Professional Documents
Culture Documents
Access to this document was granted through an Emerald subscription provided by emerald-
srm:573577 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald
for Authors service information about how to choose which publication to write for and submission
guidelines are available for all. Please visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company
manages a portfolio of more than 290 journals and over 2,350 books and book series volumes, as
well as providing an extensive range of online products and additional customer resources and
services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the
Committee on Publication Ethics (COPE) and also works with Portico and the LOCKSS initiative for
digital archive preservation.
Abstract
Purpose – Demand–supply matrices with adverse consequences has occasioned government
response to concession initiatives in infrastructure in Nigeria. However, concession-based projects have
been trailed by administrative and legal controversies. While this scenario has negatively impacted the
acceptability of a concession contract, there is, nevertheless, a paucity of research effort aimed at
developing a sustainable framework. The purpose of this paper is to develop a conceptual framework
for the evaluation and allocation of obligations of parties, thereby enhancing the synergy and
cooperation between the public and private sector organization.
Design/methodology/approach – Data were obtained through a questionnaire administered to
professionals in concession-based contracts in southwestern Nigeria, which included architects, estate
surveyors, quantity surveyors, engineers and builders, accountants/bankers/economists and lawyers.
The respondents were selected using random and respondent driven sampling approaches. The
questions were structured to ensure that the respondents have appropriate experience in
concession-based projects and hold appropriate positions as decision-makers so as to give credence to
the collected data.
Findings – The study identified 47 contractual obligations in the specific context of developing
countries. Based on “half-adjusting principle”, 13 of the obligations notably cost of land acquisition and
cost of social disturbances were allocated to the public party; 18 of the obligations notably project design
and cost of feasibility study were allocated to the private party; and 16 of the obligations including
preparation of terms of a contract and relocation of third party facilities were shared by the parties.
Originality/value – The framework benchmarked the categorization of public and private parties’
obligations in concession-based public–private partnership (PPP) contracts. The study has the
implication for the evaluation and allocation of obligations of parties, which could mitigate the risk of
failure of PPP projects in relation to the specific context of developing countries.
Keywords Infrastructure, Concession, Obligations, Public party, Private party
Paper type Research paper
Introduction
Concession-based projects constitute a segment of infrastructure that is of high capital
outlay, essentially procured through partnership. The arrangement is usually between
Journal of Place Management and
the public sector organizations and private investors (often referred to as parties, Development
Akbiyikli, 2013) for the purpose of designing, planning, financing, constructing, Vol. 9 No. 1, 2016
pp. 27-46
providing and/or operating infrastructure facilities or related services (Harris, 2003). © Emerald Group Publishing Limited
1753-8335
Infrastructure development through concession is much supported to have originated DOI 10.1108/JPMD-08-2015-0029
JPMD from the UK in 1992, though similar models were argued to have been experimented in
9,1 other countries and in the UK before this time (Kerf et al., 1998; Ohia, 2011; Akbiyikli,
2013). In a concession arrangement, project design, construction, financing and
operation rests mainly with the private sector over a pre-determined period of 25 to 30
years (Akintoye et al., 2003; Li et al., 2005). Recently, the concept of concession has
attracted worldwide attention and acquired a new resonance in the context of
28 developing countries as an innovative policy tool for remedying the lack of dynamism in
traditional public infrastructure delivery system (Jamali, 2004). Nigeria, according to
Global Legal Group (2007) and Ohia (2011), would require about N30 trillion invested at
$12b to $15b (N2.4 trillion to N3.0 trillion) annually for the next 10 years to meet the
satisfactory infrastructure requirements of the economy. Given the constraints on the
public budget, it is evident that governments alone cannot muster the resources to meet
this need, thus making private sector investment highly desirable.
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
Until 2006, when the first set of concession-based projects were launched in Nigeria,
infrastructure development in the country was dependent significantly on the public
financing models. The poor performance of the budgetary model had, therefore, left the
country with deep infrastructure demand–supply gap with adverse socio-economic
consequences. While concession innovation was adopted as a remedy tool, most of the
projects that were launched since this period had failed, and the reasons for the failure
had been attributed in greater part to ill-definition of obligations of the private party and
public sector organization in the transaction. For example, the proposed Lagos–Ibadan
concession road project witnessed little progress for upward of three years after it was
signed and before it was eventually terminated in December 2012 by the public party
(Agande, 2012). Similar underperformance experience occurred in Murtala Mohammed
Airport II (MMA2) concession projects, which occasioned renegotiation that had been
challenged as skewed toward the public party’s interest (Oduah, 2012). Mass protest by
users against tariff payment was experienced on Lekki–Epe road project, which
dragged the commencement of tolling by the private investor for one year after
September 2010, the agreed commencement date (Sanni, 2012). Most importantly, the
project had been under debate for nationalization since 2012.
