 00%
PLANNED
%
Rev.02
(Proposal
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.72 0.00 0.00 12.5 20.1 17.7 16.6 18.3 13.8 3.27 13.2 19.1 17.5 18.3 18.2 9.26
WP EOT2)
% % % % % % % % % % % 2% 8% 3% 9% 6% 0% % 0% 2% 5% 9% 7% %
INCREME
NTAL %
ACTUAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.72 0.72 0.73 0.76 1.72 2.07 2.49 2.93 3.12 4.6 6.46
% % % % % % % % % % % % % % % % % % % % % % % 2% %
INCREME 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.72 0.00 0.01 0.03 0.96 0.35 0.42 0.44 0.19 1.5 1.54
NTAL % % % % % % % % % % % % % % % % % % % % % % % % %
SECTION 5:
FINANCIAL PROGRESS
CUM. PAYMENT
CLAIM CUM. CLAIM CERTIFIED DATE PAYMENT
CERT PERIOD SUBMISSION CERTIFIED RECEIVED
AMOUNT AMOUNT AMOUNT CERTIFIED RECEIVED
NO. ENDING DATE AMOUNT AMOUNT
(RM) (RM) (RM) AMOUNT DATE
(RM) (RM)
1 25 Dec 2019 2nd Jan 2020 109,679.52 109,679.52 98,711.57 98,711.57 2/4/2020 98,700.00 7/4/2020
2 25 Jan 2020 2nd Feb 2020 167,330.48 277,010.00 122,800.00 221,511.57 2/4/2020 122,800.00 3/4/2020
3 25 Feb 2020 No submission
4 25 Mar 2020 No submission
5 25 April 2020 No submission
6 25 May 2020 No submission
7 25 June 2020 No submission
8 25 July 2020 No submission
9 25 Aug 2020 No submission
10 25 Sept. 2020 No submission
11 25 Oct. 2020 No submission
12 25 Nov 2020 No Submission
12 25 Nov 2020 No Submission
13 25 Dec 2020 No Submission
14 25 Jan 2021 No Submission
15 25 Feb 2021 No Submission
16 25 Mac 2021 2nd Mac 2021 1,101,573.20 1,378,583.20 704,665.91 968,783.44 3/5/2021 704,600.00 3/5/2021
17 25 April 2021 No Submission
18 25 May 2021 18th Jun 2021 696,292.12 1,779,547.60
18 25 June 2021
1. Crossing Duct
2. Ducting at grade / verge
3. Additional quantity to supply and install handhole
4. Traffic Management Plan (TMP)
SECTION 6:
Issue Response
No Reference No. Description Location Date Date Remarks
(By TT) (By HSSI)
To be corrected as
Used 90o bend instead of Crossing at per TCSS
1 SUKE/TCSS/TQ/001 18/10/2019 6/11/2019
elbow 90o Parapet construction
drawing.
TCSS SS need to
No ducting crossing for
Crossing at follow the mainline
2 SUKE/TCSS/TQ/002 Earthing for TCSS roadside 22/10/2019 6/11/2019
Parapet progress on deck-
cabinet
slab.
Not indicated item sub-duct in Sub-duct not
3 SUKE/TCSS/TQ/003 PTS & BOQ. Only indicated on Mainline 29/10/2019 14/11/2019 subject to variation
construction drawing of contract.
Noise barrier
construction
Request construction drawing
4 SUKE/TCSS/TQ/004 Mainline 10/12/2019 6/1/2020 drawing has been
for Noise Barrier Section A & B
send by email on
24/12/2019
Turbine Technique
to provide
No opening for TCSS services
mitigation plan in
at median parapet wall
5 SUKE/TCSS/TQ/005 At parapet 10/12/2019 6/1/2020 rectifying this issue.
(T/SUKE/9455/E/TCSS/SB/L/1
Upon conforming
.16)
has been rectified,
SC to witness.
For TCSS need to use pipe cross No objection.
