TIMELINE IMPROVEMENT HCL

*Estimasi kedatangan limbah HCl 400 ton/bulan


Februari 2020 Maret 2020
No Description PIC Week 1 Week 2 Week 3 Week 4 Week 1 Remarks
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6
1 Membuat planning improvement WWTP R&D
2 Trial limbah HCl R&D
3 Analisa hasil trial limbah HCl R&D
4 Membuat HPP pengolahan limbah HCl R&D
5 Membuat workplan improve mesin WWTP R&D
6 Membuat pengajuan pembelian material R&D
7 Follow up pembelian material Proc, R&D
8 Fabrikasi dan modifikasi mesin WWTP Prod, R&D
TIMELINE IMPROVEMENT HCL

Februari 2020 Maret 2020 April 2020 Mei 2020 Juni 2020
No Description PIC Remarks
Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

1 Membuat planning improvement WWTP R&D


2 Trial limbah HCl R&D
3 Analisa hasil trial limbah HCl R&D
4 Membuat HPP pengolahan limbah HCl R&D
5 Membuat workplan improve mesin WWTP R&D
6 Membuat pengajuan pembelian material R&D
7 Follow up pembelian material Proc, R&D
8 Fabrikasi dan modifikasi mesin WWTP Prod, R&D