In the traditional Design-Bid-Build (DBB) models, country-based Standard Form of
Contracts and International Standards, such as Joint Contractual Tribunal (JCT),
Federation International of Civil Engineers (FIDIC), New Engineering Contract (NEC),
among others, have been adopted in Nigeria, which provide a frameworks that define
parties’ obligations and protect the parties’ interests at all stages of the contracts. Such
frameworks embody contractual terms defining the parties’ obligations at both the
pre-contract and post-contract stages and clauses for enforcement of liabilities relating
to non-performance, delay in progress of performance, contract cancellation and
determination, among others. These frameworks have been very significant to
successful project delivery and avoidance of opportunity tendencies among parties.
Presently, the administration of concession-based projects in Nigeria is bedeviled by
varying challenges, particularly with respect to the definition of parties’ obligations.
Most often, these obligations are ill-defined and lack appropriate mechanisms for
enforcement, giving rise to protracted litigation (Sanni, 2012). While the resultant
scenarios, mostly, contract re-negotiation and cancellation, have negatively impacted
the popular acceptance of concession contracts in Nigeria, research efforts in the domain
of administration of parties’ obligations have been very limited. Besides the poor
performance of traditional (budgetary) financing of public infrastructure, which had Concession-
created a wide demand–supply gap, the adoption of public–private partnership (PPP) based PPP
model has been identified to be on the increase in Nigeria since 2006 (Akinsiku et al.,
2014). However, the administrative and legal controversies with respect to delineation of
projects in
contractual obligations has necessitated the development of a framework that will Nigeria
ensure synergy and cooperation between the public sector and private sector investor in
the delivery of concession-based PPP projects. Therefore, the consideration of the study 29
from the Nigerian experience is justified on the embryonic stage of PPP and
experimentation with sizeable number of ongoing PPP projects.
1998). Other variants are described as mixed companies and are differentiated by the
extent of financial resources commitment or other inputs of the public party. Unlike the
traditional DBB model of infrastructure delivery, the concession model involves
expanded stakeholders/participants domain (Marques and Berg, 2010). According to
Button (2002), the number of project participants depends largely on the project
complexity and specification. The generic structure of concession essentially comprises
the public party (referred to as the principal) and the private investor (often referred to as
the concessionaire). The public party is the client/employer and the private party is the
executor/contractor when making a comparison with the traditional procurement
model. Other stakeholders involved in a concession contract include the financing
institutions, legal agency, operators, sub-contractor and suppliers. Central to the
concession contract administration is the concession period, which is the period during
which the concessionaire owns the property right of the projects. This period, usually
25-30 years, has been established by a number of studies (Li et al., 2005; Zou et al., 2008).
The public sector is the party who draws up the lists of infrastructure investment in
accordance to the national economic development plans. The primary obligation of the
public party is to provide an institutional framework that makes the project viable and
attractive to the private party (Kerf et al., 1998). The private sector/concessionaire, on
the other hand, is the party that is responsible for finance, operation and transfer of the
facility to the public sector at the expiration of the concession period (Rajan et al., 2010;
Jin et al., 2012). Moreover, the concessionaire retains the property right of the facility
until the expiration of the concession period during which he recovers his investment
and profit. The public party becomes contractually eligible to the facility and ownership
after the concession period.
The financial institutions are organizations solely involved as equity investors (Jin
et al., 2012). These include banks, insurance companies and multi-lateral agencies (Kerf
et al., 1998). The private party is not necessarily the contractor/operator in a concession
contract where the private investor (as a person) does not have the expertise. In this case,
the contractor undertakes the construction stage as a separate company by way of a
business venture. The same justification is applicable to the operator who may be
engaged by the private investor for the post-construction operation of the facility up to
the specified concession period. This arrangement has often necessitated the
establishment of a special purpose vehicle (SPV) in a concession contract (Kerf et al.,
1998; Grimsey and Lewis, 2002; Asenova and Beck, 2003; Oyegoke, 2005; Wilson et al.,
2010). The consultants’ obligations in a concession contract are essentially project
JPMD design and construction based on concessionaire engagement. Other participants/
9,1 stakeholders (consultants, financiers, insurers, legal agents, sub-contractors and
suppliers) in a concession contract other than the public party are aggregated to a
singular outlet in a specific project administration. These are referred to as SPV (Kerf
et al., 1998). The SPV is usually a consortium or company established solely by the
private partner or jointly with the public agency for the purpose of project
30 implementation (Asenova and Beck, 2003; Grimsey and Lewis, 2004).
Gray and Larson (2003) and Wilson et al. (2010) have identified nine stages in
infrastructure delivery process. These are project inception, project definition, concept
development, design, document, procurement, construction, commissioning and
operation. In the traditional procurement models, the international standards (JCT,
FIDIC, NEC, among others) and country-specific standards form of contracts define the
obligations of the parties and liabilities for non-performance at each of these stages. In
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
however, the execution stage is been trailed by a number of challenges, which are having
a negative impact on the popular acceptance of the PPP model. The wide range of
challenges that have trailed the projects have attracted empirical researches on PPP
transactions, however, with limited focus on categorization of parties’ obligations.
