Professional Documents
Culture Documents
( Excluding
Contractors profit
Cost excluding
from conveyance,
charges MA @
Reference to
Convey-ance
seigniorage
seigniorage
Lead in KM
Un-loading
Loading &
unloading
Source of
Materials
SSR page
Code No.
Load-ing
Loading &
Unloading
charges
charges
charges
charges
number
Sl. No.
Initial
C.P.)
20%
Unit
Charges
(1) (2) (3) (4) (5) (6) (7) (8) (9) (9) (10) (11) (12) (13)
Cement 43/53 grade
1 (Sep 2016 ENC Memo dt Local 11 1 MT 4800.00 0.00 0.00
29.9.16)
MS Plates
3 (Sep 2016 ENC Memo dt Local 1 MT 44000.00 0.00
29.9.16)
8 Aggregates 40mm nominal size Parlapalli 28 M - 055 1 Cum 39 845.00 439.61 0.00 0.00
9 Aggregates 20mm nominal size Parlapalli 27 M - 053 1 Cum 39 1365.00 439.61 0.00 0.00
11 Aggregates 10mm nominal size Parlapalli 27 M - 051 1 Cum 39 935.00 439.61 0.00 0.00
12 Aggregates 6mm nominal size Parlapalli 27 M - 050 1 Cum 39 735.00 447.92 0.00 0.00
13 Cost of crusher dust Parlapalli 26 M - 021 1 Cum 39 357.00 447.92 0.00 0.00
SULLURUPET MUNICIPALITY
LEAD CHART (COMMON SSR 2017-2018)
Mannar
14 Gravel / Quarry spall 24 M - 008 1 Cum 6 110.00 86.13 0.00 0.00
polur
Close Graded GSB - 9.5 to
15 Parlapalli 26 M-016 1 Cum 39 592.00 447.92 0.00 0.00
4.75 mm
Close Graded GSB - 4.75 to
16 Parlapalli 26 M-018 1 Cum 39 510.00 447.92 0.00 0.00
2.36mm
Close Graded GSB 2.36mm
17 Parlapalli 26 M-020 1 Cum 39 489.00 447.92 0.00 0.00
and below
18 Aggregate 63 to 45 mm Parlapalli 27 M-038 1 Cum 39 662.00 447.92 0.00 0.00
Aggregat 53 to 22.4 mm
19 Parlapalli 27 M-036 1 Cum 39 872.00 447.92 0.00 0.00
21 Aggregate 11.2 to .09 mm Parlapalli 27 M-041 1 Cum 39 704.00 447.92 0.00 0.00
SULLURUPET MUNICIPALITY
LEAD CHART (COMMON SSR 2017-2018)
LEAD CHARGES
Deduction
for
Gravel 6.00 Km Contractors
Profit
Metal 39.00 Km
up to 5.00 Km 1 86.7 86.70
5.00 to 30 Km@ 8.6/Km 25 13 325.00
above 30 Km@ 7.2/Km 9 10.8 97.20
Stone 39.00 Km
up to 5.00 Km 1 86.7 86.7
5.00 to 30 Km@ 8.6/Km 25 13 325
above 30 Km@ 7.2/Km 9 10.8 97.2
Bricks 5 Km
up to 5.00 Km 1 139.5 139.5
5.00 to 30 Km@ 12.7/Km 0 20.9 0
above Km@ 10.58/Km 0 17.4 0
1000
Total 139.5 18.99 120.51
Nos
Bricks 14 Km
up to 5.00 Km 1 139.5 139.5
5.00 to 30 Km@ 12.7/Km 9 20.9 188.1
above Km@ 10.58/Km 0 17.4 0
1000
Total 327.6
Nos
URUPET MUNICIPALITY
T (COMMON SSR 2017-2018)
Total
(14)
4800.00
38500.00
44000.00
244.90
169.90
169.90
5775.71
25575.71
1284.61
1804.61
1536.61
1374.61
1182.92
804.92
URUPET MUNICIPALITY
T (COMMON SSR 2017-2018)
196.13
1039.92
957.92
936.92
1109.92
1319.92
1366.92
1151.92
URUPET MUNICIPALITY
T (COMMON SSR 2017-2018)
LEAD CHARGES
RATE ANALYSIS FOR FINISHED ITEMS (DATA) including sieniorage charges-2017-18
S
Index-code Description Unit Quantity Rate Rs. Amount Rs.
