Professional Documents
Culture Documents
3 - Start
3 - Start
Contents
Introduction...........................................................................................................................................2
Project Overview...................................................................................................................................2
Feasibility of the Objectives to be Achieved..........................................................................................2
Objective 1: To establish a multi-purpose health and well-being campus...................................3
Objective 2: To be fully operational within three years of commencing the project...................3
Objective 3: To have a positive impact on the local environment................................................4
Objective 4: Be delivered within the project budget......................................................................5
Proposed Budget, Procurement Strategy, and Timeframe....................................................................5
Business Case Budget.......................................................................................................................5
Procurement Strategy......................................................................................................................6
Timeframe........................................................................................................................................6
Project Governance Structure...............................................................................................................7
Stakeholder Management.....................................................................................................................7
Risk........................................................................................................................................................8
Recommendations and Key Findings.....................................................................................................8
References.............................................................................................................................................9
TablesY
Table 1 - Process Groups.......................................................................................................................4
Table 2 - Project Budgets.......................................................................................................................6
Table 3 - Timeframes.............................................................................................................................7
Figure
Figure 1 - Ground Plan...........................................................................................................................5
Figure 2 - Project Approval Gates..........................................................................................................7
Figure 3 - Project Governance Structure...............................................................................................8
2
Introduction
The Sanctuary Health and Wellness Complex Project Business Case is an attempt to layout the
feasibility of a three year, $15 million project which is primarily construction based. The following
paper will put forwards a critique of the Business Case which looks at the feasibility of the objectives
to be achieved, proposed budget, procurement and timeframe, project governance structure,
stakeholder management, and project risk. Before this critique can be conducted it will be useful to
provide an overview of the project. A business case is the document which looks at the economic
feasibility of a project whilst also outlining the benefits (PMI, 2017). As the business case is referred
to throughout the life of a project it should list the project objectives and reasons for the project
(PMI, 2017). The primary framework upon which the critique will be conducted will be the PMBOK
(PMI, 2017) with particular reference to the knowledge areas that relate to strong project
management principles. A number of recommendations will be presented with a view to increasing
the likelihood of project success.
Project Overview
Divine Health Service (DHS) is planning a development of an entirely new site which will house a
healthcare facility designed to relocate their existing services. The project will deliver four primary
health focused buildings and an administrative centre with sundry services such as electricity, water
supply and recycling, carparking and service roads on a two hectare site. DHS already has title of the
land along with approval from the Minister for Health to provide healthcare services upon it. The
preliminary budget put forwards is $15 million with an expected delivery date within three years. A
program of works lays out eight interconnected projects for delivery of the health and wellness
complex.
The use of project management process groups is recommended as a mechanism with which to
achieve specific project objectives (PMI, 2017). When looking at the DHS Business Case there is some
evidence that these groups are considered (see Table 1).
3
Process Group Evidence of use
Initiating Identify stakeholders
Planning Mention of the development of a Project Management Plan
Mention of Scope within the Business Case
Timelines which have approval gates built in
A budget is defined
Mention of a procurement plan within the Business Case
A stakeholder management plan
Executing Laid out briefly in the eight projects
Closing Project close requiring the completion of all construction
Table 1 - Process Groups
What is missing from the Business Case is a clear definition of the Monitoring and Controlling
Process Group. This Progress Group allows the Project Manager to know how each aspect of the
project was achieved and relates to establishing the project performance and reporting systems
(Wysocki, 2009). Without these project performance and reporting systems measurement of the
progress of the deliverables is difficult at best.
Additionally, there are a number of key aspects missing within the Planning and Process Group
which would go towards ensuring that the Project Objectives are met, examples include; the
Business Case does not touch on how the requirements are to be collected, there is no estimation of
activity duration, and there is no estimation of costs outside of a few pieces of equipment and high
level budget targets.
4
Objective 3: To have a positive impact on the local environment
The Business Case has set up a number of contradictions and also extremely problematic solutions to
achieve this Project Objective. Whilst including environmental solutions within a project is laudable
theses outcomes should at least be governed by local, state and federal statutes whilst also
contributing towards economic realities with an in-depth feasibility studie a must (Shen, Tam, Tam,
& Ji, 2010).
