INSPECTION REQUEST FOR PEST CONTROL

PROJECT : Inspection Date:

ADDRESS : Star Time:

Work Item : Finish Time:

Purpose of Inspection:
Contractor :

Type of Pest Location Tolerances Checking Method Materials Used

Notes:
Noted by : Mr. Liu Aden 30-Dec-99
Project Manager-Chinese Date

Received by :
Management Date
Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets.
All trades tasked to review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work
request does not relieve the contractor of its obligations under contract.
UEST FOR PEST CONTROL
Inspection Date:

Star Time:

Finish Time:

Purpose of Inspection:

Materials Used
hop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets.
ds and other preparations prior to the start of this requested work/s. Approval of this work
relieve the contractor of its obligations under contract.