Professional Documents
Culture Documents
Authored By:
Triveni Prasad Nanda
Assistant Professor
What is procurement?
► Speed
► Cost
► Quality
► Risk
► Asset Ownership
► Financing
Procurement steps
► Identification of Need
► Supplier Identification
► Supplier Communication
► Negotiation
► Supplier Liaison
► Logistics Management
► Tender notification
Framework of Construction Procurement Process
Purchase Order
► A purchase order is a binding
contract between the construction
organization and the supplying
organization. It serves as an offer
to the supplying organization that
is accepted once the supplier signs
the actual purchase order.
Procurement Plan
• Identify relative importance of client’s primary objectives & his attitude towards associated risk.
Understanding:
• How much he is capable and willing to spend?
• What quality he is seeking?
• What time he wants the project to be completed?
► Construction Management
► This method is as old as the construction industry. The major feature is that
the design process is separate from construction.
► Requires full documentation before the contractor can be invited to tender
the client may accept a later date to account for delays resulting from reasons
listed in the contract.
► The Design-Build approach gives the client a single point of contact.
However, the client commits to the cost of construction, as well as the
cost of design, much earlier than with the traditional approach. Whilst risk
is shifted to the contractor, it is important that design liability insurance is
maintained to cover that risk. Changes made by the client during design
can be expensive, because they affect the whole of the Design-Build
contract, rather than just the design team cost.
► Secondly, although the contract period is shortened, the process of
assessing the tenders, and selecting a contractor can be difficult due to the
fact that all the tenderers are working with different designs.
Pros of Design and Build procurement
► Client must deal with one firm and reduces the need to commit resources
and time to contracting designers and contractors separately
► Price certainty is obtained before construction commences as client‘s
programme will vary between bidders, and prices for the project will
be different for each design
► Client is required to commit to a concept design at an early stage and often
before the detailed designs are complete; and
► Design liability is limited to the standard contracts that are available
ANOTHER SPECIALIZED PROCUREMENT TYPE
► Used when project company wants the design done quickly due time constraints and
► Like EPC, but better initial design control with project client.
► Cons:
contractors
Management Contracting: Pros and Cons
► Pros
► Management team is involved at early stage
► Cons
packages contract
Construction Manager
► Client does not allocate risk and responsibility to single main contractor
► Client employs design team with construction manager (advisor)-fee based
► Little cost certainty-because trade contractors unknown till work is let out.
► Can be used for large complex projects where high deg of design
► DBT (Design-Build-Transfer)
► DBFOT (Design-Build-Finance-Own-Transfer)
models are being taken up more frequently now, where the public partner
pays a certain percentage of the total project cost up-front (in equal annual
instalments), thus easing the cash flow of the private partner.
THANK YOU
Thanks to Prof. Avinash Tandon, Ms. Deepti Shitoley and Brig. Vinod Nakra for their help.