Architect 18 14 17.3
Quantity surveyor 18 16 19.8
Engineer 18 17 21.0
Estate surveyor 18 11 13.6
Builder/project manager 18 7 8.6
Lawyer 12 9 11.1 Table II.
Economist/financial/manager/banker 12 7 8.6 Type of respondents
0-5 15 18.5
6-10 23 28.4
11-15 15 18.5
16-20 14 17.3 Table IV.
21-25 10 12.3 Years of work
Above 25 4 4.9 experience
JPMD Affiliation Frequency (%)
9,1
NIA 22 30.6
NIQS 16 22.2
NSE 11 15.3
NIOB 4 5.6
34 NIESV 11 15.3
CIB 5 6.9
NBA 7 9.7
Others 16 22.4
Total 81 100.0
Table V. Notes: NIA ⫽ Nigerian Institute of Architects; NIQS ⫽ Nigerian Institute of Quantity Surveyors; NSE ⫽
Professional Nigerian Society of Engineers; NIOB ⫽ Nigerian Institute of Building; NIESV ⫽ Nigerian institute of estate
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
affiliation surveyors and valuers; CIB ⫽ Chartered Institute of Banking; NBA ⫽ Nigerian Bar Association
0-5 38 46.9
6-10 27 33.3
Table VI. 11-15 1 1.2
Number of Over 15 3 3.7
PPP/concession No response 12 14.8
projects undertaken Total 81 100.0
Transportation 21
Water infrastructure 10
Power project 23
Table VII. Housing infrastructure 57
Participation of the Commercial/market project 26
respondents in Communication 7
alliance contracts Marine infrastructure 4
responses were from the public sector organizations (48.1 per cent), which were lower
than the 42 responses (51.9 per cent) obtained from the private sectors organizations.
Analysis of the coverage of the operations of the respondents’ organization (Table I)
showed that 35.8 per cent of the organizations operated only within their state, and16.0
per cent had operated within their geo-political zones, while 21.0 per cent and 27.2 per
cent had operated at the national and international levels, respectively. The aggregate of
64.2 per cent of respondents’ organizations who had operated beyond the shores of their
state revealed the positions of the respondents to provide information on national scope
coupled with international experience on alliance contract.
The distribution of the respondents (Table II) showed that architects involved in the
study represented 17.3 per cent of the respondents, while 19.8 per cent were quantity
surveyors. Moreover, engineers were 21.0 per cent, and 13.6 per cent of the respondents Concession-
were builders/project managers. Each of the estate surveyors and economist/financial based PPP
manager/banker involved represented 8.6 per cent, while the lawyers represented 11.1
per cent. These results showed that the respondents covered construction professionals,
projects in
financial administrators and legal practitioners who are significant infrastructure Nigeria
stakeholders who could provide adequate assessment of a concession contract in the
study area. 35
In Table III, the academic qualifications of the respondents showed that the
respondents that held a bachelor’s degree were 28.4 per cent of the sample. The highest
numbers of the respondents were those with a master’s degree and represented 45.7 per
cent of the respondents. Furthermore, 13.6 per cent obtained their post graduate diploma
and 12.3 per cent their higher national diploma. Based on these academic qualifications,
the respondents were deemed to possess adequate academic training to supply reliable
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
9,1
36
projects
JPMD
Table VIII.
concession-based
obligations of public
Categorization of the
1 Funding of the feasibility study of the project 3.70 6.27 ⫺4.527 0.001 0.337 0.114 3.70 6.27 Private
2 Funding of the sensitization of the users 6.11 3.90 4.186 0.001 0.314 0.099 6.11 3.90 Public
3 Funding of the planning approval for the project 5.00 5.00 0.000 1.000 0.000 0.000 5.00 5.00 Shared
4 Cost associated with community liaison in the 5.94 4.11 3.390 0.001 0.259 0.067 5.94 4.11 Public
project domain
5 Charges and costs of land acquisition and usage 7.93 2.05 12.165 0.001 0.693 0.480 7.93 2.05 Public
6 Monetary compensation associated with land 7.63 2.37 10.597 0.001 0.642 0.412 7.63 2.37 Public
acquisition and usage
7 Cost associated with contamination at the site 3.44 6.56 ⫺5.984 0.001 0.428 0.183 3.44 6.56 Private
resulting from project activities
