Professional Documents
Culture Documents
Civil Aviation Authority of The Philippines: Memorandum
Civil Aviation Authority of The Philippines: Memorandum
MEMORANDUM
FOR:
DATE:
BACKGROUND
2. After evaluation, Eagle Matrix Security Agency, Inc. (EMSAI) was awarded
the contract under the Three-Year Service Agreement/Security Services Contract for having
submitted the Single Calculated Responsive Bid (SCRB) for the Services.
1|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
10. On 19 August 2019, CAAP Area I approved the request for reconsideration
and waiver of penalty. A total of ten million four hundred sixty nine thousand five hundred
pesos (PHP10,469,500.00) was waived from the penalties of EMSAI from Area I. The
Request for Reconsideration and Waiver of Penalty to Area II was however, not passed upon.
2|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
11. Despite their standing obligation to pay the incurred penalties, Atty. Claustro
sent another letter to Area Center I on 11 November 2019 requesting payment from CAAP
for the unpaid Security Services from 01 March to 31 October 2019 in the amount of thirteen
million nine hundred fifty two thousand seven hundred seventy two pesos and 96/100
(PHP13,952,772.96).
13. On 04 January 2021, CSIS Area II Supervisor Derrick Mones also forwarded a
Summary Report of EMSAI Penalties from Area II for the period February 2019 up to
September 2020. The total amount of EMSAI penalties from Area II is Thirty Two Million
Three Hundred Twelve Thousand Five Hundred Pesos (PHP32,312,500.00).
14. Based from the summary reports provided by Mr. Manalo and Mr. Mones, the
combined penalties of EMSAI from Areas I and II total to Forty One Million Six Hundred
Ninety Six Thousand Five Hundred Pesos (PhP41,696,500.00).
15. Whether or not the Liquidated Damages are chargeable against the retention
money or amount due to EMSAI pursuant to Section 3, Annex D of the 2016 Revised IRR of
R.A. No. 9184.
DISCUSSION
3|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
16. The Manual of Procedures for the Procurement of Goods, Volume 2, discusses
the rule on the applicable period for the delivery of goods or performance of services. The
supplier/manufacturer/distributor must deliver the goods or perform the services procured
within the period prescribed by the Procuring Entity, as specified in the Contract. If
delays are likely to be incurred, the supplier/manufacturer/distributor must notify the
Procuring Entity in writing. It must state therein the cause/s and duration of the expected
delay. The Procuring Entity may grant time extensions, at its discretion, if based on
meritorious grounds, with or without liquidated damages. In all cases, the request for
extension should be submitted before the lapse of the original delivery date. The maximum
allowable extension shall not be longer than the initial delivery period as stated in the original
contract.1 [Emphasis supplied.]
17. Liquidated damages are damages agreed upon by the parties to a contract, to
be paid in case of breach thereof.2
18. The 2016 Revised Implementing Rules and Regulations (IRR) of R.A. No.
9184, otherwise known as The Government Procurement Reform Act has just been updated
as of 31 March 2021. The provisions of the IRR are in line with the commitment of the
Government of the Philippines to promote good governance and its effort to adhere to the
principles of transparency, accountability, equity, efficiency, and economy in its procurement
process.3
4|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
20. A similar provision is found in Section 3.1 of Annex “D” of said IRR:
3.1 When the supplier fails to satisfactorily deliver goods under the contract
within the specified delivery schedule, inclusive of duly granted time
extensions, if any, the supplier shall be liable for damages for the delay
and shall pay the procuring entity liquidated damages, not by way of
penalty, an amount equal to one-tenth (1/10) of one percent (1%) of the
cost of the delayed goods scheduled for delivery for every day of delay
until such goods are finally delivered and accepted by the procuring
entity concerned. The procuring entity need not prove that it has incurred
actual damages to be entitled to liquidated damages. Such amount shall
be deducted from any money due or which may become due to the
supplier, or collected from any securities or warranties posted by the
supplier, whichever is convenient to the procuring entity concerned. In
case the total sum of liquidated damages reaches ten percent (10%) of
the total contract price, the procuring entity concerned may rescind the
contract and impose appropriate sanctions over and above the
liquidated damages to be paid. [Emphasis supplied.]
