Professional Documents
Culture Documents
I
n today’s challenging business climate, some building owners are delaying the Variable speed drives (VSDs) can be
retrofitted onto centrifugal chillers and
implementation of new building projects and concentrating on making existing provide energy savings if the conditions
are right. It is important to understand
buildings and systems more efficient. Within an existing chilled-water system, there when conditions may (or may not) war-
rant a VSD retrofit.
are several areas of opportunity to improve energy efficiency. This article concen- Figure 1 shows the performance of a
centrifugal chiller before and after being
trates on the areas within chilled-water systems that may yield energy savings. retrofitted with a variable speed drive. It
depicts chiller performance at load points
Options are discussed for each of the This article does not examine eco- between 20% and 100% for three different
following: nomic payback; a detailed energy entering condenser-water temperatures.
•• Chiller retrofits; analysis is the best method of compar- The results clearly show that the drive
•• Changes to pumps and flow rate; ing system options and their respective does not result in reduction of chiller
•• Examining different chilled- and economic impact for each project. See
condenser-water temperatures; and the sidebar, “System Analysis,” for About the Authors
•• Enhancing system controls. more information. In addition, Chap- Mick Schwedler, P.E., is applications engineering
Each topic is examined in more detail ter 36 (Owning and Operating Costs) manager for Trane, a division of Ingersoll Rand in La
Crosse, Wis. Schwedler is chair of SSPC 90.1 and is
followed by Table 3, which provides guid- of the 2007 ASHRAE Handbook— a member of the Energy & Atmosphere Technical
ance as to which modifications may be HVAC Applications, provides further Advisory Group of the U.S. Green Building Council.
best for three chilled-water system types. information. Beth Bakkum is an information designer at Trane.
If the facility operates 24/7, even if the design day is hot and humid, there may be ben-
efits due to reduced ambient wet-bulb temperatures during the fall and winter months.
How often will the chiller operate
at the reduced load and reduced If the system has an economizer, many of the low-load hours with low condenser-water
condenser-water temperatures? temperatures are eliminated since no mechanical cooling is required. In examining
Figure 1, many of the low-load hours on the bottom two lines may well occur at times an
economizer eliminates the mechanical cooling load.
If so, the load reduction in conjunction with reduced condenser-water temperatures may
Is the chiller oversized for the present load?
offer significant savings.
Table 1: It is important to understand when conditions may (or may not) warrant a VSD retrofit.
65°F (18°F), the chiller savings range from 8% to 32%, depend- 250
ing on load. This does not include cooling tower fan energy to 200
reach the lower setpoint. 150
Is the drive replacement beneficial and economical? That 100
depends on the answers to the questions in Table 1.
50
Of course, not every chiller will perform similarly to Figure
0
1 when retrofitted with a variable speed drive. Different chiller 0 200 400 600 800
designs can benefit more or less than shown in Figure 1. It is Tons
critical to have performance data before and after the VSD Figure 1: Centrifugal chiller performance before and after VSD retrofit.
retrofit. This allows the project team to make a decision for the
specific chiller, location, and application. multiple drives is sometimes driven by the desire to “equalize
Whether or not one should retrofit every chiller with a drive run-time” on all chillers. A possible outcome of this operating
is primarily an economic question. Often applying a drive to philosophy is that all chillers must be rebuilt or replaced at
one chiller in the system yields the best payback. Purchasing approximately the same time.
System Analysis When considering a interactions of weather, loads, and cooling tower
retrofit, properly analyzing factors that affect the performance, a bin analysis is not adequate. Software
economic viability of that retrofit is critical. To tools that incorporate all of the above attributes can be
calculate chiller and system efficiency, ARI 550/590- used to perform a robust chilled water plant analysis
2003,1 Appendix D, recommends conducting a in 30 to 60 minutes. In addition, the actual utility rates,
comprehensive analysis that includes actual weather not a “weighted average,” and chilled-water system-
data, building load characteristics, operational level controls also should be modeled.
hours, economizer capabilities, and energy drawn by A comprehensive analysis enables the project team,
auxiliaries (cooling towers, pumps, etc.). operators, and building owner to make accurate
Considering all of these factors and the complex comparisons of multiple options.
200
same price
high-efficiency 150
chiller. 100
50
0
0% 20% 40% 60% 80% 100%
% Load
Figure 2 presents the results of select- one high-efficiency and one VSD chiller
ing a smaller chiller (assuming cooling provide the best payback. In a humid
load has been reduced due to lighting environment where there are fewer hours
retrofits) and compares the performance with low tower-water temperature (such
of a 600 ton high-efficiency chiller as San Juan, Puerto Rico, or Houston) two
with an equally priced VSD chiller that high-efficiency chillers may offer the best
meets Standard 90.1-2007 requirements payback. This is true particularly when the
at ARI 550/590 standard rating condi- maintenance and life-cycle replacement
tions. Note that Standard 90.1 requires cost of the VSD is factored into the analy-
both full and part load requirements to sis. This again underscores the importance
be met, and drive losses are included of performing a comprehensive analysis.
in the rating.
Present Standard 90.1 requirements: Design Parameters
•• 0.576 kW/ton full load and 0.549 When asked to retrofit a chilled-water-
integrated part load value (IPLV). system, project teams often use the same
Standard 90.1 requirements as of Jan. design chilled-water and condenser-water
1, 2010 (from Standard 90.1-2007 Ad- flow rates and temperature differences.
dendum m): This is not likely to produce optimal
•• Either 0.570 kW/ton full load and results. Instead, judicious use of existing
0.539 IPLV; or infrastructure—and using different flow
•• 0.590 kW/ton full load and 0.400 rates and temperature differences—offers
IPLV. significant benefits to the building owner.