8 Cost of supportive infrastructure 5.65 4.47 2.367 0.019 0.184 0.034 5.65 4.47 Public
9 Cost of site encumbrances 4.48 5.52 ⫺2.112 0.036 0.165 0.027 4.48 5.52 Shared
10 Cost associated with social disturbances– 7.43 2.58 9.954 0.001 0.618 0.382 7.43 2.58 Public
resettlement and rehabilitation of the people
affected by the project
11 Cost associated with treatment of fossils and 5.21 4.79 0.771 0.442 0.061 0.004 5.19 4.81 Shared
antiquities if found on project site
12 Environmental impact assessment of the project 4.36 5.64 ⫺2.115 0.036 0.165 0.027 4.36 5.64 Private
13 Ecological impact assessment of the project 5.05 4.99 0.021 0.983 0.002 0.000 5.05 4.99 Shared
14 Assessment and relocation of statutory facilities, 6.56 3.47 5.511 0.001 0.399 0.160 6.56 3.47 Public
e.g. oil pipeline and PHCN facilities
15 Assessment and relocation of third party 5.33 4.67 1.204 0.230 0.095 0.009 5.33 4.71 Shared
facilities, e.g. telecommunication facilities
16 Cost of assessing shadow tariff structure 4.99 5.01 ⫺0.116 0.907 0.009 0.000 4.99 5.01 Shared
17 Cost of demand survey 3.68 6.33 ⫺4.461 0.001 0.333 0.111 3.68 6.33 Private
18 Cost of preliminary design 2.91 6.99 ⫺7.047 0.001 0.487 0.237 2.91 6.99 Private
19 Cost of geotechnical investigations 3.26 6.74 ⫺6.377 0.001 0.450 0.203 3.26 6.74 Private
20 Cost of detail designs 2.69 7.35 ⫺9.062 0.001 0.582 0.339 2.69 7.35 Private
21 Preparation of contract documentations 4.37 5.69 ⫺2.398 0.018 0.186 0.035 4.50 5.69 Shared
22 Specification of the facility’s construction and 4.73 4.27 ⫺2.961 0.004 0.228 0.052 4.27 5.73 Public
operation
23 Cost of bid transaction and documentation 3.58 6.47 ⫺5.340 0.001 0.389 0.151 3.58 6.47 Private
(continued)
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
24 Preparation of conditions/terms of the contract 5.56 4.51 1.863 0.064 0.146 0.021 5.56 4.60 Shared
25 Definition of obligations and liabilities for 5.48 4.63 1.909 0.058 0.149 0.022 5.48 4.73 Shared
default by parties
26 Cost of engagement of independent consultants 4.49 5.51 ⫺2.012 0.046 0.157 0.025 4.60 5.51 Shared
27 Cost of establishment of project governance 5.15 4.85 0.378 0.706 0.030 0.001 5.15 4.85 Shared
structure
28 Preparation of financing plan and 2.91 7.09 ⫺9.928 0.001 0.617 0.381 2.91 7.09 Private
documentation
29 Securing of bank guarantee 2.72 7.26 ⫺9.565 0.001 0.603 0.364 2.72 7.26 Private
30 Securing of performance bond 2.49 7.51 ⫺11.120 0.001 0.660 0.436 2.49 7.51 Private
31 Consumer demand guarantee 4.19 5.84 ⫺3.073 0.002 0.236 0.056 5.48 4.19 Public
32 Warrantees to comply with the contract term 3.79 6.21 ⫺4.726 0.001 0.350 0.122 3.79 6.21 Private
33 Guarantees 7.94 2.06 ⫺13.492 0.001 0.730 0.532 7.94 2.06 Public
34 Insurance against third party claims 2.70 7.30 ⫺9.794 0.001 0.612 0.375 2.70 7.30 Private
35 Insurance against breach of statutory duty 3.60 6.40 ⫺5.430 0.001 0.394 0.156 3.60 6.40 Private
36 Property/asset/material/component damage 2.31 7.69 ⫺12.167 0.001 0.693 0.481 2.31 7.69 Private
insurance
37 Insurance against death and personal injury 1.79 8.21 ⫺16.620 0.001 0.796 0.633 1.79 8.21 Private
38 Indemnity insurance 2.41 7.59 ⫺11.272 0.001 0.665 0.443 2.41 7.59 Private
39 Insurance against nationalization of the project 4.86 5.14 ⫺0.445 0.657 0.035 0.001 4.86 5.14 Shared
40 Formulation of legal and regulatory framework 5.98 4.02 4.138 0.001 0.311 0.097 5.98 4.02 Public
41 Cost of legal documentation 4.26 5.74 ⫺2.893 0.004 0.223 0.050 4.26 5.74 Private
42 Regulation of supply of 6.22 3.78 ⫺4.250 0.001 0.318 0.101 6.22 3.78 Public
material/labor/component
43 Mitigation of foreign currency restrictions 6.89 3.11 7.712 0.001 0.521 0.271 6.89 3.11 Public
44 Cost of project monitoring and evaluation 5.19 4.81 0.768 0.444 0.061 0.004 5.19 4.85 Shared
45 Documentation of step-in right 5.37 4.63 1.825 0.070 0.143 0.020 5.37 4.72 Shared
46 Determination of toll points 5.33 4.67 1.642 0.103 0.129 0.017 5.33 4.75 Shared
47 Determination of tariff structure 5.59 4.41 2.852 0.005 0.220 0.048 5.59 4.62 shared
Notes: ⫽ Eta squared correlation co-efficient; actual mean (MAC); adjusted mean (MADJ); ⫽ significance threshold; ⫽ 0.000 ⱕ ⱕ 0.450
Table VIII.