5/5/2020
Subject refer to
6 SUKE/TCSS/TQ/006 for fiber & power cable from SB Mainline 11/3/2020 (by email)
PTS303 for
con. at Toll Plaza Building, TP23 undertaking
Construction
drawing for Feeder
5/5/2020
Request Construction Drawing of Pillar Street
7 SUKE/TCSS/TQ/007 Mainline 11/3/2020 (by email)
Feeder Pillar Street Light Lighting had been
sent by email
dated 30/4/2020
Issue ACAD of the
Request for usage Telekom Toll Plaza TM routing to the
8 SUKE/TCSS/TQ/008 19/6/2020 19/8/2020
routing at TP3 3 PABX room at TP3
Ampang
The drawing has
Request Construction Drawing
9 SUKE/TCSS/TQ/009 of TP1, TP2, TP3
Toll Plaza 24/6/2020 23/10/2020 been forwarded via
email.
Generally, no
To advice on Method of objection on the
10 SUKE/TCSS/TQ/010 Installation of Ducting TCSS at A CA1 19/6/2020 21/8/2020 proposal without any
-Grade Area effect to time, cost &
quality
Allocated manhole at
the end of the TCS
Request for using TCS Ducting
Toll Plaza lane ducting for
11 SUKE/TCSS/TQ/011 for TCSS Fiber from UK Bound to 19/6/2020 21/8/2020
2 TCSS fiber ducting
PABX Room at TP2
up to T2 server room
only.
Turbine to provide
details the cable pit
Propose alternative design cross
12 SUKE/TCSS/TQ/012 CA1 18/9/2020 8/10/2020 dimensions & qty
at CA1
estimates. This cable
pit not in TCSS BQ
MONTHLY PROGRESS REPORT TCSS NO. 021
SUPPLY, DELIVERY, INSTALLATION, TESTING, COMMISSIONING AND MAINTENANCE OF TRAFFIC CONTROL AND SURVEILLANCE
SYSTEM (TCSS) FOR PROJECT SUNGAI BESI – ULU KELANG ELEVATED EXPRESSWAY (SUKE)
Issue Response
No Reference No. Description Location Date Date Remarks
(By TT) (By HSSI)
Issue Response
No Reference No. Description Location Date Date Remarks
(By TT) (By HSSI)
TO REQUEST COORDINATION
27 SUKE/TCSS/TQ/0027 Mainline 26/3/2021
DRAWING (TCSS/TCS/M&E/SL)
TO ENQUIRE ADDITIONAL
28 SUKE/TCSS/TQ/0028 Mainnline 26/3/2021 18/5/2021
INFORMATION AT RSA AREA
TO REQUEST SUGGESTION
METHOD TO RAISE UP
29 SUKE/TCSS/TQ/029 CB1 4/5/2021 16/4/2021
MANHOLE & FINAL ROAD
LEVEL AT CB1
TO REQUEST SUGGESTION
CH11110
30 SUKE/TCSS/TQ/0030 NEW LOCATION JRC7 AT 4/5/2021 19/4/2021
SB
CH.11110 SB
TO SUGGEST NEW ROUTE AT
CH11170
31 SUKE/TCSS/TQ/0031 CH.11170 SB TO AVOID RS 4/5/2021 19/4/2021
SB
WALL (450mm X 450mm)
REQUEST FOR UPDATED AND
CURRENT INFORMATION
32 SUKE/TCSS/TQ/0032 CB1 23/4/2021 7/5/2021
REGARDING ROAD STRETCH
AT CB1
REQUEST FOR NYLON ROPE
33 SUKE/TCSS/TQ/0033 AT SECOND DUCTING AT PIER PIER 50 23/4/2022 30/4/2021
50 TO PIER 57
REQUEST FOR NYLON ROPE
34 SUKE/TCSS/TQ/0034 AT SECOND DUCTING AT PIER PIER 41 23/4/2023 30/4/2021
41 TO PIER 43
REQUEST FOR
35 SUKE/TCSS/TQ/0035 CONFIRMATION TO USE GI CB1 23/4/2024 30/4/2021
PIPE 80mm AT SECTION CB1
To compensate the clearance of
35 SUKE/TCSS/TQ/0036 VMS corbel for VMS08 & VMS09 CB3 25/6/2021 Under Review
at CB3.
