You are on page 1of 35

CHINA HARBOUR ENGINEER COMPANY LIMITED

Construction of Surface Method Statement


Water Treatment Plant
and Impounding 12a-Painting and
Reservoir protective coating
CONTRACT No. KWASA / KWSP /
ICB-02

Date: 2017.03.12 Revision:00

MS-12a

Painting and Protective coating


CONTENTS
INTRODUCTION

SCOPE OF WORK

MATERIALS

MACHINERY & EQUIPMENT

MANPOWER

MATERIAL CONTROL

WORKING PROCEDURE

SAFETY CONTROL

QUALITY CONTROL AND INSPECTION


APPENDIX

Prepared By Reviewed By Approved By


Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

1. INTRODUCTION

This Method Statement covers the working procedure, quality control and resources to be
used for the Painting work as per drawing, design and specification at “Construction of
Surface Water Treatment Plant and Impounding Reservoir”

2. SCOPE OF WORK

The scope under this paper covers the control of paint materials and procedure to be followed
in the course of surface preparation, painting/coating application, inspection and safety
requirement for above ground steel structures.

3. Materials

The major materials used for the painting works, but are not limited to the following.
 PU- Polyurethane Paint
 Epoxy Zing Phosphate Primer
 Epoxy Thinner
 Curing Agent (for Top Coat)
 Curing Agent (for primer)
 Iron Sand (Sand Blaster)
4. Machinery & Equipment

 Inspection Equipment

Surface profile gauge Magnetic thickness gauge Holiday Detector

o Temperature gauge & Hydrometer


o Surface Profile gauge
o Magnetic thickness gauge
o Holiday Detector

2|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

 Blasting And Coating Equipment

Sand Basting equipment Air Spray

o Sand Blasting Equipment


o Generator
o Power tool cleaning equipment
o Air spray equipment
o Brushes

5. Manpower
 QC
 Forman
 Skill Workers

5.1 Manpower and Responsibilities

The work will be carried out by qualified personnel in a neat and workmanlike manner
conforming to all applicable project specification under the responsibility of Foreman .Site
Engineer will assist the Foreman in implementation and control of work and associated safety
procedures. Safety officer will ensure that all the activities are carried out in accordance with
the relevant safety regulations. Project Manager will supervise the work on top.

3|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

6. Material Control

- All materials send to the job site will be from approved source
- All material will be inspected in accordance with the procedure for the material’s
loading, unloading, data sheets, storage and distribution. Coating material shelf
life will be checked for expiry date. RFI will be issued for inspection.

Storage for coating materials

- Coating Material will be stored in cool and dry place well ventilated and free
from excessive heat, open flame or source of ignition and CHEC’s central store is
selected for that purpose.

7. WORKING PROCEDURE

7.1. Environment check

- Before commencing work on surface preparation and coating, the atmospheric


temperature and the relative humidity will be measured in order to determine the
dew point. Relative humidity reading will be measured at interval of two hours.
- Following determination of the dew point, the steel surface temperature will be
measured at regular 2 hour interval. The steel surface temperature will be 30 C or
more above the dew point during surface preparation as well as during coating as
per SPECIFICATION-2457-3.04E.

4|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

7.2. Surface Preparation

- As per specification the surface will be blast cleaned and the cleaning will
produce A surface finish to BS 7079:2009.
- If there any organic substance such as oil, grease and other contaminant will be
removed in accordance with specification prior to blasting operation
- All rough welds. Burrs and sharp surface projections shall be ground smooth and
all weld spatters will be removed prior to blasting operation.
- Sand will be used as blast cleaning abrasive.

- All surfaces including welding seams will be blast cleaned to Sa 2⅟2 of BS 7079
(very thorough blast cleaning. Mill scale, rust and foreign matter shall be
removed to the extent that the only traces remaining are slight stains in the forms
of spots or stripes).
- The surface roughness will not exceed 100 microns as per SPECIFICATION-
1815-1.01.
- If blasting is not possible in welded seams, alternative method will be used as per
procedure specified in the SPECIFICATION-01815-1.02 (D).
- Grit and dust then will be thoroughly removed with brush and compressed air
free of oil and water.

Surface profile comparator

- The surface will be compared by surface profile comparator and surface profile
depths and the range will be determined.
- The surface profile comparator will be used by either visual or tactile comparison
with the surface to be inspected and the two segments that bracket the test surface
are determined.

