You are on page 1of 8

CONSTRUCTION BULLETIN

Welcome to the March 2021 edition


of our Construction Bulletin.
In this edition we cover a range of recent developments in
international construction law:
• Experts and Conflicts of Interest
• The Pre-Estimate of Loss Test for Liquidated Damages
is Alive and Well in Singapore
• Hong Kong Court of Appeal Confirms Strict Approach
to Notice as a Condition Precedent to Entitlement
• Sampling Variations: An Acceptable Approach in
MARCH 2021

Construction Disputes?
The inside back page of this bulletin contains details
of team news and webinars at which the members
of the construction team will be speaking over the
coming months.
Michael Sergeant, Partner
michael.sergeant@hfw.com
Katherine Doran, Senior Associate
katherine.doran@hfw.com
EXPERTS AND CONFLICTS SCL and the developer’s contract
OF INTEREST (partly contained in a letter from SCL)
provided that solution. SCL stated,
Appointing the right expert is “we will not…undertake any…
critical to achieving a satisfactory engagement that…might [create
outcome in construction disputes. an] actual or perceived conflict.”
Consequently, clients are The court concluded that “we”
increasingly proprietorial about meant the entire Secretariat group
the experts they instruct. However, because 1) the group marketed itself
the ‘supply’ of suitable experts is as a single outfit; 2) SCL’s conflict
decreasing due to consolidation searches spanned the group; 3)
of international consultancy firms. group companies shared owners and
This creates a tension, which was directors; and 4) profits were shared
ANDREW ROSS tested in a recent case exploring group-wide. Additionally, the court
ASSOCIATE, LONDON the nature of experts’ duties to thought that interpreting “we” as
their clients. SCL alone could allow Secretariat
“While acknowledging Case Background companies to act for rival parties in
that fiduciary duties the same arbitration, undermining
The developer of a petrochemical the clause’s purpose.
were not incompatible plant was the respondent in two
with an expert’s role, the arbitrations. In the first (commenced Implications
court considered this was by a contractor), it instructed Similar scenarios could occur on
an “inapt” description Secretariat Consulting Pte Ltd (SCL) any large construction project. It is
(part of the Secretariat group) to entirely understandable that parties
of the relationship .” provide arbitration support and to a case will want to ensure there
expert services. In the second, is no risk of their expert having a
commenced by the project manager, conflict of interest or of information
the project manager asked Secretariat inadvertently leaking to an opponent.
International UK Ltd (SIUL) (another This case reassures parties in that
Secretariat company) to provide regard by clarifying that courts will
quantum and delay expert services. generally take a strict approach
The developer sought an injunction to apparent conflicts of interest
to prevent SIUL from acting for the across global consultancies. The
project manager, arguing that SCL’s court also clarified that parties
engagement on the first arbitration can actively manage this risk by
created a conflict of interest. including appropriate obligations
The court concluded that the prohibiting conflicts of interest in
Secretariat group owed the developer their appointments.
a fiduciary duty of loyalty, requiring it While the court avoided importing
to act unselfishly in the developer’s fiduciary obligations into this
best interests, preventing SIUL from expert/ client relationship, it did not
acting in the second arbitration. completely rule out doing so in future,
The decision was unprecedented despite the potentially uncertain
and sparked concerns about far- and wide-ranging consequences.
reaching consequences, for example, Potential conflict situations like this
impacting experts’ duties to tribunals. are likely to become more common
as expert consultancies grow and
Court of Appeal decision adopt a more corporate outlook.
On appeal, the Court of Appeal This decision provides reassurance
took a pragmatic approach.1 While to users of expert services that they
acknowledging that fiduciary duties won’t be prejudiced as a result.
were not incompatible with an ANDREW ROSS
expert’s role, the court considered Associate, London
CONSTRUCTION BULLETIN MARCH 2021

