Equipment Owner Type / Model

Manufacturer Serial
Manufacture Date Capacity / SWL
Reference Specification SWIM SEC.03 / BS EN13001 Standard Lifting Procedure

A R
Final Result
(A: Accept / R: Reject)

Item Inspection Criteria RESULTS


Pass Fail N/A Comments

1 General Requirements

1.1 Equipment documents are available


1.2 Previous inspection reports are checked
Serial number and Rated Load are clearly marked or
1.3
tagged
2 INSPECTION POINTS

Ensure eye is smooth and free from nicks, gouges


2.1 and any other defects that could act as stress raisers
Check Pad eye for wear, distortion, elongation, bent,
2.2 twisted, wear to the hole and signs of cracking
Check all welds and heat affected zones for signs of
2.3 cracking also weld profile for correctness
Check supporting steel work for signs of damage,
2.4
distortion and overloading
2.5 Cracks or undercut/overlap in welds
2.6 Hole is to be smooth enough

2.7 Bolts for tightness (if fitted)


Where the pad eye is part of a Rigging Arrangement,
2.8 ensure that the load applied is within the maximum
SWL of the pad eye

REMARKS