5|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

7.3. Mixing and Thinning

- Paint will be mixed in accordance with manufacturer’s instruction and as per


specification.
- Mixing ratio for primer – Base paint : curing agent =2: 1 by volume. Thinner will
used for thinning maximum ratio for thinner 20% as per recommendation by
manufacturer. See APPENDIX E.
- For final coating mixing ratio is –Base paint : hardener=3:1.Thinner will be used
as per requirement for spraying but the mixing ratio is maximum 20% as per
recommendation by manufacturer. See APPENDIX E.
- Mixing in open container will be done in a well ventilated area away from spark
or flames.
- Coating work will be used after 5 minutes of mixing. Paint will not remain in the
spray pots, painter bucket

7.4. Painting and Coating Application

- Primer coat will be applied after surface is properly prepared according to


procedure 7.1. & 7.2., inspected and approved by the consultant engineer.
- After ensuring the surface is dry and cleaned then the primer coat (mixed as per
procedure 7.3.) will be applied within 4 hours after blast cleaned as per
SPECIFICATION-01815-1.01
- 1st coat of top coat will be applied between 24 to 48 hours after completing the
primer coat. See APPENDIX E.
- 2nd coat of top coat will be applied between 24 to 48 hours after completing the
1st top coat. See APPENDIX E.
- As per recommendation of steel sheet pile manufacturer & manufacturer of paint
two protective coating shall be applied in the steel sheet piles. See APPENDIX F
& APPENDIX E.
- Air spray will be used for all coating and for air spray air pressure will be 50~70
psi.
- Paint ingredient will be kept uniformly mixed in the spray pots or containers
during paint application by intermittent agitation as frequently as is required.
- Brush will be used for only blind areas of all rivets and bolts and inaccessible
areas.

6|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

- For each coats as per manufacturer instruction touch dry is 2 hours and final
curing period for use is 7 days. See APPENDIX E.
- The finish coating surface will be of uniform color and free from pinhole,
peeling, sags and runs etc. which will be checked, inspected and approved by the
consultant engineer.

7.5. Drying/Curing

- All drying and re-coat times will be that specified by manufacturer and project
specification. See APPENDIX E.
- Curing will conform to the manufacturer’s recommendation. See APPENDIX E.
- Paint will be protected from rain, condensation, contamination until dry to fullest
extent practical.
- No paint subjected to immersion before it is thoroughly dried or cured.

7.6. Film Thickness Measurement

- The dry film thickness of individual coats and of the total coating system will be
checked at 5 random locations over areas representative of the work in progress.
- As per recommendation by manufacturer, dry film thickness will be 30-40 µm
See APPENDIX E.
- No coat or finished coating will be less than 75% of the nominal thickness as per
SPECIFICATION-02457-3.04 G
- With the exception of areas such as welds etc. the minimum dry film thickness
will not exceed by more than 50%.
- Dry film thickness will be measured with a magnetic thickness gauge suitable for
given type of coating thickness range and substrate material.

7.7. Repair of Damage areas

- Damaged painting and coating, and/or coating which does not pass the holiday
detection test will be repaired and retested to the satisfaction of consultant/client.
- The coating materials used for repair and maintenance will be same as the
original materials.

7|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

- The surface preparation method for repair will depend upon the size of areas to
be coated and the repair coating materials required.
- The area of the coating damage or holiday, along with the adjacent area of
coating for a minimum of 25 mm on all sides will be thoroughly prepared.
- The painting repair method will be as per pain manufacturer’s specification.
- Repair coating will applied so that the final coat overlaps the surrounding sound
coating for a minimum 25 mm

8. SAFETY CONTROL

- Safeties in blasting and painting operation are paramount. Both operators and
supervisors will must be fully conversant with all safety requirements associated
with blasting and cleaning scaffolding and access platforms, ventilation in in
enclosed areas as per project safety plan.

The special PPE for worker

- The PPE requirement include hard hat with chin strap, safety glasses, coverall
with long sleeves, steel toed safety shoes, safety harness, working gloves and ear
plugs when working.
- Only experienced and competent persons with valid work permit will be allowed
to operate all the equipment’s every day after checked by safety officer.
- Extreme precaution will be used when working with paint materials, cleaning
fluids, etc. especially in close proximity to oxygen piping or oxygen equipment.
- Heavy concentration of volatile or toxic fumes shall be used.

8|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

- Safety devices and safety warnings shall be provided starting from the site
entrance gate till the casting area.
- All safety precaution will be complying with the contractor’s project safety
plan.

