Professional Documents
Culture Documents
(Gulf)
30 November 2010
API Auditorium, Dubai
U.S.A.
Different philosophies of civil law e.g. the French Civil Code vs. the German Civil Code
30 November 2010 3
30 November 2010 4
Closed Open
Start with the parties’ agreement More emphasis on freedom of
(pacta sunt servanda) but more contract
mandatory requirements which can
override this
30 November 2010 5
30 November 2010 6
30 November 2010 7
30 November 2010 8
30 November 2010 9
30 November 2010 10
Start with the words the parties have used but you may also look at the wider
context – e.g. Article 1156 of the French Civil Code:
“One must in agreements seek what the common intention of the contracting
party was, rather than pay attention to the literal meaning of the terms”
Evidence of negotiations is admissible as evidence of the parties’ intentions
Mandatory provisions in the Civil law cannot be excluded (e.g. liability for acts of
intentional misconduct / “gross negligence”)
Tribunals have more discretionary powers to intervene to re-write the parties’
agreement
30 November 2010 11
30 November 2010 12
“The rule excludes evidence of what was said or done during the course of negotiating the
agreement for the purpose of drawing inferences about what the contract meant. It does
not exclude the use of such evidence for other purposes, for example, to establish that a
fact which may be relevant as background was known to the parties, or to support a claim
for rectification or estoppel. These are not exceptions to the rule. They operate outside it”
Looking at such background evidence can evidently also be used to influence the
objective interpretation, per Baroness Hale (paragraph 99):
“But I have to confess that I would not have found it quite so easy to reach this conclusion
had we not been made aware of the agreement which the parties had reached on this
aspect of their bargain during the negotiations which led up to the formal contract. On any
objective view, that made the matter crystal clear”
Final destination – parol evidence rule maintained, but can still look at the material
30 November 2010 13
30 November 2010 14
30 November 2010 15
However, before assessing how the civil law will determine the issue, a key
question to consider is whether the contract is “administrative” or
“commercial”
Can make a significant difference to how the contract is applied and / or
how the issue is determined
U.A.E. law – where one of the parties is a public body, the contract may be
construed to be an “administrative contract”
Consequence: the court may have less power to intervene in an
administrative contract and / or the public body may have additional rights
Will see this in some of the particular examples…
30 November 2010 16
30 November 2010 17
French courts have the power to reduce or increase the amount of the LDs
stated in the contract (referred to as “penalties” under French law) when they
appear to be manifestly excessive or derisively low
Article 1152: “Where an agreement provides that he who fails to perform it shall
pay a certain sum as damages, the other party may not be awarded a greater sum.
Nevertheless, the judge may even of his own motion, moderate or increase the
agreed penalty, where it is manifestly excessive or derisively low. Any stipulation to
the contrary shall be deemed unwritten”
This power used to be limited only to LDs in civil / commercial contracts, but
French law has now extended this to administrative contracts
30 November 2010 18
The French courts take into account various factors when considering
whether to reduce or increase penalties:
the existence and amount of actual damages suffered as a result of the delay –
e.g. are the LDs “manifestly excessive” as compared with the actual losses
being suffered;
the value of the contract;
whether changes in the project required a time extension; and
the degree to which the party has failed to perform (e.g. deliberate failure might
entail higher levels of damages – “good faith” duties making a difference).
This is a much wider discretion than under the English common law
(although, in practice, it is difficult to persuade the French courts to exercise
these powers)
30 November 2010 19
As a matter of practice, LDs in administrative contracts are normally pre-defined and not
subject to negotiation. By contrast, in a commercial or civil contract, the parties typically
reach their own agreement on the amount of liquidated damages
U.A.E courts are entitled to modify the amount of LDs to ensure that it is equal to the actual
loss suffered – Article 390(2) of the U.A.E. Civil Code:
“The judge may in all cases, upon the application of either of the parties, vary such agreement so as
to make the compensation equal to the loss, and any agreement to the contrary shall be void”
But administrative contracts are treated differently from commercial contracts in practice
(commercial contracts: LDs may be increased or decreased; administrative contracts: LDs
may only be reduced)
Also, under civil law systems generally, LDs limitations can be exceeded where a party has
acted with intentional misconduct and / or “gross negligence”
30 November 2010 20
English common law (as with U.S.A. and Commonwealth common law)
contains considerable case law on various issues of delay analysis
Civil law codes and doctrine typically do not contain such specific bodies of
law on these detailed areas of construction practice
Whilst the underlying principles may be different (e.g. the “prevention
principle” will not be recognized as such in civil law), the degree of logical
analysis of basic issues in the common law can be used to persuasive effect
in civil law contexts
For example:
a) “Time at large” (e.g. principles of contract certainty, substantial performance
and good faith in administering the contract); and
b) Concurrent delay (e.g. apportionment of damages to take account of different
causative effects, e.g. Article 290 of the U.A.E. Civil Code)
30 November 2010 21
i. Force Majeure
No defined meaning in common law; therefore extensive contract
provisions. Typically, an event beyond a party’s control which prevents any
particular obligations from being performed
In civil law, force majeure exists separately to the contract i.e. protection
even where there is no force majeure provision
ii. Frustration
An external event which renders performance of the contract substantially
impossible
A common law doctrine permitting termination of the contract, but no
liability for damages
30 November 2010 22
Similarly, Article 6.2.2. of the UNIDROIT Principles provides for relief from hardship:
“where the occurrence of events fundamentally alters the equilibrium of the contract either
because the cost of a party’s performance has increased or because the value of
performance a party receives has diminished”
30 November 2010 23
English law and most other common law jurisdictions have imposed reasonably
strict requirements for claimants to prove cause and effect in order to recover
damages (e.g. Wharf Properties v Eric Cumine (1991))
The case law on “global claims” has reflected this (although more recent
indications of a more permissive approach e.g. John Doyle v Laing (2004))
Civil law jurisdictions do not typically have any specific provision or doctrine on
“global claims” as such (e.g. in the U.A.E, the courts require the claimant to provide
supporting evidence for each and every element under the claim)
However, it may be possible to use other provisions which are included in some
civil codes to support global claims
For example: Article 1332 of the Peruvian Civil Code:
“If the damage could not be proven in its exact amount, such amount shall be
determined by the judge through equitable quantification”
30 November 2010 24
Common law
The procedure is “adversarial”
More emphasis is on the parties for the collection of evidence and presentation of their
case
Extensive document discovery
More reliance is put on fact evidence, oral arguments and examination
Established rules of evidence
Experts normally are appointed and paid by the parties
Judges are drawn from senior practising lawyers
30 November 2010 25
30 November 2010 26
30 November 2010 27