You are on page 1of 2

product feature

Metal Deck: What Design


Engineers Should Know
Two experts share their metal deck know-how with these 15 tips.

S
SO YOU THINK YOU KNOW A THING rating requirements. If spray-applied in. to 3 in. composite deck, typical spans
OR TWO ABOUT METAL DECK, fire protection is required, the paint are 10 ft to 15 ft. “When you use a dove-
RIGHT? Not so fast—when working must be a classified product, listed in tail profile, you can span 15 ft., but you
with metal deck, there’s an entire laun- the UL assembly and compatible with have to shore it,” notes Abbata. The situ-
dry list of components to consider: things the spray-applied fire protection ma- ation then becomes one of give-and-take.
such as coatings, fire ratings, shoring, terial selected on the project. Clearly “Because it’s a shored system, you save on
construction loads and limitations, de- show on the structural contract draw- material, and you can span farther, but the
sign economics, and corrosion potential. ings where spray-applied fire protec- actual cost of the material is more,” he
When dealing with deck, forethought is tion will be required. says. “For example, with a standard profile,
essential and may save your project time you can’t span 20 ft. There’s no strength

5
and money. The coatings, not the deck itself, to it. But you can with a dovetail profile.”
Since there’s much more to metal deck determine the compatibility of the

9
than 1½ -in.-wide rib deck, in an effort deck with the desired function. Giving due consideration to all el-
to share their accumulated knowledge, ements of construction, deck with

6
MSC consulted two experts in the field, Time of exposure to construction joists at 5 ft. on center is not always
John Mattingly, director of engineering traffic and anticipated construc- the most economical design choice.
at Nicholas J. Bouras, Inc., and Allan Ab- tion loads impact which floor deck Again, according to Abbata, it’s a mat-
bata, manager of research and develop- product and thickness is selected. ter of six of one, half a dozen of the other
ment at the Metal Dek Group, a unit of Deck must be fastened before ap- in terms of savings. Given a set bay ge-
Consolidated Systems, Inc. Below, they plying any construction loads, and ometry, you can use more intermediate
list what they believe every design en- the SDI tables are based on standard supports with a lighter deck, or fewer
gineer should know about working with construction loads. To avoid damage, intermediate supports with a heavier
metal deck. actual construction loads must either deck. If you choose the latter, you’ll have
be consistent with these standards or a little less steel because you have fewer

1
Metal deck manufacturers are eager project-specific load tables. joists to install, but you’re replacing all
to be a resource for designers. Take those joists with heavier decking.

7
advantage of their resources. Studs are not required over beams

10
to provide composite slab action; Composite metal decking can

2
Metal deck can be tailored for spe- however, they can increase compos- reach spans of 30 ft. in shored
cific structural, acoustical, and aes- ite slab capacity. Studs are required construction.
thetic needs. for composite beam action. Both stud

11
location in the corrugation and corru- There has been a trend toward

3
In composite floor decking, fire rat- gation geometry impact the nominal screws at side laps in roof decking
ing requirements typically control stud shear capacity (refer to the AISC vs. welding. Anticipate that the
both concrete type and slab thick- 13th Edition manual, Section I3.2c). deck erector will request this change.
ness selection. The final decision can be affected by

8
Temporary shoring of deck does cosmetic concerns within the building,

4
Before selecting painted cold-rolled not always indicate that the design fire rating restrictions, and diaphragm
roof decking (not galvanized), in- is uneconomical. requirements. Welds still are an accept-
vestigate all project areas for fire Based on a standard profile of about 2 able method of fastening side laps.

MODERN STEEL CONSTRUCTION SEPTEMBER 2006


12
Corrosion potential in composite
deck, even in interior, residen-
tial uses, is particularly relevant
when less experienced contractors will
be installing the deck and slab or when
proactive maintenance by owners is less
than certain.

13
In general, on smaller projects
it’s false economy to select a deck
at the extremes of its span limits.
“The biggest costs on smaller projects
are set-up and shipping, which are con-
stant costs,” says Mattingly. On smaller
projects, job site congestion and inexpe-
rience are more likely to occur, increas-
ing the probability of overloading the
deck during construction.

14
Clearly defined designed criteria,
such as live and dead load, worst
case span condition, and clearly
defined diaphragm requirements can
make it easy for deck manufacturers to
provide design solutions for structural
systems.

15
The roof deck manufacturer can
provide the allowable diaphragm
shear resistance. The art of dia-
phragm design lies in perimeter details
that are designed to collect shear and
to transmit shear into and out of the
diaphragm. Avoid ripped sheets at shear
walls, and avoid finish strips unless the
finish strip is properly designed to resist
and transmit the required shear.

—compiled by Kara Luger

SEPTEMBER 2006 MODERN STEEL CONSTRUCTION

You might also like