9. QUALITY CONTROL AND INSPECTION

- Daily reports shall be assured on all painting activities and recorded on


blasting/painting inspection reports. These records will be maintained and
monitored by QC engineer who together with consultant engineer/employer will
sign on all inspection reports.
- The completed coating will be checked for thickness by magnetic thickness
gauge

- The completed coating will be checked for adhesion by means of adhesion test to BS
3900 part E6, carried out on 10% on the piles. The adhesion of any completed coating
will not be worse than classification 2 (The coating has flaked along the edges
and/or at the intersections of the cuts. A cross-cut area greater than 5 %, but not
greater than 15 %, is affected)
- As per specification Adhesion test will not carry out until seven days after
coating.
- Pre form of inspection sheets for quality control is attached in Appendix C.

Apparatus for pull off test

9|Page
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

Appendix A: Flow Chart for Material Testing & Work Inspection

Check for surface


Atmospheric Is it Yes Clean & surface
Start
Check satisfactory? roughness

Approved source Rework


and type of material No
delivered to site
including Paint,
Primer, Curing agent,
Thinner etc. Is it
Yes No
satisfactory?

RFI List with delivery Inspection for


notes issued with Is it mixing as
Yes
particular of material satisfactory? specified in 7.3
quantity and test
Remix

Is it No
satisfactory?

Yes

Coating application
check for time and
Intervals between coat

7 days After
final coating

Inspection for Inspection for Film Inspection for


Uniformity of coating Thickness by Magnetic Adhesion by pull-off
By Holiday Detector Thickness Gauge test

No

Is it Is it
Repair Work No
satisfactory? satisfactory?

Yes

Yes END

10 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

Appendix B: Flow Chart for Working Procedure of Painting & Protective Work

11 | P a g e
APPENDIX C: QC SHEET & CHECKLISTS
Construction of Surface Water Treatment Plant and Impounding Reservoir
PAINT & PROTECTIVE WORK
ATMOSPHERIC CHECK
RELATIVE STEEL SURFACE
DATE TIME LOCATION ATMPH TEMP DEW POINT REMARK
HUMIDITY TEMP

SUPERVISOR/CHEC AECOM/SMEC KWASA

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:


Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

Construction of Surface Water Treatment Plant and Impounding Reservoir


PAINT & PROTECTIVE WORK
SURFACE PROFILE CHECK
AREA OF BLAST BLASTING BLASTING BLAST CLEANED
DATE TIME LOCATION REMARK
CLEANING START FINISH GRADE

SUPERVISOR/CHEC AECOM/SMEC KWASA

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

13 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

Construction of Surface Water Treatment Plant and Impounding Reservoir


PAINT & PROTECTIVE WORK
COATING CHECK

INTERVAL READING OF
READING OF
AREA OF BETWEEN MAGNETIC PULL OFF TEST
DATE TIME LOCATION COAT ID HOLIDAY REMARK
COATING COATING OR THICKNESS RESULT
DETECTOR
BLASTING GAUGE

SUPERVISOR/CHEC AECOM/SMEC KWASA

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

14 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

Construction of Surface Water Treatment Plant and Impounding Reservoir


PAINT & PROTECTIVE WORK
RECORD SHEET FOR PAINT MIXING

BASE PAINT CURING AGENT


THINNER WORK REMAINING
DATE TIME COATING TYPE REMARK
VOL FINISH TIME QTY
NAME VOL NAME VOL

SUPERVISOR/CHEC AECOM/SMEC KWASA

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

15 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

Construction of Surface Water Treatment Plant and Impounding Reservoir


PAINT & PROTECTIVE WORK
RECORD SHEET FOR MATERIAL RECEIVE
MATERIAL
MANUFACT PRODUCT PRODUCT STORE
DATE TIME MATERIAL NAME RECEIVED EXPIRY DATE REMARK
URE DATE TYPE NUMBER AREA
DATE

SUPERVISOR/CHEC AECOM/SMEC KWASA

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

16 | P a g e
APPENDIX D : MAS
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

18 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

19 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

APPENDIX E: PAINT PROPERTIES, SPECIFICATION & TEST REPORTS

20 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

21 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

22 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

23 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

24 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

25 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

26 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

27 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

28 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

29 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

30 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

31 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

32 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

33 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

34 | P a g e
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 12a- Painting and Protective Work

APPENDIX F: STEEL SHEET PILE MANUFACTURER’S RECOMMENDATION

35 | P a g e

You might also like