Issue
Date Response
No Reference No. Description Location Remarks
(By Date (By TT)
HSSI)
Non-compliance
of Road Duct
1 SUKE/NCR/TCSS/001 CB1 (UK) 3/6/2021
Crossing
Installation
Approved /
Commented / Under Review / Superseded /
Item Submitted Approved (with Remarks
Resubmitted Outstanding Withdrawn
Comments)
WMS 20 13 3 4 0 -
Installation of Equipment
3 SUKE/TCSS/MWS/003 (REV1) 01 Mainline 5/10/2020 5/10/2020 16/10/2020 B
Earthing System (TCSS)
Installation of Vehicle
5 SUKE/TCSS/WMS/005 (REV2) 02 Mainline 5/10/2020 5/10/2020 7/11/2020 A
Detection System
Installation of Variable
6 SUKE/TCSS/WMS/006 00 Mainline 28/5/2020 28/5/2020 23/6/2020 B
Message Sign
Installation of Emergency
7 SUKE/TCSS/WMS/0007 (REV2) 02 Mainline 5/10/2020 5/10/2020 10/10/10 B
Telephone
Installation of Crossing
8 SUKE/TCSS/WMS/0008A 00 Mainline 21/7/2020 21/7/2020 17/8/2020 A
Duct
Installation of Crossing
9 SUKE/TCSS/WMS/0008B (REV1) 01 Mainline 19/8/2020 19/8/2020 25/8/2020 A
Duct
Installation of Crossing
10 SUKE/TCSS/WMS/0008C (REV2) 02 Mainline 5/10/2020 5/10/2020 10/10/2020 A
Duct
Installation of Crossing
11 SUKE/TCSS/WMS/0008D (REV3) 03 Mainline 2/11/2020 2/11/2020 5/11/2020 A
Duct
Installation of Equipment
12 SUKE/TCSS/WMS/0009 00 Mainline 12/8/2020 12/8/2020 24/8/2020 C
Lightning Protection (TCSS)
Installation of Dynamic
13 SUKE/TCSS/WMS/0010 Road Sign & Travel Time 00 Mainline 12/8/2020 12/8/2020 29/8/2020 C
Signboard
Submitted Approved /
Commented / Under Review /
Item Approved With Remarks
Resubmitted Outstanding
Comments
34 1 6
Material Submittal 41 -
2
Approval
0 - withdrawn
SECTION 7:
1. PROJECT DETAILS
This report presents the Monthly Environmental, Safety and Health for the project Sungai Besi - Ulu Kelang
Elevated Expressway.(SUKE)
2. ACTIVITIES
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE CA4
Date: 28th May 2021
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE CB1
Date: 11th June 2021
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE CB1
Date: 12th June 2021
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE TP1
Date: 15th June 2021
Safety Induction
Location: SUKE TP1
Date: 17th June 2021
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE CB3
Date: 18th June 2021
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE CB1
Date: 23rd June 2021
Safety and Health Toolbox Briefing and Temperature Screening before start work
Location: SUKE CB1
Date: 24th June 2021
3. MANPOWER/ MAN-HOURS
4. SAFETY TRAINING
Site/
1 June 2021 1 N/A N/A
Site Office
TOTAL 1 0 0
a. FATALITY 0 0 0 0 0 0
b. PERMANENT DISABILITY 0 0 0 0 0 0
d. BODILY INJURY 0 0 0 0 0 0
e. DAMAGE OF PROPERTY 0 0 0 0 0 0
f. OCCUPATIONAL DISEASE 0 0 0 0 0 0
g. NEAR MISS 0 0 0 0 0 0
TOTAL 0 0 0 0 0 0
Frequency Rate 0 0%
Severity Rate 0 0%
Fatality Rate 0 0
Fatality Rate = No.of Fatality X 1,000 Incident Rate = No.of Accident X 1,000
Annual Average Employment Annual Average Employment
- Refer Project Safety & Health Plan (TT/TSSB/ SUKE /19 504 /TCSS/SHP/001Rev0) -
7.2 Environmental
- NA -
SECTION 8:
SCHEDULE PERFORMANCE
SECTION 9:
Electrical - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Wiremen - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Welder - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Installer - - - - - - - - - - - - - - - - - - - - - - - 2 - - - - - - -