37
Nigeria
projects in
based PPP
Concession-
JPMD obligations in the 47 obligations identified from literature and those peculiar to the
9,1 Nigerian environment on a scale involving ratings between 0 and10, where 0 represents
lowest rating and 10 representing highest rating. These were used to compute the mean
ranking (MAC) for each of the identified obligations. The degree of concordance (0.000 ⱕ
ⱕ 0.450) in the rating amongst the respondents from the two parties’ organizations
revealed a low agreement. The low concordance could be explained in part to
38 contrasting interests of the parties, which the participants from the organization stand
to protect. The private sector organization is undertaking a concession transaction as a
business venture to maximize profits on investment, whereas the public party
organization is interested in the transaction to take the advantage of the finance and
technical expertise of the private party to deliver projects, which otherwise would have
been delivered by its limited resources. On the other hand, the ratings could have been
influenced by bias and inexperience as concession contracts had not been extensively
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
practiced in Nigeria for sufficient skills of the participants on some issues related to the
innovation. The low ratings, however, necessitated the test of the degree of dispersion of
the rating both among the respondents from different parties and within a party group.
This was achieved through eta squared coefficient of correlation and Mann–Whitney U
test. The correlation coefficients obtained were used to adjust the calculated mean for
each obligation to obtain an adjusted mean (MADJ). The allocation of the obligations to
either the public or private party was based on the MADJ on half adjusting principle
earlier discussed by Ke et al. (2010). The Ke et al. (2010) half adjusting principle was
adopted in developing risk allocation framework in alliances contracting and presented
the risk allocation as mean values (MAC) of participants’ responses. In all, three risk
allocation criteria were identified according to the principle. These were risks with a
mean score smaller than 2.5 allocated to the public party; risks with a mean score greater
than or equal to 2.5 and smaller than 3.5 equally shared by both parties; and risks with
a mean score greater than or equal to 3.5 allocated to the private party.
The assessment in Ke et al. (2010) was based on a 1-5-scale rating and because the
assessment in this study is on a 1-10 rating, the adjusting principle was modified to a
10-point scale. In this regard, the mean score for the obligations were compared in each
case and the allocation procedure was allocating an obligation to the public party where
the approximate mean value of the private party is less than 5.0; allocating an obligation
to the private party where the approximate mean value of the public party is less than
5.0; and obligation where both parties scored mean value approximated to 5.0 was
classified as shared. The allocation was based on calculated MAC adjusted by coefficient
of dispersion () to MADJ values. The values at the significance level of 5 per cent of
Mann–Whitney U test were used as the criterion for the application of the adjustment
coefficient. Obligations with mean value greater than 5.00 on a scale of 10 were allocated
to public party where the Mann–Whitney U test is significant at 5 per cent, otherwise the
MAC below respective threshold was adjusted by the corresponding coefficient of eta
square. The eta squared correlation tends toward zero when the mean value of an
obligation for public party and private party tends equality. In this regard, where the
significance coefficient is greater than the threshold of 0.05, the value of the lesser mean
is adjusted by the corresponding eta correlation (). The significance threshold became
perfectly insignificant at 1.000. At these points, zero adjustment coefficient was revealed
by the eta square () adjustment on the estimated mean MAC, and the estimated MAC
was expected to be equitably 5.00 to both the public party and private party. The
allocation formula at this threshold is an equitable sharing of the obligation at half-half. Concession-
This is an absolute situation of half adjusting principle. based PPP
These situations were obtained in obligations like funding of planning approval
(0.000), ecological impact assessment (0.000) and cost of assessing shadow tariff
projects in
structure (0.000). In these situations, the estimated MAC needed no adjustment as the Nigeria
multiplication of the estimated MAC and the eta square ( ⫽ 0.000) produced zero
values. On the other hand, the MADJ values for other obligations are revealed in 39
Table III. Based on the allocation criteria and the adjustment procedure discussed
above, obligations of sensitization of users, cost associated with community liaison,
charges and costs of land acquisition and usage and compensation associated with
land acquisition and usage were allocated to the public party. Other obligations that
were allocated to the public party are provision of supportive infrastructure, cost
associated with social disturbances (resettlement and rehabilitation of the people
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
party to undertake the design, construction and charge the tolls was allocated to the
public party in agreement with Hannah (2008). This is agreeable as the public party is
the custodian of the instrument of law.
Obligations of feasibility study, cost associated with site contamination,
environmental impact assessment, demand survey, preliminary design, geotechnical
investigations, detail designs, specification of the facility’s construction and
operation, cost of bid transaction and documentation, preparation of financing plan
and documentation, performance bond, warranties to comply with the contract term,
insurance, legal documentation were allocated to the private party. The allocation of
obligation of feasibility study to the private party agreed with findings of Shaw et al.