this was an “inapt” description of T +44 (0)20 7264 8048


the relationship and that importing E andrew.ross@hfw.com
the “legal baggage” of a fiduciary
1 [2021] EWCA Civ 6
relationship may have “unseen
ramifications”. The court sought an
alternative solution.
THE PRE-ESTIMATE OF LOSS declined to extend the penalties rule
TEST FOR LIQUIDATED to primary obligations. The Court said
that by extending the penalties rule
DAMAGES IS ALIVE AND
to primary obligations, the court was
WELL IN SINGAPORE interfering with the parties’ freedom
In Denka Advantech Pte Ltd to contract.
v Seraya Energy Pte Ltd,1 the Pre-Estimate of Loss Test
Singapore Court of Appeal affirmed
the traditional pre-estimate of However, the Court of Appeal did
loss test for liquidated damages not apply the test for penalties set
continues to apply in Singapore. out in the English Supreme Court
decision of Cavendish v Makdessi. 3
In doing so, they declined to follow the In Cavendish, the English court
wider “legitimate interest” test now CHRIS CHO
found that liquidated damages will
applied in the English and Australian ASSOCIATE, MELBOURNE
be enforceable unless the clause is a
courts. This case is likely to be of secondary obligation which imposes a “The traditional pre-estimate
great interest to both contractors detriment which is unconscionable or
in Singapore and to international of loss test for liquidated
out of all proportion to the legitimate
contractors whose contracts are interest of the innocent party. damages continues to
subject to Singaporean law and apply in Singapore.”
will open the door to challenges to This test was widely considered to
liquidated damages clauses. be an attempt by the Supreme Court
to give greater autonomy to the
Background parties to agree liquidated damages
The case concerns contracts for and to seek to reduce unmeritorious
the supply of electricity rather than challenges to liquidated damages.
construction, but the principles are The Singaporean Court of Appeal
equally applicable. In brief, Seraya refused to apply this test. Instead,
contracted to supply electricity they affirmed the traditional “pre-
to Denka. Denka wrongfully estimate of loss” test in the Dunlop
terminated the contracts and Seraya Pneumatic Tyre Co case.4 The Court
claimed damages. The contracts in Denka v Seraya concluded that
included liquidated damages the “genuine pre-estimate” test
clauses for breach. Denka alleged is consistent with the nature of
that the liquidated damages were liquidated damages, which is to
unenforceable penalties. compensate for monetary loss. A rate
The Decision of liquidated damages fixed higher
than a pre-estimate of loss “must
The Court of Appeal decided that the
necessarily be penal”.
liquidated damages in the Seraya
contracts were not penalties and Commentary
were enforceable. In doing so, the The court did stress that in the
court conducted a wide ranging majority of cases, the application of
review of the law on penalties. Firstly, the two tests (pre-estimate of loss
the court considered whether the and legitimate interest) is likely to be
rule against penalties applies only the same. However, the likely results
to secondary obligations (i.e. breach of the decision in Denka will be that
of contract claims) as in England or the Singapore courts have opened
whether the rule applies to primary a door to challenging liquidated
obligations, as is the case in Australia. damages that other jurisdictions have
The court went on to address the already tried to close.
applicable test for enforceability
of liquidated damages provisions, CHRIS CHO
i.e. whether to follow the wider Associate, Melbourne
legitimate interest test, which now T +61 (0)3 8601 4514
applies in English law. E chris.cho@hfw.com

Scope of the Penalty Rule 1 Denka Advantech Pte Ltd v Seraya Energy Pte Ltd
[2020] SGCA 119