No
1 2 3 4.00 5 6
Unit : 1cum
A. MATERIALS:
Cement kg. 480.00 4.80 2304.00
Sand (including 5% wastage) cum 1.05 244.90 257.15
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 370.00 74.00
Grand Total 2635.15
Unit : 1cum
A. MATERIALS:
Cement kg. 360.00 4.80 1728.00
Sand (including 5% wastage) cum 1.05 244.90 257.15
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 370.00 74.00
Grand Total 2059.15
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement kg. 180.00 4.80 864.00
Sand (including 5% wastage) cum 1.05 244.90 257.15
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 370.00 74.00
Grand Total 1195.15
Earthwork in excavation for Manual Meansas per drawing and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal
Chapter-3 upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material
3 as per Technical Specification 305 MORD / 304 MORTH
RBR-EECD-5
Ordinary soil
Manual Means
Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 370.00 1346.80
Add Municipal Allowances @ 20% 269.36
1616.16
b&c) Overheads & Contractors Profit
220.04
13.615 %@
Cost of 10 cum = a+b+c 1836.20
Rate per cum = (a+b+c)/10 183.62
Earth work excavation forMechanical Means and depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental, labour charges such as shoring ,sheeting,
4 BLD-CSTN-2-2 planking, strutting, etc. complete for finished item of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS 308).
Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 8.32 370.00 3078.40
Add for MA @ 20 % 615.68
b) Machinery
Hydraulic Excavator 1 cum bucket hour 6.00 2888.60 17331.60
capacity
21025.68
c&d) Overheads & Contractors Profit @ 13.615 2862.65
Cost for 240 cum = a+b+c+d 23888.33
Rate per cum = (a+b+c+d)/240 99.53
Conveyance of un-useful excavated earth to a distance of 1 KM for disposal including hire
charges of T & P, labour charges etc., complete for finished item of work.
4
Filling with sand in the bottom layers not exceeding 15 cm thick, consolidating each deposited layer
by watering and ramming including cost and conveyance of water to work site and all operational,
Chapter-11 incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO.
6
RBR-FNDN-2 309 & 310)
sand filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 370.00 114.70
Add 20% extra on Labour for Municipal 22.94
limits
b) Material
sand cum 1.00 169.90 169.90
Water Page 25, Item 178 Kl 0.10 103.00 10.30
317.84
Overheads & Contractors Profit 13.615% 43.27
Rate per cum = a+b+c+d 361.11
Filling with Stone crusher dust in the bottom layers not exceeding 15 cm thick, consolidating each
deposited layer by watering and ramming including cost and conveyance of water to work site and
Chapter-11 all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of
5
RBR-FNDN-2 work. (APSS NO. 309 & 310)
11 V.C.C. grade M 30 Design Mix, using 20 mm Graded Metal corresponding to Table 9 of IS 456
using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as machine mixing, laying concrete,
9 RBR-FNDN-4 curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work,
(MORTH 12.8 G)
11.3 The Hire charges for vibrators are included in overhead charges
Case 1 : Using Concrete Mixer
Unit = cum
(a) Material
Cement t 0.4 4800.00 1920.00
Coarse sand cum 0.45 169.90 76.46
20 mm aggregate cum 0.54 1804.61 974.49
10 mm aggregate cum 0.36 1374.61 494.86
(b) Labour
Mate day -
Mason (30% 1st Class + 70% 2nd Clas) day 0.1 433.50
43.35
Supply of 25 mm thick high performance premoulded expansion joint filler board (SILFLEX
10 CAPCELL HD-100 or equivalent make), placing the same 25 mm below top of pavement
slab, sealing with bituminous hot sealing compound (Grade 'A' ISI)/polysulphide at 4.5 m
interval in CC pavement including cost and conveyance of all materials for expansion joints
conforming to MORTH specification No. 602 - 1 Rmt
as per approved rated in previous
estimation 1 Sqm. 223.97 223.97
7
RCC Culvert SLABS
A. MATERIALS:
20 mm aggregate cum 0.54 1804.61 974.49
10 mm aggregate cum 0.36 1374.61 494.86
Sand cum 0.450 169.90 76.46
Cement Kgs 0.330 4800.00 1584.00
3129.80
B. LABOUR:
1st Class Mason day 0.067 465.00 31.16
2nd Class Mason day 0.133 420.00 55.86
Mazdoor (Both Men and Women) day 2.500 370.00 925.00
1012.02
Add 20% extra on Labour for Municipal 202.40
limits
1214.42
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.28 cum) hour 0.267 492.60 131.52
capacity Page 29 item 38-a
Water (including for curing) kl 1.200 103.00 123.60
4599.35
for culvert slab -1.00 cum
R.C.C. cum 1.00 4599.35 4599.35
4599.35
Overheads & Contractors Profit 13.615% 626.20
BASIC COST per 1 cum 5225.55
Laying VCC (1:2:4) using 20mm HBG m/c metal and OPC including cost & conveyance of all
materials, labor charges, centering, machinery, laying in position, vibration, curing and all
incidental chrges etc., complete for lean concret
9
for culvert walls
(i) Unit = 1cum
A. MATERIALS:
Cement kg 330.00 4800.00 1584.00
Coarse aggregate 20 mm cum 0.90 1804.61 1624.15
coarse aggregate (Sand) cum 0.45 169.90 76.46
Water (including for curing) kl 1.20 103.00 123.60
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.28 cum) hour 1.00 492.60 492.60
capacity Page 29 item 38-a
C. LABOUR:
Mason (30% 1st Class + 70% 2nd Clas) day 0.10 433.50 43.35
Brick Masonry in CM (1:6) with Bricks traditional size 23 x 11 x 7 cms 2nd class including
cost and conveyance of all materials to site of work and curing etc., complete.