(1996), Wamuziri and Clearie (2005), Zou et al. (2008), Wilson et al. (2010) and Singh
and Kalidindi (2009) that the private party conducts feasibility studies of proposed
solutions as part of bid preparation requirements. The findings on allocation of
obligation of feasibility study to the private party, however, disagreed with Voelker
et al. (2008) and Jingfeng et al. (2009) submission on the allocation of obligations
feasibility to the public party in PPP transactions. The finding on allocating
environmental impact assessment (EIA) to the private party agreed with the finding
of Wamuziri and Clearie (2005) who considered EIA by the private party as part of
project viability assessment.
The finding on allocation of design obligations is in concordance with findings of
Askar and Gab-Allah (2002), Zhang (2004), Hannah (2008), Shaoul et al. (2010) and
Mouraviev and Kakabadse (2012) who attributed the cost of preliminary design and
detailed design to the role of a private party. Considering the private party’
comparative advantage of technical expertise, this is agreeable as it will ensure
quality design and saving of effort and resources at the construction stage of the
project. Moreover, the designers would be able to translate the design expertise to
the on-site operation, rather than having to work on designs by consultants of public
party. Allocating the assessment of ground conditions, geotechnical and
topographical surveys to the private party is worthwhile as soil properties are
unknown to the project team and unexpected finds/discovery and contamination are
capable of delaying the project progress or lead to increased costs to the private
party as earlier asserted by Wamuziri and Clearie (2005) and Fischer et al. (2010).
Allocating the obligation associated with site contamination agreed with the
findings of Love et al. (2000) that contamination is a risk at the developmental phase
that should be undertaken by the private party. Its allocation to the private party is Concession-
further justified because public party may not necessarily anticipate this and may based PPP
not consider it in the bid preparation. The findings on provision of performance
bonds by the private party agreed with the position of Kerf et al. (1998) that the
projects in
instrument of performance bonds and insurance cover to lower the risks of Nigeria
non-compliance should be provided by the private party. This position is acceptable
because these risks are unavoidable risks of doing business, and they could be better 41
borne by the private party, who can obtain some protection by taking out insurance.
Obligations that were found to be shared between the public and private parties were
cost of site encumbrances, cost associated with treatment of fossils and antiquities,
ecological impact assessment of project, assessment and relocation of third party
facilities (e.g. telecommunication facilities), cost of assessing shadow tariff structure and
preparation of contract documentations. Other obligations that were found to be shared
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
References
Abednego, M.P. and Ogunlana, S.O. (2006), “Good project governance for proper risk allocation in
public-private partnerships in Indonesia”, International Journal of Project Management,
Vol. 24 No. 7, pp. 22-34.
Adegoke, O.J., Olaleye, A. and Araloyin, F.M. (2010), “An examination of the need for public Concession-
private partnership in the provision of urban infrastructure in lagos metropolis”, IFE
Journal of Environmental Design and Management, Vol. 4 No. 1, pp. 76-109.
based PPP
Agande, B. (2012), “FG terminates Lagos-Ibadan Expressway contract”, The Vanguard, available
projects in
at: www.vanguardngr.com/2012/11/fg (accessed 6 July 2013). Nigeria
Akbiyikli, R. (2013), “Performance assessment of a private finance initiative road project”,
Transport, Vol. 28 No. 1, pp. 11-24. 43
Akinsiku, O.E., Babatunde, S.O. and Opawole, A. (2014), “Adoption of public-private partnerships
(PPP) procurement method on infrastructure delivery in Nigeria”, Journal of the Nigerian
Institute of Quantity Surveyors, Vol. 58, pp. 3-12.
Akintoye, A., Hardcastle. C. Beck, M., Chinyio, E. and Asenova, D. (2003), “Achieving best value
in private finance initiative project procurement”, Construction Management and
Economics, Vol. 21, pp. 461-470.
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
Asenova, D. and Beck, M. (2003), “The UK financial sector and risk management in PFI projects:
a survey”, Public Money & Management, Vol. 23 No. 3, pp. 195-203.
Askar, M.M. and Gab-Allah, A.A. (2002), “Problems facing parties involved in build, operate, and
transport projects in Egypt”, Journal of Management in Engineering, Vol. 18 No. 4,
pp. 173-178.
Babatunde, S.O., Opawole, A. and Akinsiku, E.O. (2012), “Critical success factors in public-private
partnership (PPP) on infrastructure delivery in Nigeria”, Journal of Facilities Management,
Vol. 10 No. 3, pp. 212-225.
Babatunde, S.O., Perera, S. and Lei Zhou, L. (2016), “Methodology for developing capability
maturity levels for PPP stakeholder organisations using critical success factors”,
Construction Innovation, Vol. 16 No. 1, pp. 81-110.
Babatunde, S.O., Perera, S., Lei Zhou, L. and Chika Udeaja, C. (2015), “Barriers to public private
partnership projects in developing countries”, Engineering, Construction and Architectural
Management, Vol. 22 No. 6, pp. 669-691.