The Australian High Court in 2 Andrews v Australia and New Zealand Banking
Group Limited (2012) 247 CLR 205
Andrews2 extended the application
3 Cavendish Square Holding BV v Makdessi [2016] AC
of the penalty rule to apply not 117
only when there is a breach of 4 Dunlop Pneumatic Tyre Co Ltd v New Garage and
Motor Co Ltd [1915] AC 79
contract but also to breaches of
primary contractual obligations.
The Singaporean Court of Appeal
HONG KONG COURT OF with MTRC. The clause 21 argument
APPEAL CONFIRMS STRICT had not been included in Bauer’s
claims notices.
APPROACH TO NOTICE AS
A CONDITION PRECEDENT Clause 21.1 of the subcontract
TO ENTITLEMENT contained the following notice
provision: “… as a condition precedent
The decisions of the Court of First to [Bauer’s] entitlement to any such
Instance, and Court of Appeal, claim, [Bauer] shall give notice of its
in relation to an arbitral award intention to the [JV] within fourteen
concerning the validity of claim (14) days after the event…” Further,
notices has generated significant clause 21.2.1 of the subcontract,
interest within the construction required Bauer to submit a further
JULIE-ANNE MALLIS industry in Hong Kong and other notice in writing within 28 days of
ASSOCIATE, HONG KONG common law jurisdictions.1 the notice provided under clause 21.1
The latest decision of the Court of stating “the contractual basis together
“For contracts that are with full and detailed particulars and
Appeal confirms that a party to a
already on foot, it is construction contract must strictly the evaluation of the claim”.
imperative that parties, in comply with all conditions precedent When the case went to arbitration,
particular, contractors and when notifying the other party of its the arbitrator rejected Bauer’s claim
subcontractors carefully claim(s) under the contract regardless for a variation as it had failed to
of how stringent the conditions follow the contractual mechanism
comply with all conditions precedent may be or how meritorious and obtain a formal instruction
precedent when giving their case is. Failure to comply with from the Engineer. However, the
notice of claims.” conditions precedent will put a party arbitrator – who was sympathetic to
at risk of being time-barred. Bauer’s claims – found that Bauer
Background had complied with the requirements
of clause 21 of the subcontract by
The Employer, MTR Corporation setting out the factual basis of its
(MTRC), awarded a contract to a claim (notwithstanding that it had
joint venture which comprised not set out all of the contractual
Maeda Corporation and China State bases for its claim). In particular, the
Construction and Engineering (JV) arbitrator held that “as a matter
for the construction of tunnels for the of sympathy and as matter of
Hong Kong to Guangzhou Express Rail construction, the contractual basis
Link. The JV, in turn, entered into two of the claim stated in the clause
subcontracts with Bauer Hong Kong 21.2 notice did not have to be the
Ltd (Bauer) to carry out excavation contractual basis on which the party
works for, and the installation of, in the end succeeds in an arbitration.
diaphragm walls for the tunnels. First, to expect a party to finalize
During the excavation works, Bauer its legal case within the relatively
encountered unforeseen ground short period and be tied to that case
conditions causing it to excavate through to the end of an arbitration
more rock than it had initially is unrealistic. Secondly, what is
anticipated. Bauer submitted various important from the point of view of
notices to the JV stating that it was the Contractor is to know the factual
entitled to a variation under clause 19 basis for the claim so that it can
of the subcontract in respect of the assess it and decide what to do.”
unforeseen ground conditions. The JV was granted leave to appeal
The dispute was referred to the arbitrator’s decision, in a case
arbitration. In the arbitration Bauer which came before both the Court of
argued that it was entitled to a First Instance and the Court of Appeal.
variation under clause 19 of the Court of First Instance
CONSTRUCTION BULLETIN MARCH 2021

