BOQ Summary Page 1 of 1

BOQ SUMMARY

Project Name: 2ND FLOOR BEAMS

Element :  Beam

No. Material Unit Quantity Rate Cost


1 Concrete C20 (cum) 16.15 6500.00 104956
Sub Total 16.15 1,04,955

2 Rebar #9.5 (Fy230) (kg) 629.95 53.00 33387


3 Rebar #15.9 (Fy230) (kg) 1338.67 53.00 70950
4 Rebar #16 (Fy230) (kg) 18.20 53.00 965
5 Rebar #19 (Fy230) (kg) 1.85 53.00 98
6 Rebar #19.1 (Fy230) (kg) 176.33 53.00 9346
7 Rebar #25 (Fy230) (kg) 74.46 53.00 3947
8 Rebar #25.4 (Fy230) (kg) 718.32 53.00 38071
Sub Total 2957.79 1,56,762

9 Shuttering (sq.M) 134.49 600.00 80696


Sub Total 80,695

Grand Total 3,42,413

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 183.18 kg/cum
2 Concrete % C20 = 100.00 % 
3 Shuttering  = 8.33 sqm/cum