REQUEST FOR INSPECTION

Saudi Aramco 6717-ENG (11/98) 726-200 (Inspection Department) Ref: RFI No. RFI-WELD-049

BI: 10-09003-0006 JO: Phase Construction Title Industrial Support Facilities (ISF) Package 13

To : Project Inspection Unit/ Mr. Liaqat Ali Civil Mech. Plumb. Comms. Elect. Others

Inspection/monitoring is required on (date) 23-Feb-2021 (time) 9:00 AM prior to

for the following location/equipment Administration Building T81-B100

Work Permit Required: Yes No Inspection Level: RH Review/Approval of Documents Hold points Witness Point

SAPMT representative has verified that the work is ready for CONTRACTOR has verified that the work to be inspected is
inspection and conforms to the project requirements complete and in compliance with the following specifications:

SAPMT Name Abdullah Alwasel SAES/SAMSS/Others# SATIP-M-001-01 / SAIC-M-2012


Signature Date 22-Feb-2021 Contractor/Company RTCC
Telephone Fax QA/QC Name Britto Emerson
QA/QC Signature Date 22-Feb-2021

This form received by the undersigned Inspection Department employee:

Name Liaqat Ali Signature Date Time

Work Description: Pre-Welding Inspection of Fully Threaded Rod on the embedded


plates 1VL 2006A-1pc, 1VL 2015A-1pc, 1VL 3012-1pc, 1VL 1015-1pc, 1VL 2019-1pc, 1VL
1004-1pc, 1VL 1005-1pc

NOTE: Inspector's signature is for receiving this request only and not for approval or disapproval of the work or facility inspected.

Distribution:
A. Original – Inspection Unit B. 1st Copy – RPO Proponent C. 2nd Copy – ID Coordinator D. 3rd Copy – Construction Contractor