subcontract (as was set out in its


claims notices issued under the Madam Justice Mimmie Chan
subcontract). In addition, Bauer disagreed that clause 21 of the
argued that it was entitled to subcontract should be construed
additional payment or loss and sympathetically to Bauer. In
expense under clause 21 of the particular, she found that, “however
subcontract. Clause 21 was a ‘like much sympathy the contractor may
rights’ clause, predicated on the JV’s deserve, Clause 21 employs clear and
entitlements under the main contract mandatory language for the service
and contents of the notices to be Key Takeaways 1 Maeda Corporation and China State Construction
Engineering (Hong Kong) Limited v Bauer Hong
served, with no qualifying language Kong Limited [2019] HKCFI 916 and Maeda
The decisions provide a salient
such as “if practicable”, or “in so Corporation and China State Construction
reminder that courts will not re- Engineering (Hong Kong) Limited v Bauer Hong
far as the sub-contractor is able””.2 Kong Limited [2020] HKCA 830.
write the plain language of parties’
Madam Justice Chan also noted that 2 Maeda Corporation and China State Construction
contracts. They are in line with recent Engineering (Hong Kong) Limited v Bauer Hong
the language used in clause 21.1 of
English and Australian authorities Kong Limited [2019] HKCFI 916, [31].
the subcontract was “clear on its
that where it is sufficiently clear 3 Ibid.
plain reading” and that it is not for “a 4 Ibid, [18].
that a notice provision is a condition
court or tribunal to re-write the Sub- 5 Maeda Corporation and China State Construction
precedent to entitlement, strict Engineering (Hong Kong) Limited Joint v Bauer
Contract or Clause 21 for the parties
compliance is required.7 Hong Kong Limited [2020] HKCA 830, [53].
after the event”. 3 6 Ibid.
Parties should ensure that their 7 See, for example, Towergate Financial (Group) Ltd v
In light of her findings above, Madam
contracts are drafted using clear Hopkinson [2020] EWHC 984; Obrascon Huarte Lain
Justice Chan held that Bauer had SA v Her Majesty’s Attorney General for Gibraltar
and unambiguous language. If it [2014] EWHC 1028 and CMA Assets Pty Ltd v John
failed to give proper notice of its
is intended that a notice provision Holland Pty Ltd [No.6] [2015] WASC 217.
claims under clause 21.2 of the
be strictly complied with, then
subcontract. Concluding that the
expressly identify the provision as a
arbitrator’s decision to allow Bauer’s
‘condition precedent’, and state the
claim of ‘like rights’ was wrong in law,
consequences of failure to comply.
Madam Justice Chan stated that the
arbitrator “failed to pay heed and For contracts that are already on
give effect to the express provisions foot, it is imperative that parties,
of Clause 21.2, which is clearly stated in particular, contractors and
to be a condition precedent for any subcontractors carefully comply with
claim to additional payment or loss all conditions precedent when giving
and expense, and is required by the notice of claims. In addition to time
express provisions of clause 21.3 to be limits for notices, the content of the
“strictly complied with”.4 notice can also be important. If it
is a condition precedent to specify
Bauer was granted leave to
the contractual basis of the claim,
appeal to the Court of Appeal.
that is what the claiming party must
Court of Appeal do. Parties should not expect to be
able to rely on different or additional,
The Court of Appeal comprising
contractual bases at a later stage.
Madam Justice Susan Kwan VP,
Attention should also be paid to
Madam Justice Maria Yuen and
requirements concerning the form
Justice Aarif Barma unanimously
of notice (for example, if it must be in
upheld the first instance decision.
writing; whether email will suffice; if it
Finding that the wording of clause must be in a separate document).
21.2.1 of the subcontract was “clear
Where notice provisions are similar
and unambiguous”, the Court of
or identical to those in Maeda
Appeal emphasised that Bauer
Corporation v Bauer, contractors and
was “required to give notice of
subcontractors must set out all of the
the contractual basis [within the
contractual bases they intend to rely
stipulated time], not any possible
upon within the prescribed time and
contractual basis which may turn out
in the correct notice otherwise they
not to be the correct basis.”5
are at risk of being time-barred from
The Court of Appeal also noted that pursuing their claim(s).
the phrase “the contractual basis” in
It is anticipated that Bauer
clause 21.2.1 of the subcontract did
may seek leave to appeal to
not preclude Bauer from identifying
the Court of Final Appeal.
more than one contractual basis for
its claims. Bauer could have stated JULIE-ANNE MALLIS
more than one contractual basis Associate, Hong Kong
in the same notice or submitted T +852 3983 7695
separate notices for each contractual E julie-anne.mallis@hfw.com
basis it intended to rely upon.6
However, such action was required to
be taken within the time prescribed
by the subcontract. Bauer could
not, at a later stage, substitute one
contractual basis for another.
SAMPLING VARIATIONS: AN regard to the remaining instructions.
ACCEPTABLE APPROACH IN The defendants rejected this
approach and asked the court to
CONSTRUCTION DISPUTES?
strike out the claim. They objected to
On large projects, disputes between Standard Life’s approach to sampling
the employer and contractor can which they submitted had focused
often involve hundreds or even on the higher-value variations and
thousands of variations. Clearly, it is was not suitable for a professional
not practical to resolve the dispute negligence claim.
by dealing separately with each
The judge confirmed that
variation, and the cost involved
extrapolation is permissible as a
would be prohibitive.
matter of law and that it is a critical
CHRIS UTTON Sampling and Extrapolation tool for case management. He
ASSOCIATE, LONDON also explained that the key issue
In arbitration and adjudication, it
for claimants is to demonstrate
“In arbitration and has become commonplace for the
the sample selected is sufficiently
contractor to select a representative
adjudication, it has become representative to enable the court to
sample of the variations and use
commonplace for the extrapolation to establish the full
place reliance upon it.
contractor to select a extent of the claim. Often, when there The judge held that the sample
representative sample is a large number of variations, there selected was not representative and
will be distinct themes that make it gave draft directions. Standard Life
of the variations and use
possible to group them together. An would first have the opportunity to
extrapolation to establish example of such a grouping might remove any variations upon which
the full extent of the claim.” be where a contractor’s claim relies it could not genuinely rely. The
on orally instructed variations which defendants would then be permitted
the employer rejects because the to nominate a sample of 160 variations
contract permits written instructions for analysis and extrapolation.
only. In this situation, the contractor
Conclusion
may select a representative sample
of the variations explaining why (by The case provides clear judicial
reference to detailed particulars) they support for the use of sampling in
should be allowed. For example, claims where there are large numbers
the contractor may argue that the of variations. In this instance,
employer expressly waived the need the claim was for professional
for a written instruction. The findings negligence but the judge confirmed
by reference to the sample can then extrapolation may be legitimate in
be extrapolated and inferences drawn other kinds of cases, particularly
in relation to the other variations. when the same error has been
mass-produced. For contractors on
This pragmatic solution has been
large projects involving thousands of
widely accepted by arbitrators and
variations, this is good news because
adjudicators. Judges, on the other
it validates the use of sampling in
hand, have tended to take a more
circumstances where a claim would
cautious approach. A recent decision
otherwise be unmanageable.
in the High Court of England and
Wales suggests that the courts are CHRIS UTTON
now warming to the idea. Associate, London
T +44 (0)20 7264 8059
Standard Life Assurance Limited
E chris.utton@hfw.com
v Gleeds (UK) & Others1
1 [2020] EWHC 3419 (TCC)
Standard Life (the employer) paid its
contractor £146 million in settlement
of the final account. Standard
CONSTRUCTION BULLETIN MARCH 2021