Boudet, H.S., Jayasundera, D.C. and Davis, J. (2011), “Drivers of conflict in developing country
infrastructure projects: experience from the water and pipeline sectors”, Journal of
Construction Engineering and Management, Vol. 137 No. 7, pp. 498-511.
Button, K. (2002), “Effective infrastructure policies to foster integrated economic development”,
available at: www.uneca.org/adfiii/docs (accessed 30 January 2013).
Cheung, E. Chan, A.P.C. and Kajewski, S. (2010), “The researcher’s perspective on procuring
public works projects”, Structural Survey, Vol. 28 No. 4, pp. 300-313.
Famakin, I.O., Aje, I.O. and Ogunsemi, D.R. (2012), “Assessment of success factors for joint
venture construction projects in Nigeria”, Journal of Financial Management of Property
and Construction, Vol. 17 No. 2, pp. 153-165.
Fischer, K., Leidel, K., Riemann, A. and Alfen, H.W. (2010), “An integrated risk management
system (IRMS) for PPP projects”, Journal of Financial Management of Property and
Construction, Vol. 15 No. 3, pp. 260-282.
Global Legal Group (2007), “The international comparative legal guide to PFI/PPP projects, a
practical insight to cross-border PFI/PPP projects work”, available at: www.iclg.co.uk/
khadmin/Publications/pdf/1027.pdf (accessed 17 December 2010).
Goodrum, P.M., Wan, Y. and Fenouil, P.C. (2009), “A decision-making system for accelerating
roadway construction”, Engineering, Construction and Architectural Management, Vol. 16
No. 2, pp. 116-135.
JPMD Gray, C.G. and Larson, E.W. (2003), Project Management-The Managerial Process, McGraw – Hill
Irwin Publisher, New York, NY.
9,1
Grimsey, D. and Lewis, M.K. (2002), “Evaluating the risks of public private partnerships for
infrastructure projects”, International Journal of Project Management, Vol. 20, pp. 107-118.
Hannah, G. (2008), “Developments in the public-private partnership funding of Scottish schools”,
Journal of Applied Accounting Research, Vol. 9 No. 2, pp. 112-125.
44 Ibrahim, A.D., Price, A.D.F. and Dainty, A.R.J. (2006), “The analysis and allocation of risks in
public private partnerships in infrastructure projects in Nigeria”, Journal of Financial
Management of Property and Construction, Vol. 11 No. 3, pp. 149-164.
Irwin, T., Klein, M., Perry, G.E. and Thobani, M. (1999), “Managing government exposure to
private infrastructure risks”, The World Bank Research Observer, Vol. 14 No. 2, pp. 229-245.
Jamali, D. (2004), “Success and failure mechanisms of public private partnerships (PPPs) in
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
developing countries: insights from the Lebanese context”, International Journal of Public
Sector Management, Vol. 17 No. 5, pp. 414-430.
Jin, X., Zhang, G. and Yang, R.J. (2012), “Factor analysis of partners’ commitment to risk
management in public-private partnership projects”, Construction Innovation:
Information, Process, Management, Vol. 12 No. 3, pp. 297-316.
Jingfeng, Y., Alex, Y.Z., Miroslaw, J.S. and Li, Q. (2009), “Selection of performance objectives and
key performance indicators in public–private partnership projects to achieve value for
money”, Construction Management and Economics, Vol. 27 No. 3, pp. 253-270.
Ke, Y., Wang, S. and Chan, A.P.C. (2010), “Equitable risks allocation of projects inside China:
analyses from Delphi survey studies”, Chinese Management Studies, Vol. 5 No. 3,
pp. 298-310.
Ke, Y., Wang, S., Chan, A.P.C. and Cheung, E. (2011), “Understanding the risks in China’s PPP
projects: ranking of their probability and consequence”, Engineering, Construction and
Architectural Management, Vol. 18 No. 5, pp. 481-496.
Kerf, M., Gray, R.D. and Taylor, R.R. (1998), “Concession for infrastructure: a guide to the design
and award”, World Bank Technical Paper No. 399, pp. 1-194.
Li, B., Akintoye, A., Edwards, P.J. and Hardcastle, C. (2005), “Critical success factors for PPP/PFI
projects in the UK construction industry”, Construction Management and Economics,
Vol. 23, pp. 459-471.
Love, P.E.D., Wood, B.M., Picken, D. and Confoy, B. (2000), “The privatisation of correctional
facilities in Australia”, Facilities, Vol. 18 No. 1, pp. 56-65.
Mahalingam, A. (2010), “PPP experiences in Indian cities: barriers, enablers and the way forward”,
Journal of Construction Engineering Management, Vol. 136 No. 4, pp. 419-429.
Marques, R. and Berg, S. (2010), “Revisiting the strengths and limitations of regulatory
contracts in infrastructure industries”, Journal of Infrastructural System, Vol. 16 No. 4,
pp. 334-342.