BLD-CSTN-3
16
Unit = 1cum
A. MATERIALS:
Cement kg 48.00 4800.00 230.40
Bricks traditional size 23 x 11 x 7 cms Nos 512.00 2957.16
2nd class 5775.71
Plastering with CM (1:3), 12 mm thick including cost and conveyance of all materials like
cement, fine aggregate (sand) , water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental and labour charges such
9 BLD-CSTN-6-1
as machine mixing, , curing etc.,complete .
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 2635.15 395.27
B. LABOUR:
Mason 1st class day 0.60 465.00 279.00
Mazdoor (unskilled) day 0.96 370.00 355.20
Add for MA @ 20 % 126.84
Grand Total 1156.31
c&d) Overheads & Contractors Profit @ 13.615% 157.43
10 sqm 1313.74
1 sqm 131.37
59 Plastering with CM (1:4), 20 mm thick including cost and conveyance of all materials like
cement, fine aggregate (sand) , water etc., to site and including Seigniorage charges, sales &
BLD-CSTN-6-7 other taxes on all materials including all operational, incidental and labour charges such
as machine mixing, , curing etc.,complete .
20
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.210 2059.15 432.42
B. LABOUR:
Mason 2nd class day 0.94 420.00 394.80
Mazdoor (unskilled) day 1.60 370.00 592.00
Add for MA @ 20 % 197.36
Grand Total 1616.58
c&d) Overheads & Contractors Profit @ 13.615% 220.10
10 sqm 1836.68
1 sqm 183.67
Collection, supply and spreading of Gravel including cost and conveyance of material to
work site, stacking to deptl. gauge and labour charges etc.complete for shoulders as per
10 Gravel 6
Table 400- 8 & 9 of MORTH
gravel filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 370.00 114.70
Add 20% extra on Labour for Municipal limits 22.94
b) Material
gravel filling cum 1.00 196.13 196.13
333.77
Overheads & Contractors Profit 13.615% 45.44
Rate per cum 379.21
Plain Cement Concrete (1:4:8) for under bed using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials and
including all charges for machine mixing, laying concrete in foundations and under flooring bed,
11 BLD-CSTN-2-5 ramming in 15 cm layers finishing top surface to the required level curing etc., complete for finished
item of work. (APSS No. 402)
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 4800.00 777.60
Coarse aggregate 40 mm cum 0.90 1284.61 1156.15
Fine aggregate (Sand) cum 0.45 169.90 76.46
Water (including for curing) kl 1.20 103.00 123.60
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 492.60 492.60
C. LABOUR:
Mason (30% 1st Class + 70% 2nd Clas) day 0.1 465.00 46.50
Unit = 1cum
Cost of Gravel for filling cum 1.00 196.13 196.13
Mazdoor for filling including watering and
day 0.31 370.00 114.70
ramming
Add 20% on filling 22.94
333.77
c&d) Overheads & Contractors Profit 45.44
Grand Total 379.21
11 Supply and placing of the Design Mix VRCC Concrete corresponding to IS 456 using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate)
from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on
all materials including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from
standard suppliers approved by the department including pumping, centering, shuttering, laying
concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication charges for
finished item of work.