Life alleged that 3,600 variation


instructions, issued negligently by
its design team, had resulted in the
sum being £38 million higher than it
ought to have been.
Standard Life analysed a sample
of 122 instructions and maintained
that the court’s findings could be
extrapolated to draw inferences with
Upcoming events: Our recent team news:
HFW Offshore Wind Webinar Our London team moved up to
Series: February to March 2021 Band 2 in Legal 500.
Equitable and other Remedies Our Australia team moved up to
2 March 2021 (9am - 10am GMT) Tier 4 in Legal 500 Asia-Pac.
Speakers: Max Wieliczko, Our Kuwait office was ranked
Michael Sergeant, Richard Booth, in Chambers for the first
Katherine Doran time, with special reference
for its construction work.
Game Changer: The Emergency
Arbitrator and Legal Strategy In October 2020, construction partner
4 March 2021 (8.30 am – 9.30 am GMT) Antony Riordan joined our Sydney
office from a rival firm. His team
Speakers: Ben Bury,
includes four associates: Brooke
Chanaka Kumarasinghe
Gilbey, Natasha Joukhdar, Rachel
HFW Offshore Wind Webinar Irwin and Jacqueline Borgese.
Series: February to March 2021 In the last year we have added
Case Studies three new associates to our London
16 March 2021 (9am - 10am GMT) team: Andrew Ross, Chris Utton and
Roxanne Langford.
Speakers: Max Wieliczko,
Michael Sergeant, Richard Booth,
Katherine Doran

Kuwait Construction Contracts


Forum Webinar
Opportunities and Challenges for
Kuwait’s Construction Industry in 2021
16 March 2021 (7am – 8am GMT)
Speakers: James Plant, Rula Dajani
Abuljebain, Michael Sergeant

Construction Law Update Webinar


28 April 2021 (9am – 10am GMT)
Speakers: Michael Sergeant,
Max Wieliczko, Richard Booth,
Chris Philpot, Daniel Johnson,
Andrew Ross, Katherine Doran

Construction Law Update Webinar


29 April 2021 (4pm – 5pm GMT)
Speakers: Michael Sergeant, Max
Wieliczko, Richard Booth, Katherine
Doran, Chris Philpot, Daniel Johnson,
Andrew Ross, Katherine Doran

International Construction
Arbitration Webinar
26 May 20201 (9am – 10 am GMT)
Speakers: Max Wieliczko, Michael
Sergeant, Ben Mellors, Kijong Nam,
James Plant, Katherine Doran

If you have any queries regarding


any of these upcoming webinars,
or to register your interest in
attending, please contact us at
events@hfw.com.
HFW has over 600 lawyers working in offices across the Americas,
Europe, the Middle East and Asia Pacific. For further information about
our construction capabilities, please visit hfw.com/Construction

hfw.com
© 2021 Holman Fenwick Willan LLP. All rights reserved. Ref: 002797

Whilst every care has been taken to ensure the accuracy of this information at the time of publication, the information is intended as guidance only.
It should not be considered as legal advice. Holman Fenwick Willan LLP is the Data Controller for any data that it holds about you. To correct your
personal details or change your mailing preferences please email hfwenquiries@hfw.com

Americas | Europe | Middle East | Asia Pacific

You might also like