Testers - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
SHO - 1 1 1 - - - - - - - - - - - - 1 1 - - 1 1 - 1 - - - 1 1 1 1
Worker - 4 4 4 4 - - - - - - - - - - - 4 4 - 4 7 7 4 6 - - - 4 4 4 4
TOTAL - 7 7 7 6 - - - - - - - - - - - 9 8 - 5 10 11 6 15 - - - 7 7 6 8
JUNE 2021
DATE/TIME MAY 2021
26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1:00 AM
2:00 AM
3:00 AM
4:00 AM
5:00 AM
6:00 AM
7:00 AM
8:00 AM
9:00 AM
10:00 AM
11:00 AM
12:00 PM
1:00 PM
2:00 PM
3:00 PM
4:00 PM
5:00 PM
6:00 PM
7:00 PM
8:00 PM
9:00 PM
10:00 PM
11:00 PM
12:00 AM
Rain Hour 4 4
SECTION 10:
PROGRESS PHOTOGRAPH
PROGRESS PHOTOGRAPH
SECTION A
Outcome / Finding : Check Positioning of Installation Bolt at Corbel (VDS 20/ET 10)
– WPC Install Bolt using Wrong Base Plate(400mm to 300mm)
Date : 11.06.2021
Outcome / Finding : Check Positioning of Installation Bolt at Corbel (VDS 20/ET 10)
– WPC Install Bolt using Wrong Base Plate(400mm to 300mm)
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 12.06.2021
Date : 17.06.2021
Outcome / Finding : Trenching & Installation 2 Ways PVC Pipe for TCSS
Ducting at 10050 SB
Date : 22.06.2021
Outcome / Finding : Trenching & Installation 2 Ways PVC Pipe for TCSS
Ducting at 10050 SB
Date : 22.06.2021
Outcome / Finding : Trenching & Installation 2 Ways PVC Pipe for TCSS
Ducting at 10050 SB
Date : 22.06.2021
Outcome / Finding : Trenching & Installation 2 Ways PVC Pipe for TCSS
Ducting at 10050 SB
Date : 22.06.2021
Outcome / Finding : Trenching & Installation 2 Ways PVC Pipe for TCSS
Ducting at 10050 SB
Date : 22.06.2021
Outcome / Finding : Trenching & Installation 2 Ways PVC Pipe for TCSS
Ducting at 10050 SB
Date : 22.06.2021
Outcome / Finding : Install Pre-Casting Footing for TCSS Pole (CCTV 21)
Date : 22.06.2021
Outcome / Finding : Install Pre-Casting Footing for TCSS Pole (CCTV 21)
Date : 22.06.2021
Outcome / Finding : Install Pre-Casting Footing for TCSS Pole (CCTV 21)
Date : 22.06.2021
Outcome / Finding : Making Good Work after Work Done (Touch up Existing
Drain)
Date : 22.06.2021
PROGRESS PHOTOGRAPH
SECTION B
Outcome / Finding : Rodding & Put Nylon Rope in ducting TCSS from each
Manhole
Date : 27.05.2021
Outcome / Finding : Rodding & Put Nylon Rope in ducting TCSS from each
Manhole
Date : 27.05.2021
Outcome / Finding : Rodding & Put Nylon Rope in ducting TCSS from each
Manhole
Date : 27.05.2021
Outcome / Finding : Rodding & Put Nylon Rope in ducting TCSS from each
Manhole
Date : 27.05.2021
Outcome / Finding : Rodding & Put Nylon Rope in ducting TCSS from each
Manhole
Date : 27.05.2021
Outcome / Finding : Rodding & Put Nylon Rope in ducting TCSS from each
Manhole
Date : 27.05.2021
Date : 28.05.2021
Date : 28.05.2021
Outcome / Finding : Install GI pipe for crossing and Install Manhole (JRC7)
Date : 30.05.2021
Outcome / Finding : Install GI pipe for crossing and Install Manhole (JRC7)
Date : 30.05.2021
Outcome / Finding : Install GI pipe for crossing and Install Manhole (JRC7)
Date : 30.05.2021
Outcome / Finding : Install GI pipe for crossing and Install Manhole (JRC7)
Date : 30.05.2021
Outcome / Finding : Install GI pipe for crossing and Install Manhole (JRC7)