PLINTH
Footings PEDESTALS
Beams
M20 Design mix 6294.13 6294.13 6294.13
Hire charges of centering and scaffolding 277.00 1335.00 315.00
A. MATERIALS:
20mm HBG graded metal cum 0.800 1615.36 1292.29
Sand cum 0.400 169.90 67.96
Cement Kgs 350.000 4.80 1680.00
B. LABOUR:
1st Class Mason day 0.167 465.00 77.66
2nd Class Mason day 0.167 420.00 70.14
Mazdoor (Both Men and Women) day 5.600 370.00 2072.00
Add for MA @ 20 % 443.96
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.333 492.60 656.64
capacity
Water (including for curing) kl 1.200 103.00 123.60
BASIC COST per 1 cum 6484.24
COLUMNS FF SF TF
M20 Design mix 6484.24 6484.24 6484.24
Hire charges of centering and scaffolding
341.00 341.00 341.00
BLD-CST - 9-5
White washing two coats with whiting of approved quality to give an even shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered
materials including cost of all materials, labour charges and incidental such as
scaffolding, lift charges etc., complete for finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / kg 2.00 27.95 55.90
Gum, conjee water, or prickly pear juice including L.S 2.50
necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.210 535 112.35
Mazdoor (unskilled) day 0.320 370.00 118.40
Sundries including brushes, ladders, etc., 1.00% 0.58
Total cost for 10 sqm 289.73
Total cost for 1 sqm 28.97
BLD-CST - 9-5
Flooring with ceramic tiles, set over base coat of cement mortar (1:8), 12 mm thick
over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to
full depth mixed with pigment of matching shade, including cost of all materials like
cement, sand water and tiles etc., complete, including seigniorage charges, etc.,
complete for finished item of work, but excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles sqm 10.10 432.00 4363.20
Cement for CM (1:8) for base coat kg. 21.60 1195.15 2.50
Cement for slurry kg. 33.00 4.8 2.50
White cement kg. 2.00 27.95 55.90
Sand for CM (1:8) cum 0.12 244.90 29.39
B. LABOUR
Mason 1st class day 0.96 465.00 446.40
Mason 2 class
nd day 2.24 420.00 940.80
Mazdoor (unskiled) day 3.30 370.00 1221.00
Add water charges 1% 1.00% 103.00 1.03
Total cost for 10 sqm 7062.72
Total cost for 1 sqm 706.27
Painting Walls with Snowcem or other equal and approved Water Proof Cement Paint
over Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg kg 3.500 41.00 143.50
B. LABOUR
Painter day 0.500 535.00 267.50
Mazdoor (unskilled) day 1.500 370.00 555.00
Sundries including brushes, etc., 1.000% 9.66
Total cost for 10 sqm 975.66
Total cost for 1 sqm 97.57
Supply, Delivery filter media all round casing pipe for Bore well including
2 1 bag cost conveyance etc., complete as per site conditions
Rate 4544.60
Rate 499.91
Labour charges for sloter cutting to 180mm ФPVC pipe complete as per
6 1 rmt ss.
Rate 384.02
Rate 96.90
Rate 34084.50
Supply and delivery of 65mm 7/18 WPSC(whether proof single core )ISI
9 1 rmt Aluminium service coils of make finolex/ Goldmedal/million/payal/ PVC
ELEC-1.6.2,SSR 2018-19.
Rate 31.92
RATE ANALYSIS FOR FINISHED ITEMS (DATA) including sieniorage charges-2019-20
Index- S No Description Unit Quantity Rate Rs. Amount Rs.
