Professional Documents
Culture Documents
Welcomes all
On 18th National Award for Excellence in
Energy Management 2017
Company Profile
Unit Profile
Plant Configuration and Flow diagram
List of ENCON Projects
Plant Performance over the years
Innovative Projects
Sustainability Initiatives
Methodology of Energy monitoring
Best practices/ Involvement of Employees
CSR initiatives
Awards & Accolades
Way forward
Saving
Achieved Saving Achieved
Energy Saving Projects (01 No.)
SN Electrical Thermal Energy
Energy (Rs. Lacs)
(Rs. Lacs)
Single ACW pump run against double ACW pump
operation for both TPP by throttling all I/L &
1 39.2
O/L valve of ACW line to each equipment to
optimum flow of ACW.
Optimization of service air and stoppage of one
2 Compressor (earlier running 02 compressor for 38.5
two Plants)
Stoppage of one PA fan of Boiler -2 by modifying
3 14.5
the start logic
Saving
Achieved Saving Achieved
Energy Saving Projects (06 Nos.)
SN Electrical Thermal Energy
Energy (Rs. Lacs)
(Rs. Lacs)
Boiler -1 ID draft optimized at -15mmWC against -
1 2.3 -
25mmWC
Running of one BFP up to 80 % load for Both
2 191.1 -
Plant
3 Reduction of LOI from 10.5 to 4.5% 45.2
Further optimization of Instrument air pressure
4 3.5 -
from 6.5 kg/sq.cm to 6.0 kg/sq.cm
Operation of Boiler at Lower Bed Height i.e.
5 87.1 -
Reduction by 50MMWC.
Start Using of Pet Coke as alternate fuel to
6 12.9
improve Boiler Efficiency of Both TPP
Sub Total 284.0 58.1
Sewagram Cement Works
Energy Savings Projects with No Investment Fy’16-17
Saving Saving
Achieved Achieved
Energy Saving Projects (14 Nos.)
SN Electrical Thermal
Energy Energy
(Rs. Lacs) (Rs. Lacs)
Boiler-1&2 efficiency increase by optimize excess
1 31
O2 in flue gas at 3.9 % against 4.5 %
DM plant operation running hour optimized at 5
2 1.4
hrs./5 days against 2 hrs./day
For Boiler -1 &2, Lime screw feeder stop due to pre
3 1.6
mixing of lime in Coal conveyor belt
Without
Investment
Rs. 5.54 Cr.
Total Saving-
Rs. 17.38 Cr.
+
With
Investment
Rs. 11.84 Cr.
4.00
3172 3.68
3040
Challenges
Non utilization of high LOI (Loss on ignition) fly ash in Cement Plant
Disposal of fly ash
Low boiler efficiency thus high Power generation cost
Fugitive dust emission, land contamination etc. while disposal
Losses
(Total Fly ash generated=86MT/Day)
Final Outcome
Saving Saving
Utilization of 100% of fly ash of Description (Rs. (Rs. Lac/
Lac/Day) Annum)
AFBC Boiler in Cement
Manufacturing Fuel 2.2 744
Improved AFBC Boiler efficiency
Ash
from 82.4% to 88.1% utilization 0.3 111
in cement
Elimination of Fugitive dust Aux.
0.01 3
emission by using the ash in Power
Cement Plant Lime
0.1 26
Stone
Reduced Auxiliary power
consumption by 246 kWh/day
Total Saving 2.6 884
Objectives:
Reduction in Power Generation cost.
Conservation of Natural resources i.e. Coal/Lignite
Problem /Background:
Boilers were designed on Lignite/Imported Coal as a
performance fuel.
Available coal cost Rs/MCV is higher compare to Petcoke.
Available Lignite coal having high moisture about 25 to 35 %
which reducing boiler efficiency.
During firing of Petcoke facing issue of Volatile matters & ash
content
SO2 emission was limiting the Petcoke Consumption.
Analysis:
Initiated Brain storming and no. of suggestion identified. One suggestion was
pre mixing of crushed lime stone in coal at belt to improve VM (due to 30%
LOI in Lime) and ash content which interns reduction in GCV of Mixed fuel.
Modification:
Erected one new discharge chute (size 20’’) with manual isolation gate from
Lime screen discharge chute which divert lime stone in coal feeding
conveyor belt.
Results :
Productivity- Increased Boiler Efficiency and safe operation.
Innovation- Now we are transferring the Petcoke with lime stone from
common belt conveyor.
Approach:
Data
Brain Idea Collection Project on
Storming Generation and LOI
analysis
High Fly
ash LOI
Training
2 Improper Air Flow Optimized the air flow ratios i.e. Primary
air Vs secondary air Vs tertiary air
4 Low retention time due to Discussed with OEM and optimized the
High furnace draft furnace draft in between -10 to -15
(-25 to -35 mmWC) mmWC)
5 Engineers were not aware Analysis started on shift basis twice and
about LOI of their shift training given to them
LOI Trend
11%
9%
7%
5%
3%
1%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31
September-2016 October-2016 November-2016
Results :
Reduction in Fly ash LOI by 7%
Increment in Boiler Efficiency by 1.8%
Saving of Rs. 45.2 Lacs
Utilization of 100% fly ash in Cement Plant
Sewagram Cement Works
Project - 4 # Optimize Operation of BFP pumps
Analysis - Boiler Load increased beyond 55 % load with single Boiler Feed Pump
and check its Motor KW, Full load current, pump parameter & pump curve and
stabilize single BFP up to 80% Boiler load and starting 2nd BFP above 80 % load.
500
0
2014-15 Target SEC for PAT-2 cycle 2015-16 2016-17
(Baseline Year) (04/16 to 03/19)
Lawn
Developed
50418
(SQF)
2000
7722
Tree
6241
Plantation
(Nos.)
3410
FY’16 FY’17
143 18 84 91 164 29 103 38
470 282
945 55
182 808
187
238 13
69 Total 2240 Kl/day Total 1679 Kl/day
CSR Desal
CSR Desal
Drinking+ Service Civil
Drinking+ Service Civil
TPP Fire + Hort. TPP Fire + Hort.
Clinkerisation Cement mills Clinkerisation Cement mills
DG DG
4.8
Employee recognition
ISO 14001:2015
ISO 9001:2015
AFBC boiler converted into CFBC boiler to reduce fly ash LOI
Idea
Extent of man-power Progress of
SN EnCon idea * originated
involved *** implementation
in FY **
Bed ash handling of AFBC Boiler through Primary Air fan in place of
Compressed air shared with M/s ISGEC
Provision of MCB before signal isolator in VFD shared with M/s ABB
Corporate CSR
CSR Vision
CSR Policy
Education
Focus Area
Social Causes Health Care
Infrastructure Sustainable
Development Livelihood