Date : 30.05.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 11.06.2021
Date : 12.06.2021
Date : 12.06.2021
Date : 12.06.2021
Date : 14.06.2021
Date : 14.06.2021
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Location : SECTION CB1 (CH11740 & CH11611 SB ,CH11677 & CH12794 UK)
Date : 17.06.2021
Date : 17.06.2021
Date : 17.06.2021
Date : 17.06.2021
Date : 17.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 18.06.2021
Date : 22.06.2021
Date : 22.06.2021
Date : 23.06.2021
Date : 23.06.2021
Date : 23.06.2021
Date : 23.06.2021
Date : 23.06.2021
Date : 23.06.2021
SECTION 11:
RISK MANAGEMENT
- ATTACH HIRARC -
HIRARC Forms
1. Termination of electrical Exposure to live electrical Electrocution Nil 2 3 6 1. Ensure that work is performed by competent (SV) N/a
cable @ fiber optic wire. personnel.
connection. 2. Ensure that SOP is followed all the times.
3. Wear non-conductive and heavy duty gloves.
Exposure to sharp cutter Hands injury Nil 3 1 3 1. Use designated wire cutter. Worker N/a
blades. 2. Wear suitable heavy duty gloves.
2. Splicing of connector. Exposure to sharp cutter Hands injury Nil 3 1 3 1. Use designated wire cutter. Worker N/a
blades. 2. Wear suitable heavy duty gloves.
Wrongly joint the connector Property damage/ tools not Nil 2 1 2 Ensure that work is performed by competent (SV) N/a
functioning properly personnel.
HAZARD IDENTIFICATION, RISK ASSESSMENT, AND
RISK CONTROL SUKE
1. Lifting of VMS and gantry Fast moving vehicle from Hit by vehicle which can 1. Isolation. 3 5 15 1. Ensure that workers follow SOP at all time, (SV) N/a
structure by crane. other contractor. cause serious bodily injury Traffic TMP must be obtained prior to entering site.
and property damage. Management 2. Place blinker at a safe distance before TMP
2. Workers wear excavation location.
high visibility
vest.
Unstable/uneven crane Collapse of crane onto Nil 2 5 10 1. Ensure crane possess valid Certificate of Crane N/a
grounds. traffic and properties. Fitness (Perakuan Mesin Angkut). Provider
2. Ensure crane driver is competent.
3. Conduct site inspection prior to lifting All
acitivity. workers
4. Use suitable crane pad plate for
unstable/uneven grounds.
Loosely fit/damaged Fall of suspended load onto Nil 2 5 10 Inspect and verify any cables and Crane N/a
attachment/cable of road users and nearby attachment is safe before lifting. Operator
suspended load. workers.
Lifting conducted under Fall of suspended load onto Nil 2 5 10 Stop work immediately. (SV) N/a
strong windy weather. road users and nearby
workers.
Working near suspended Workers hit by swinging Nil 2 2 4 Barricade lifting area. (SV) N/a
load. load and thus causing
bodily injury.
2. Climbing and descending of Working at height without Falling and may cause Nil 3 4 12 Worker must wear full body harness and Worker N/a
gantry ladder. fall arrest system. bodily injury. hook lanyard to a steady anchorage at all
time.
HAZARD IDENTIFICATION, RISK ASSESSMENT, AND
RISK CONTROL SUKE
Misorientation/mishandling 1. Property damage. Nil 1. Ensure that operation of excavator/backhoe (SV) N/a
of backhoe bucket while 2. Hit nearby workers and is performed by competent personnel.