An example of same price chillers at The chilled-water options apply to air-
ARI 550/590 standard rating conditions cooled and water-cooled chillers.
gives the following performance:
•• VSD: 0.572 kW/ton full load and Reducing Chilled-Water Flow Rate,
0.357 IPLV; and Expanding DT
•• High Efficiency: 0.501 kW/ton full The ASHRAE GreenGuide4 references
load and 0.430 IPLV. the CoolTools Chilled Water Plant Design
Once again it is obvious that energy and Specification Guide5 and recom-
savings are accrued by using a VSD on mends “starting with a chilled-water
a chiller when cooler tower-water tem- temperature difference of 12°F to 20°F
perature is available, that is, the refrigerant (7°C to 11°C).” While primarily intended
pressure differential or “lift” is reduced. for new systems, this guidance can be
This makes sense since the drive speed used for many existing systems.
cannot reduce without causing the chiller Reducing Pumping Energy. Sig-
to surge, unless the required compressor nificant pump savings can be realized
lift is reduced. by reducing flow rates, especially in
Given the previous information, a constant-flow chilled-water systems. This
comprehensive analysis may show that may be achieved by making those flow
Chiller
P
Back-up Pump
Figure 3: Variable
Air-side Coil With Three-
primary flow (VPF) Way Valve to Provide
system using three- Minimum Flow Rate
DP
cooling capacity.” This is done by selecting pass line with a control valve to maintain
the existing tower and new chiller at higher the chiller’s minimum flow rate. In an ex-
temperatures (e.g., 88°F to 103°F [31°C isting plant, minimum flow can instead be
to39°C], rather than 85°F to 95°F [29°C to maintained by using an adequate number
35°C]). Using this concept may well bring of three-way valves to ensure that the chill-
an “over-budget” job back into budget. er’s minimum required evaporator flow
rate is always met. In Figure 3, this simple
Variable Flow Considerations approach reduces pumping costs while
Converting Constant-Flow Systems to providing the chiller with enough chilled
Variable Flow water, and it’s simple in retrofit applications
It may be benef icial to convert a whether there is a single chiller or multiple
constant-flow system to variable flow. chillers, since the three-way valves are part
Generally, the most economical way to do of the existing infrastructure.
so is by using the variable primary flow Be careful applying VPF to an existing
(VPF) concept, since a VSD can be ap- system with chillers differing in size, or
plied to the pump (provided the pump and chillers with differing evaporator pressure
drive are compatible). This article only drops. Flow variations may cause opera-
addresses a few issues with respect to tional issues, and sequencing and loading
applying VPF to existing systems. See the of chillers can be especially challenging.
references for more information.9,13,18 Variable Condenser Water Flow.
While there are many issues that should Some project teams consider varying con-
be considered, three are paramount with denser water flow to reduce system energy
respect to the chiller: use. This concept has been successfully
•• Confirm with the chiller manufac- implemented, but is not in widespread
turer that the existing unit controls use today. The difficulty is that varying
can tolerate variable evaporator condenser-water flow results in chiller and
flow. If not, consider a control cooling tower performance changes—and
retrofit. those changes are in opposite directions;
•• Provide system hardware and that is a reduction in cooling tower energy
controls that keep the evaporator and condenser water pumping energy re-
flow rate between the minimum sults in increased chiller power since the
and maximum allowed by the leaving condenser water temperature and
manufacturer. condenser refrigerant pressure both rise.
•• Ensure that system flow rate chang- So, implementation is difficult. While
es are below the threshold allowed several articles address varying flow rate
by the manufacturer. through the condenser and across the cool-
Many new VPF applications provide ing tower, few give specific implementa-
flow-sensing devices, and a separate by- tion guidance. Baker, et al.,11 provide a
Chiller kW
Variable primary flow is becoming a popular choice for new 200
systems, often due to reduced installed costs. Some system 150
owners also consider converting their existing primary-
100
secondary (P-S) systems to VPF. The operational savings
are related primarily to pump energy, but the savings are not 50
for the specific plant with help from the present operators. At first glance, the chiller operating at 50% load seems
While savings are hard to quantify, automated chiller plant almost twice as efficient as it is when operating at 100%
control frees building personnel to work on other building load. However, these ratings are also at two different enter-
components or tasks. However, there are control options that ing condenser-water temperatures (ECWT), making this an
save energy and operating cost. invalid comparison.
As discussed in the “Chiller Retrofit” section, a VSD reduces
Number of Chillers Operating chiller energy when compressor “lift” is reduced. During actual
An oft-asked question is whether it is more efficient to oper- chiller operation, the cooling towers provide the same water
ate two chillers at a lower load or a single chiller at a higher temperature. Therefore, a valid evaluation must compare chiller
load. This is likely in response to data supplied by all chiller kW at the same ECWT, whether one chiller is operating at 100%
manufacturers based on ARI 550/590-2003.1 load, or two chillers are operating at 50% load.
Table 2 shows full and part load data used to calculate So when is it beneficial to operate more than one chiller?
integrated part load value for the 600-ton (2110 k/W) chiller Figure 4 depicts a two-chiller plant with equally sized chillers.