A simple viewing of the proposed ground plan shows that the water recycling services are situated
within a few meters of the Serviced Residential Facility (see Fig. 1). The Business Plan does not state
if this water recycling will be grey or black water, if the levels of grey water exceed 3,000 litres per
day additional State Government approvals would be required (BCC, 2019). Under the Water Supply
(Safety and Reliability) Act 2008 there are stringent requirements regarding the use of recycled
water and the treatment of sewage (Government, 2017).
At the very least the approval process of this Project Objective should be mentioned within the
Project Risks. Any risk management should be tailored towards the organisation undertaking the risk
whilst also taking into account externalities such as government regulation (Baccarini & Archer,
2001; Raz, Shenhar, & Dvir, 2002). A decision support system for this Project Objective and a way to
maximise project value might be to look at a set of options in regards to utilities such as power and
water as a way to mitigate this risk (Mahdi & Alreshaid, 2005).
The major contradiction within this Project Objective is the stated aim to be energy and water
neutral. However, within two of the sub-projects, the pool and the administration building, gas is
listed as an energy source. A fundamental aspect of a project business case is to align all of the
5
necessary assumptions, alternatives and constraints whilst avoiding internal inconsistencies
(Kerzner, 2017).
The greatest risk of not achieving this set of projects lays in the overall compartmentalisation of each
project. By placing each building into a different project immediately the overheads of duplication
start to play into the bottom line of the budget. Whilst there is value in placing a number of
interrelated projects into a program (PMI, 2017), with the Sanctuary Health and Wellness Complex
Project Business Case there seems to be a lack of high-level planning which could track the
interdependencies and progress of individual projects. As an example, the Integrated Commissioning
and Operational Handover Works Project which could be a strong approach to bringing all the
projects together makes no mention of the energy and water generation and storage technology
project which is key to ensuring all buildings have basic utilities.
Project Budget
Site Infrastructure and Enabling works $ 1,500,000
Wellness Centre / Alternative Medical Centre $ 2,500,000
Community Health Centre $ 2,500,000
Serviced Residential Facility $ 2,000,000
Sports Centre $ 3,000,000
Administration and Centralised Building Services $ 2,000,000
Community Engagement and Promotions $ 750,000
Integrated Commissioning and Operational Handover works $ 750,000
Total $ 15,000,000
Table 2 - Project Budgets
A quick review of the cost per square meter of commercial buildings in Australia shows that a cost
between $2,900 and $3,800 per square meter is not unreasonable (LMI-Group, 2019; Washington-
Brown, 2019). The DHS Business Case allows for $2,500 per square meter for the four largest
buildings (see Table 2), inclusive of specialist medical equipment.
Whilst the projected budget is not wildly off from market expectations there is little to no room for
any unexpected costs. Delivering on budget is the goal of most projects, but as the Business Case
6
states that “there is no allowance for escalation”, if interpreted correctly this shows that there are
no contingency funds. As it is well documented that the majority of construction projects exceed
their original budget (Shane, Molenaar, Anderson, & Schexnayder, 2009), there is a major risk built
into the Business Case that could lead to either major cost blowouts or even project failure.
Procurement Strategy
How a project defines and implements its procurement strategy is one of the PMBOK Project
Management Knowledge Areas (PMI, 2017). A strong overarching procurement strategy should
deliver value creation whilst also providing strong relationships with supply chain alliances (Walker &
Rowlinson, 2008). With the structure of having eight different projects defined within the DHS
Business Case there may well be eight different procurement strategies. As each project has been
provided permission to decide on timeframes and approaches to procurement there is a risk that
this will lead to overall project delays. In a project which is to be tied tightly to community
stakeholders the procurement strategy can be influenced in a positive manner by these participants
in the project (Walker & Rowlinson, 2008).
Timeframe
As might be expected project timeframes are covered by the Project Schedule Management
Knowledge Area in the PMBOK (PMI, 2017). The Business Case timelines lay out the program of
works to be finished within two years and nine months, inside the three years mentioned in Project
Objective Two (see Table 3).
The use of approval gates (see Fig. 2) is a well-regarded project management practice for ensuring
that a phased approach contributes towards improved project performance and success (Besner &
Hobbs, 2006). Attention should be paid to the execution phase, specifically as several of the
construction projects cannot commence until the completion of the Site Infrastructure and Enabling
Works sub-project. This sets up a critical path for the entire project.