Mouraviev, N. and Kakabadse, N. (2012), “Conceptualising public-private partnerships: a critical
appraisal of approaches to meanings and forms”, Society and Business Review. Vol. 7 No. 3,
pp. 260-276.
Ng, A. and Loosemore, M. (2007), “Risk allocation in the private provision of public
infrastructure”, International Journal of Project Management, Vol. 25 No. 1, pp. 66-76.
Oduah, S. (2012), “Federal aviation authority Nigeria (FAAN) defies court”, Terminates Maevis
Concession, available at: www.thisdaylive.com/articles (accessed 3 June 2013).
Oghojafor, B.E.A., Kuye, O.L. and Alaneme, G.C. (2012), “Concession as a strategic tool for ports Concession-
efficiency: an assessment of the Nigerian ports”, American Journal of Business and
Management, Vol. 1 No. 4, pp. 214-222.
based PPP
Ohia, U. (2011), “Infrastructure concession in Nigeria: challenges and opportunities”, a paper
projects in
presented at the 5th National Diaspora Conference, Held at the Congress Hall, Transcorp Nigeria
Hilton Hotel, 25-27 Abuja.
Patrick, X.W., Wang, S.W. and Fang, D. (2008), “A life-cycle risk management framework for PPP 45
infrastructure projects”, Journal of Financial Management of Property and Construction,
Vol. 13 No. 2, pp. 123-142.
Quraeshi, Z.A. and Luqmani, M. (2011), “A framework for building competitive sectoral
capabilities in developing countries”, Competitiveness Review: An International Business
Journal Incorporating Journal of Global Competitiveness, Vol. 21 No. 1, pp. 47-65.
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
Rajan, A.T., Siddharth, R. and Mukund, S.P. (2010), “PPPs in road renovation and maintenance: a
case study of the East Coast road project”, Journal of Financial Management of Property
and Construction, Vol. 15 No. 1, pp. 21-40.
Sachs, T., Tiong, R. and Wang, S.Q. (2007), “Analysis of political risks and opportunities in public
private partnerships (PPP) in China and selected Asian countries: survey results”, Chinese
Management Studies, Vol. 1 No. 2, pp. 126-148.
Sanni, A.G. (2012), “Evaluation of risks associated with concession contracts in Lagos State,
Nigeria”, Unpublished MSc thesis, Department of Quantity Surveying, Obafemi Awolowo
University, Ile-Ife.
Shaoul, J., Stafford, A. and Stapleton, P. (2010), “Financial black holes: the disclosure and
transparency of privately financed roads in the UK”, Accounting, Auditing and
Accountability Journal, Vol. 23 No. 2, pp. 229-255.
Shaw, L.N., Gwilliam, K.M. and Thompson, L. (1996), “Concessions in transport”, World Bank
Report TWU-27, Environmentally Sustainable Development.
Singh, L.B. and Kalidindi, S.N. (2009), “Criteria influencing debt financing of Indian PPP road
projects: a case study”, Journal of Financial Management of Property and Construction,
Vol. 14 No. 1, pp. 34-60.
Voelker, C., Permana, A., Sachs, T. and Tiong, R. (2008), “Political risk perception in Indonesian
power projects”, Journal of Financial Management of Property and Construction, Vol. 13
No. 1, pp. 18-34.
Wamuziri, S.C. and Clearie, A.G.F. (2005), “Economic feasibility of the proposed second forth road
bridge using public private partnership procurement”, Journal of Financial Management of
Property and Construction, Vol. 10 No. 2, pp. 95-106.
Wilson, D.I., Pelham, N. and Duffield, C.F. (2010), “A review of Australian PPP governance
structures”, Journal of Financial Management of Property and Construction, Vol. 15 No. 3,
pp. 198-215.
Zhang, X. (2004), “Concessionaire selection: methods and criteria”, Journal of Construction
Engineering and Management, Vol. 130 No. 2, pp. 235-244.
Zhang, X.Q. and Kumaraswamy, M.M. (2001), “Hong Kong experience in managing BOT
projects”, Journal of Construction Engineering and Management, Vol. 127 No. 2,
pp. 154-162.
Zou, P.X.W., Wang, S. and Fang, D. (2008), “A life-cycle risk management framework for PPP
infrastructure projects”, Journal of Financial Management of Property and Construction,
Vol. 13 No. 2, pp. 123-142.
JPMD Further reading
9,1 Ankrah, N.A., Proverbs, D. and Debrah, Y. (2009), “Factors influencing the culture of a
construction project organisation: an empirical investigation”, Engineering, Construction
and Architectural Management, Vol. 16 No. 1, pp. 26-47.
Heravi, G. and Hajihosseini, Z. (2012), “Risk allocation in public–private partnership
infrastructure projects in developing countries: case study of the Tehran–Chalus toll road”,
46 Journal of Infrastructural System, Vol. 18 No. 3, pp. 210-217.
Corresponding author
Akintayo Opawole can be contacted at: tayodk@yahoo.com
Downloaded by University of Sussex Library At 06:23 28 May 2016 (PT)
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com