Professional Documents
Culture Documents
P Planning 130107202302 Phpapp02
P Planning 130107202302 Phpapp02
Project Planning
Planning in General : SWOT analysis
S: Strengths
W: Weaknesses
O: Opportunities
T: Threats
Objectives should be: SMART
S: Specific
M: Measurable
A: Achievable
R: Realistic
T: Timely
24/09/2006 Emad Elbeltagi 2
1
Project Planning
Somebody Anybody
TASK
Everybody Nobody
Project Planning
Characteristics of a good plan
2
Project Planning
Planning Inputs and Outputs
INPUTS OUTPUTS
Contract information Activities
Drawings Relationships among activities
Specifications Method statement
Available resources Responsibility
PLANNING Reporting levels
Bills of quantities
Project network diagram
Site reports
Activities duration
Organizational data
Activities cost
Construction methods
Project Planning
Planning Major steps
3
Project Planning
Work Breakdown Structure (WBS)
¾ The WBS is a hierarchical structure which is designed to
logically sub-divide all the work-elements of the project into
smaller elements.
House
Project Planning
Work Breakdown Structure (Why)
4
Project Planning
WBS & Organizational Breakdown Structure (OBS)
WBS (Work elements)
Project
Electrical
Formwork Reinforcement Concreting ……
Subcontr superinte
actor B ndent
Concrete
foreman
OBS
(Responsibility Project General Civil Control account
Formwork
& reporting) manager contractor superinte
ndent foreman
Rebar
Subcontr foreman
actor A Mechanic
al
superinte
ndent
Project Planning
WBS Coding
¾ Each work package or activity in a WBS is given a
unique code that is used in project planning and
control Identifying Activities
5
Project Planning
Project Activities
¾ Project is divided into segments of work called activities
Project Planning
Project Activities
Types of construction activities:
6
Project Planning
Project Activities
Example (Double Span Bridge):
Project Planning
Activities Relationships
¾ The order in which project activities are to be performed
can start
7
Code Description Predecessors
10 Set-up site ---
14 Procure RFT ---
16 Procure P.C. Beams ---
20 Excavate left abutment 10
30 Excavate right abutment 10
40 Excavate central pier 10
50 Foundation left abutment 14, 20
60 Foundation right abutment 14, 30
70 Foundation central pier 14, 40
80 Construct left abutment 50
90 Construct right abutment 60
100 Construct central pier 70
110 Erect left P.C. Beams 16, 80, 100
120 Erect right P.C. Beams 16, 90, 100
140 Fill left embankment 80
150 Fill right embankment 90
155 Construct deck slab 110, 120
160 Left road base 140
170 Right road base 150
180 Road surface 155, 160, 170
190 Bridge railing 155
200 Clear site 180, 190
Project Planning
Type of Activities Relationships
Four Types:
Finish to Start (FS) Finish to Finish (FF)
Start to Start (SS) Start to Finish (SF)
FS FF
SS SF
8
Project Planning
Overlaps
how much a particular activity must be completed
before a succeeding activity may start
¾ Used for activities not using the same type of resources
¾ With a value less than the duration of the preceding activity
Project Planning
Overlaps
Example
9
Project Planning
Relationships Considering Resource Constraints
Predecessors Predecessors
Activity description (unconstrained (constrained
resources) resources)
A1 Excavate unit 1 - -
B1 Concreting unit 1 A1 A1
C1 Brickwork unit 1 B1 B1
A2 Excavate unit 2 - A1
B2 Concreting unit 2 A2 B1, A2
C2 Brickwork unit 2 B2 C1, B2
A3 Excavate unit 3 - A2
B3 Concreting unit 3 A3 B2, A3
C3 Brickwork unit 3 B3 C2, B3
Project Planning
Project networks: AOA
Two Types:
¾ Activity-On-Arrow; AOA (Arrow Networks).
AOA
¾ Activity represented as arrows with start and finish nodes called
Events
Activity A
i j
j>i
10
Project Planning
Project networks: AOA
A B
5 10 15 B depends on A
A C
5 10 15 C depends on A and B
B
5
15
B B depends on A
5
A
10
C
15 C depends on A
5 15
A C B depends on A and B
D depends on A and B
B 10 D
5 15
Project Planning
Project networks: AOA
Dummy activity
¾ Activity with zero duration and no resources to adjust the network
A C A C
5 15 20 5 20 25
B D Dummy
25 B D
10 C depends on A and B 10 15 30
D depends on B only
A
A 5 15
5 15
B
Dummy
B
10
11
Project Planning
Project networks: AON
AOA
¾ Activity represented as nodes
Activity number
10
A
Activity name
Project Planning
Project networks: AON
10 20
B depends on A
A B
10 30 40 C depends on A and B
A C D
D depends on C
20
B
30
C
10 20 B depends on A
A B C depends on B
D depends on B
40
D
12
Project Planning
Project networks: Example
Activity Predecessors
A -
B -
C A, B
D C
E C
F D
G D, E
Project Planning
Project networks: Example (AOA)
13
Project Planning
Project networks: Example (AON)
Start - SS(Start)=1
A Start 2=SS(Start)+1
B Start 2=SS(Start)+1
C A, B 3=Highest of [SS(B), SS(A)]
D C 4=SS(C)+1
E C 4=SS(C)+1
F D 5=SS(D)+1
G D, E 5=Highest of [SS(D), SS(E)]
Finish F, G 6= Highest of [SS(F), SS(G)]
Project Planning
Project networks: Example (AON)
Sequence step 1 2 3 4 5 6
14
Project Planning
Activity Duration & Direct Cost
Project Planning
Activity Duration & Direct Cost
Productivity can be estimated:
Productivity data
15
Project Planning
Activity Duration & Direct Cost
Example
What is the duration to install 6000 square feet of walls shuttering if:
¾ Crew of 2 carpenters is used, output of 200 square feet/day
¾ Productivity is measured as 0.008 man-hour/square feet. Number
of carpenters =3, and number of working hours/day = 8 hours
Project Planning
Activity Duration & Direct Cost
Example (balanced mix of resources)
A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.
- A 6 man concrete crew can place 16 m3 of concrete/day.
- A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.
- A carpenter and assistant can fix and remove 16 m2 of shuttering/day
16
Project Planning
Activity Duration & Direct Cost
Activity direct cost:
17