3 3 9
excavating. thus cause bodily injury. 2. Other workers must keep a safe distance
from backhoe/excavator.
Falling of heavy load. 1. Serious bodily Nil Other workers must keep a safe distance All N/a
injury/fatality. 3 3 9 from backhoe/excavator. workers
2. Property damage.
Uncovered trench/hole. Falling into and thus Nil Always place barricade to trench/hole (SV) N/a
4 3 12
causing bodily injury.
2. Installation of precast concrete Loosely fit/broken cable Falling load to nearby Nil Ensure that workers keep safe distance from (SV) N/a
3 4 12
footing JRC 7 that is used to lift JRC 7. workers and properties. the suspended load.
HAZARD IDENTIFICATION, RISK ASSESSMENT, AND
RISK CONTROL SUKE
Uneven ground due to piled Tripping and thus fall. Nil Recover soil/ground level accordingly after (SV) N/a
excavated soil at the 4 1 4 excavating.
working area.
3. Compacting recovered trenches Manual lifting of heavy Fatigue and Nil Implement ‘buddy’ working system. (SV) N/a
4 1 4
by using handheld compactor tool. musculoskeletal pain.
tool.
Exposure to continuous Fatigue, musculoskeletal Nil 1. Implement job rotation system and (SV) N/a
tool vibration. pain and nerve damage. 4 3 12 adequate resting time.
2. Supply worker with adequate drinking water.
HAZARD IDENTIFICATION, RISK ASSESSMENT, AND
RISK CONTROL SUKE
Unstable crane grounds. Collapse/overturn of Nil 2 5 10 1. Implement safe operating procedures Crane N/a
crane which may at all time. Operator
cause multiple 2. Suitable crane pad must be in place
fatalities of workers prior to lifting.
and road users and
significant property
damage.
Loosely fit/damaged Fall of suspended load Nil 3 5 15 Inspect and verify any cables and Crane N/a
attachment/cable of onto road users and attachment is safe before lifting. Operator
suspended load. nearby workers.
Lifting conducted under Fall of suspended load Nil 2 5 10 Stop work immediately. Crane N/a
strong windy weather. onto road users and Operator
nearby workers.
Working near suspended Workers hit by Nil 2 2 4 Barricade lifting area. Crane N/a
load. swinging load and Operator
thus causing bodily
injury.
Communication failure Fall of suspended load Nil 2 5 10 1. Ensure communication device works Crane N/a
between signalman and onto road users and properly prior to lifting. Operator
crane operator during nearby workers. 2. Ensure that only trained signalman
securing pole bolts and perform the signaling operation (SV)
nuts.
HAZARD IDENTIFICATION, RISK ASSESSMENT, AND
RISK CONTROL SUKE
No. Sub Activities Operations Environmental Aspect Env. Environmental Risks Impact Significance Control Measures / Remarks
(Please check) Impact
Quantitative Score
High Priority
Low Priority
Probability (P)
Severity (S)
(46-100)
(6-25)
(1-5)
Medium
N A E
Px
Significant
Not
Sx
Priority
CI
Excavation and / Carbon monoxide emission from 1,6 2 2 1 4 / Minimize the use of
ducting works for excavator/backhoe excavator/backhoe
fibre optic cable
/ Soil erosion and sedimentation 3 3 3 1 9 / 1- Reinstating & compacting the
1.
background surface area
2- Replant grass for slope
protection
/ Domestic waste 3 4 1 2 8 / 1- Maintain a good housekeeping
2- Provide plastic garbage for
domestic waste
High Priority
Low Priority
Severity (S)
Probability (P)
(46-100)
(6-25)
Medium
N A E
Px
Significant
Not
Sx
Priority
CI
High Priority
Low Priority
Probability (P)
Severity (S)
(46-100)
(6-25)
Medium
N A E
Px
Significant
Not
Sx
Priority
CI
Not Significant
Medium Priority
High Priority
Probability (P)
Low Priority
(46-100)
(26-45)
Severity (S)
(6-25)
(1-5)
N A E Px
Sx
CI