The Critical Path method is a tool to develop and control Schedule Management which will allow
prediction of timeframes, evaluation of alternative plans, provide the ability to check progress, and
form the basis for decision making within the project (James E. Kelley & Walker, 1959). What is not
considered within the Business Plan is the timelines for delivering the additional project relating to
the water and power services. Missing out a dependency within the Critical Path method can
7
contribute towards projects going overtime and often over budget and should be considered a
project risk (Kliem & Ludin, 2017).
There are several issues with the hierarchical nature of the Project Governance Structure (see Fig. 3),
however the key one is the lack of link back into the parent organisation. Without providing a direct
link between the executive and the project there is a risk that projects may continue without
supporting the organisation’s strategy (Too & Weaver, 2014). Such a misalignment may also mean
that the PMO is unable to provide correct oversight and strategic reporting capabilities (Too &
Weaver, 2014).
Stakeholder Management
A special mention should be made of the Stakeholder Management Plan, seen as critical across four
of the five Process Groups (PMI, 2017). Several additional afterthoughts seem to have been brought
into the Business Case which present additional risk of project success, such as linking the sporting
facilities to a local school which is yet to be built. By bringing in this kind of community stakeholder
without due consideration to the overall organisational strategy of DHS, which is primarily a
healthcare provider, considerable stakeholder dissatisfaction could occur (Mallak, Kurstedt, &
Patzak, 1991). Properly managed this inclusion could add additional value to the overall project and
increase additional future clients.
What is not considers as part of the Stakeholder Management Plan is the existing clients and their
ability to access the health services in the new location, a possible hurdle in achieving the Project
Objective of realising an annual turnover of $50 million. Overall the list of stakeholders identified
may be too few as additional stakeholders such as a procurement company, contractors, DHS itself
are not considered. The decision to split Community Engagement and Promotions into a separate
project ignores that stakeholder management is a key component of each sub-project which could
lead to mixed messages being delivered.
8
Risk
Throughout this critique a number of risks have been identified which are not covered in the
Business Case:
Whilst many of these might not be considered normal construction project risks, by their very
exclusion in the Business Case they become project risks. Missing key risks at the initiation and
planning process groups can have a detrimental impact on project success (Kliem & Ludin, 2017).
1. Better identification of the strategic need for the new complex, along with an alignment to
the parent organisation’s ongoing strategy.
2. A reconsideration of the approach to supplying water and power to the final site, the level of
risk this introduces may be too high and severely impact on overall project success. At the
very least provide additional project options.
3. Consider bundling the construction sub-projects together to remove the siloed nature of
several processes, such as schedule and procurement management.
4. Reconsider the budget required to deliver the project on time. A larger budget with built in
contingency is suggested.
Whilst not addressed specifically throughout the critique, by not addressing the four
recommendations the possibility of scope creep becomes a strong probability. As there is no
statement of project exclusions this risk becomes even more likely.
9
References
Atkinson, R., Crawford, L., & Ward, S. (2006). Fundamental uncertainties in projects and the scope of
project management. International Journal of Project Management, 24(8), 687-698.
doi:https://doi.org/10.1016/j.ijproman.2006.09.011
Baccarini, D., & Archer, R. (2001). The risk ranking of projects: a methodology. International Journal
of Project Management, 19(3), 139-145. doi:https://doi.org/10.1016/S0263-7863(99)00074-
5
Banuelas Coronado, R., & Antony, J. (2002). Critical success factors for the successful
implementation of six sigma projects in organisations. The TQM Magazine, 14(2), 92-99.
doi:10.1108/09544780210416702
BCC, B. C. C. (2019). Greywater uses. Retrieved from https://www.brisbane.qld.gov.au/environment-
waste/water/water-smart-homes/greywater/greywater-uses
Besner, C., & Hobbs, B. (2006). The Perceived Value and Potential Contribution of Project
Management Practices to Project Success. Project Management Journal, 37(3), 37-48.
doi:10.1177/875697280603700305
Chua, D. K. H., Kog, Y. C., & Loh, P. K. (1999). Critical Success Factors for Different Project Objectives.