21. Based from the aforementioned provisions, the procuring entity or CAAP has
the right to claim Liquidated Damages from EMSAI as the latter has defaulted in the
fulfillment of its obligations under the contract as early as February 2019.
22. A review of the documents provided by the CSIS of Areas I and II, since the
effectivity of the contract on February 2019, EMSAI has been failing to provide the
necessary firearm to posted guard, had issued ammunition short of the requirement, or had
not issued extra magazine or holler for extra ammunition, failed to provide the required
number of radios, failed to provide the required service vehicle, and has posted Guards that
are not qualified, all in violation of the Security Services Contract.
5|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
24. Nevertheless, R.A. No. 9184 and its IRR provide for the remedy in the event
that supplier EMSAI could not pay the same. As mentioned earlier, CAAP may deduct the
liquidated damages from any money due or which may become due to the EMSAI, or
collected from any securities or warranties posted by EMSAI, whichever is convenient to
CAAP as the procuring entity.
25. The liquidated damages of EMSAI shall be the amount equal to one-tenth
(1/10) of one percent (1%) of the cost of the delayed goods or services scheduled for delivery
or performance for every day of delay. The liquidated damages will be imposed until such
goods or services are finally delivered or performed and accepted by CAAP.
26. A rough estimate of EMSAI’s liquidated damages based from its violations
from Area I may be illustrated as follows:
LIQUIDATED
LIQUIDATED NO. OF DAYS DAMAGES DUE
MONTH and PENALTY
DAMAGES UNTIL for the period
YEAR INCURRED*
(1/10 of 1%) 01 March 2020 01 February 2019
to 01 March 2020
Feb 2019 126,000.00 126.00 394 49,644.00
Mar 2019 139,500.00 139.50 366 51,057.00
Apr 2019 135,000.00 135.00 335 45,225.00
May 2019 139,500.00 139.50 305 42,547.50
Jun 2019 868,000.00 868.00 274 237,832.00
Jul 2019 2,518,000.00 2,518.00 244 614,392.00
Aug 2019 1,691,000.00 1,691.00 213 360,183.00
Sep 2019 1,623,000.00 1,623.00 182 295,386.00
Oct 2019 1,534,500.00 1,534.50 152 233,244.00
Nov 2019 1,485,000.00 1,485.00 121 179,685.00
Dec 2019 1,124,500.00 1,124.50 91 102,329.50
Jan 2020 325,500.00 325.50 60 19,530.00
Feb 2020 304,500.00 304.50 29 8,830.50
TOTAL 2,239,885.50
* Numerical figures provided by CSIS Danilo Manalo of Area I dated 04 August 2020.
6|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
27. In the preceding table, the computed liquidated damages of EMSAI for CAAP
Area I alone totals to two million two hundred thirty nine thousand eight hundred eighty five
pesos and 50/100 (PHP2,239,885.50) and counting.
28. Ten percent (10%) of the total contract price is One Million Nine Hundred
Sixty Eight Thousand Six Hundred Ninety Pesos & 97/100 (PhP1,968,690.97).
29. Given that the liquidated damages of EMSAI have already reached the ten
percent (10%) of the total contract price, CAAP may now opt to rescind the contract AND
impose appropriate sanctions over and above the liquidated damages.
30. Based from the foregoing, CAAP may now either retain any money due to
EMSAI or collect from any securities or warranties posted by EMSAI, whichever is more
convenient to CAAP.
RECOMMENDATION
7|Page
Republic of the Philippines
CIVIL AVIATION AUTHORITY OF THE PHILIPPINES
c. That CAAP, upon conference of SBAC and other concerned offices, may
decide to rescind the contract with EMSAI and impose other sanctions as
deemed fit in addition to the liquidated damages.
RONALD V. ESTABILLO
Civil Aviation Area Manager – Area I
Civil Aviation Authority of the Philippines
Airport Road, Brgy. 36 Araniw
Laoag City, Philippines 2900
Copy furnished:
8|Page