code
1 2 3 4.00 5 6
Unit : 1cum
A. MATERIALS:
Cement kg. 480.00 38.50 18480.00
Sand (including 5% wastage) cum 1.05 1497.50 1572.38
C. LABOUR:
Man mazdoor for mixing day 0.20 420.00 84.00
mortar
Add Municipal Allowances @
20% 4027.28
Grand Total 24163.65
Unit : 1cum
A. MATERIALS:
Cement kg. 360.00 38.50 13860.00
Sand (including 5% wastage) cum 1.05 1497.50 1572.38
C. LABOUR:
Man mazdoor for mixing day 0.20 420.00 84.00
mortar
Add Municipal Allowances @
20% 3103.28
Grand Total 18619.65
Chapter- Filling with sand in the bottom layers not exceeding 15 cm thick, consolidating
3 11 RBR- each deposited layer by watering and ramming including cost and conveyance of
FNDN-2 water to work site and all operational, incidental, labour charges, hire charges of
T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
sand filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 420.00 130.20
Add 20% extra on Labour for 26.04
Municipal limits
b) Material
sand cum 1.00 1362.50 1362.50
1492.70
Overheads & Contractors Profit 13.615% 203.23
Rate per cum = a+b+c+d 1721.97
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / hour 1.00 394.40 394.40
0.8 cum) capacity
C. LABOUR:
Mason day 0.1 500.00 50.00
Mazdoor (unskilled) day 1.39 420.00 583.80
Add for MA @ 20 % - 126.76
subTotal 3685.11
c&d) Overheads & Contractors Profit 501.73
Grand Total 4313.59
FOUNDATIONS, PLINTH,
PEDESTALS (Below Plinth)
A. MATERIALS:
20mm HBG graded metal cum 0.900 1463.92 1317.53
Sand cum 0.450 1497.50 673.88
Cement Kgs 330.000 4.60 1518.00
B. LABOUR:
1st Class Mason day 0.133 500.00 66.50
2nd Class Mason day 0.267 460.00 122.82
Mazdoor (Both Men and day 3.600
Women) 420.00 1512.00
ADD MA @20% 340.26
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / hour 1.000
0.8 cum) capacity 394.4 394.40
Cost of Petrol for Vibrator Liters 0.667 209.10 139.47
Water (including for curing) kl 1.200
107.00 128.40
BASIC COST per 1 cum 5873.00
Contract Profit 13.615% 799.61
7012.87
COLUMNS, LINTELS, WATER
TANKS, RCC WALLS IN
BUILDINGS
A. MATERIALS:
20mm HBG graded metal cum 0.900 1463.92 1317.53
Sand cum 0.450 1497.50 673.88
Cement Kgs 330.000 4.60 1518.00
B. LABOUR:
1st Class Mason day 0.167 500.00 83.50
2nd Class Mason day 0.167 460.00 76.82
Mazdoor (Both Men and day 4.700
Women) 420.00 1974.00
426.86
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / hour 1.000
0.8 cum) capacity 394.4 394.40
Water (including for curing) kl 1.200
107.00 128.40
Hire charges of centering Sqm 1.000 171.24 171.24
6337.77
e) Contract Profit 13.615% 862.89
7627.52
BASIC COST per 1 cum PLINTH Beams
Footings PEDESTALS
M20 Design mix 7627.52 7627.52 7627.52
Hire charges of centering and
scaffolding 277.00 1335.00 315.00
Labour charges 473.00 1141.00 753.00
Add for MA @ 20 % 94.60 228.20 150.60
Sub Total 8377.52 10103.52 8695.52
Overheads & Contractors 1140.60 1375.59 1183.90
Profit 13.615%
9612.72 11707.32 10030.02
BLD- Supplying, fitting and placing HYSD bar reinforcement in foundation complete as
6 CSTN-2- per drawings and technical specifications for Bars below 36 mm dia including
18 over laps and wastage, where they are not welded
Unit = t
(a) Material
HYSD bars including 5 per cent t 1.05 38500.00 40425.00
for overlaps and wastage
Unit = 1cum
A. MATERIALS:
Cement kg 48.00 4600.00 220.80
Fly Ash Bricks traditional size Nos 512.00 3165.55
23 x 11 x 7 cms 2nd class 6182.71
a) S& F 50 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with
GI fittings including the cost of pipe Including labour charges etc complete.
11 1 rmt
Hiring the jcb for jungle clearance including driver,diesel charges etc as per departemental
instructions
12 1 hr
1.00 hr 1000.00
Rate 1000.00
Sullurpeta Municipality
DETAILED AND ABSTRACT ESTIMATE
Name of the work: Providing of parking tiles at chengalamma temple area in 8 th ward of Sullurpet Municipality
Painting to the brick wall 1 x 20 1.61 - 0.900 28.980 122.420 1 sqm 3547.73
ECV : 1252941.32
9 Provision for GST % 12 150352.96
10 Provision Labour cess % 1 12529.00
11 Provision for 3rd party quality control 0.75 9397.06
12 provision for user Charges % 1 12529.00
13 Unforeseen Items(Lump Sum) % 12250.66
Total 1450000.00
Est.cost.Rs15.00 Lakhs
Under the program of Developmental works in Sullurpet Municipality , the Public of
Rajaka Community Sullurpet Municipality has facing problems and they are submitted
representation for constructing Dobhi ghat in sullurpet municipality. . In this regard the Municipal
Council Sullurpet Municipality has resolute the proposed work Vide CR No.146 dated 07.09.2020
for the work of Providing of Compound wall & other civic eminities to dobhighat in 17th
ward of Sullurpet Municipality
Accordingly, the estimate is prepared for Providing of Compound wall & other
civic eminities to dobhighat in 17th ward of Sullurpet Municipality
The Estimate is prepared as per Schedule of rates 2019-20 and the work
were carried out as per the APDSS only.