Journal of Construction Engineering and Management, 125(3), 142-150.
doi:10.1061/(ASCE)0733-9364(1999)125:3(142)
de Wit, A. (1988). Measurement of project success. International Journal of Project Management,
6(3), 164-170. doi:https://doi.org/10.1016/0263-7863(88)90043-9
Ebbesen, J. B., & Hope, A. (2013). Re-imagining the iron triangle: embedding sustainability into
project constraints. PM World Journal, 2(III).
Government, Q. (2017). Water Supply (Safety and Reliability) Act 2008. Retrieved from
https://www.legislation.qld.gov.au/view/html/inforce/current/act-2008-034
Howell, G., Laufer, A., & Ballard, G. (1993). Uncertainty and project objectives. Project Appraisal,
8(1), 37-43. doi:10.1080/02688867.1993.9726884
James E. Kelley, J., & Walker, M. R. (1959). Critical-path planning and scheduling. Paper presented at
the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference, Boston,
Massachusetts.
Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and
controlling (12 ed.). New Jersey: John Wiley & Sons.
Kliem, R. L., & Ludin, I. S. (2017). Reducing project risk. London: Routledge.
LMI-Group. (2019). Building Cost Calculator/Indicative Guide Retrieved from
https://www.lmigroup.com/RiskCoach/calculators/buildingcalculator.aspx?access=anv
Mahdi, I. M., & Alreshaid, K. (2005). Decision support system for selecting the proper project delivery
method using analytical hierarchy process (AHP). International Journal of Project
Management, 23(7), 564-572. doi:https://doi.org/10.1016/j.ijproman.2005.05.007
Mallak, L. A., Kurstedt, H. A. J., & Patzak, G. R. (1991). Satisfying stakeholders for successful project
management (DOE/DP/48058-T8; Other: ON: DE91012413 United States Other: ON:
DE91012413 OSTI; NTIS; GPO Dep. CHO English). Retrieved from
Montgomery, D. C., & Woodall, W. H. (2008). An Overview of Six Sigma. International Statistical
Review, 76(3), 329-346. doi:10.1111/j.1751-5823.2008.00061.x
Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: inhibiting factors
and mitigating measures in practice. Construction Management and Economics, 28(5), 509-
526. doi:10.1080/01446191003674519
PMI, P. M. I. (2017). A guide to the project management body of knowledge (PMBOK guide) (Vol. 6th
Edition). Newtown Square, Pennsylvania: Project Management Institute.
10
Pyzdek, T. (2003). The six sigma. McGrow-Hill, New York.
Raz, T., Shenhar, A. J., & Dvir, D. (2002). Risk management, project success, and technological
uncertainty. R&D Management, 32(2), 101-109. doi:10.1111/1467-9310.00243
Roberts, P. (2011). Effective Project Management: Identify and Manage Risks Plan and Budget Keep
Projects Under Control. London: Kogan Page Publishers.
Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C. (2009). Construction Project Cost
Escalation Factors. Journal of Management in Engineering, 25(4), 221-229.
doi:10.1061/(ASCE)0742-597X(2009)25:4(221)
Shen, L.-y., Tam, V. W. Y., Tam, L., & Ji, Y.-b. (2010). Project feasibility study: the key to successful
implementation of sustainable and socially responsible construction management practice.
Journal of Cleaner Production, 18(3), 254-259.
doi:https://doi.org/10.1016/j.jclepro.2009.10.014
Shenhur, A. J., Levy, O., & Dvir, D. (1997). Mapping the dimensions of project success. Project
Management Journal, 28(2), 5-13.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework
for project governance. International Journal of Project Management, 32(8), 1382-1394.
doi:https://doi.org/10.1016/j.ijproman.2013.07.006
Toor, S.-u.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: Stakeholder perception of key
performance indicators (KPIs) for large-scale public sector development projects.
International Journal of Project Management, 28(3), 228-236.
doi:https://doi.org/10.1016/j.ijproman.2009.05.005
Walker, D., & Rowlinson, S. (2008). Procurement Systems: a cross-industry project management
perspective. London: Taylor & Francis.
Washington-Brown. (2019). Construction Cost Calculator Australia. Retrieved from
https://www.washingtonbrown.com.au/building-cost-calculator/
Wysocki, R. K. (2009). Effective Project Management: Traditional, Agile, Extreme (5th ed.).
Indianapolis: Wiley.
11