2bedroom flat

it depend on labour cost, omo onile factor and ready availability of money.
e.g
1000 blocks of 6 inches @ 130 = #130, 000. but d truth is d blocks made these days are
knock-offs.
alternatively,
if you mould yourself.
2 trips of sand @ 18000each = 36000 ( a trip moulds more dan 15 bags of cements ).
20 bags of cement @ 1500 = 30000.
1 bag = 50 blocks.
labour is 600 per bag = 16000
water 2000
total = 84,000. & sand for about over 10bags of cement still left.

imagine 130000 to 84 000 for 1000 blocks. 

i hear some1 talk about soak away ?.


now people use "shalanga" method of 3feet wide 20-25feet deep....cost 20k , plus the
sand u get from it will serve as filling. 2 is enuf for 3 bedroom. na to just slab am
remain, na everlasting.
if not, 8 by 10 by 8 feet soak away is about 70k to dig, ul need blocks n cement plus
slabing too....over 100k, & future xpenses to dey pack ( evacuate ) poo.

apply d above methods n others


#2million will complete 3 bedroom flat