Professional Documents
Culture Documents
Construction Disputes?
The inside back page of this bulletin contains details
of team news and webinars at which the members
of the construction team will be speaking over the
coming months.
Michael Sergeant, Partner
michael.sergeant@hfw.com
Katherine Doran, Senior Associate
katherine.doran@hfw.com
EXPERTS AND CONFLICTS SCL and the developer’s contract
OF INTEREST (partly contained in a letter from SCL)
provided that solution. SCL stated,
Appointing the right expert is “we will not…undertake any…
critical to achieving a satisfactory engagement that…might [create
outcome in construction disputes. an] actual or perceived conflict.”
Consequently, clients are The court concluded that “we”
increasingly proprietorial about meant the entire Secretariat group
the experts they instruct. However, because 1) the group marketed itself
the ‘supply’ of suitable experts is as a single outfit; 2) SCL’s conflict
decreasing due to consolidation searches spanned the group; 3)
of international consultancy firms. group companies shared owners and
This creates a tension, which was directors; and 4) profits were shared
ANDREW ROSS tested in a recent case exploring group-wide. Additionally, the court
ASSOCIATE, LONDON the nature of experts’ duties to thought that interpreting “we” as
their clients. SCL alone could allow Secretariat
“While acknowledging Case Background companies to act for rival parties in
that fiduciary duties the same arbitration, undermining
The developer of a petrochemical the clause’s purpose.
were not incompatible plant was the respondent in two
with an expert’s role, the arbitrations. In the first (commenced Implications
court considered this was by a contractor), it instructed Similar scenarios could occur on
an “inapt” description Secretariat Consulting Pte Ltd (SCL) any large construction project. It is
(part of the Secretariat group) to entirely understandable that parties
of the relationship .” provide arbitration support and to a case will want to ensure there
expert services. In the second, is no risk of their expert having a
commenced by the project manager, conflict of interest or of information
the project manager asked Secretariat inadvertently leaking to an opponent.
International UK Ltd (SIUL) (another This case reassures parties in that
Secretariat company) to provide regard by clarifying that courts will
quantum and delay expert services. generally take a strict approach
The developer sought an injunction to apparent conflicts of interest
to prevent SIUL from acting for the across global consultancies. The
project manager, arguing that SCL’s court also clarified that parties
engagement on the first arbitration can actively manage this risk by
created a conflict of interest. including appropriate obligations
The court concluded that the prohibiting conflicts of interest in
Secretariat group owed the developer their appointments.
a fiduciary duty of loyalty, requiring it While the court avoided importing
to act unselfishly in the developer’s fiduciary obligations into this
best interests, preventing SIUL from expert/ client relationship, it did not
acting in the second arbitration. completely rule out doing so in future,
The decision was unprecedented despite the potentially uncertain
and sparked concerns about far- and wide-ranging consequences.
reaching consequences, for example, Potential conflict situations like this
impacting experts’ duties to tribunals. are likely to become more common
as expert consultancies grow and
Court of Appeal decision adopt a more corporate outlook.
On appeal, the Court of Appeal This decision provides reassurance
took a pragmatic approach.1 While to users of expert services that they
acknowledging that fiduciary duties won’t be prejudiced as a result.
were not incompatible with an ANDREW ROSS
expert’s role, the court considered Associate, London
CONSTRUCTION BULLETIN MARCH 2021
Scope of the Penalty Rule 1 Denka Advantech Pte Ltd v Seraya Energy Pte Ltd
[2020] SGCA 119
The Australian High Court in 2 Andrews v Australia and New Zealand Banking
Group Limited (2012) 247 CLR 205
Andrews2 extended the application
3 Cavendish Square Holding BV v Makdessi [2016] AC
of the penalty rule to apply not 117
only when there is a breach of 4 Dunlop Pneumatic Tyre Co Ltd v New Garage and
Motor Co Ltd [1915] AC 79
contract but also to breaches of
primary contractual obligations.
The Singaporean Court of Appeal
HONG KONG COURT OF with MTRC. The clause 21 argument
APPEAL CONFIRMS STRICT had not been included in Bauer’s
claims notices.
APPROACH TO NOTICE AS
A CONDITION PRECEDENT Clause 21.1 of the subcontract
TO ENTITLEMENT contained the following notice
provision: “… as a condition precedent
The decisions of the Court of First to [Bauer’s] entitlement to any such
Instance, and Court of Appeal, claim, [Bauer] shall give notice of its
in relation to an arbitral award intention to the [JV] within fourteen
concerning the validity of claim (14) days after the event…” Further,
notices has generated significant clause 21.2.1 of the subcontract,
interest within the construction required Bauer to submit a further
JULIE-ANNE MALLIS industry in Hong Kong and other notice in writing within 28 days of
ASSOCIATE, HONG KONG common law jurisdictions.1 the notice provided under clause 21.1
The latest decision of the Court of stating “the contractual basis together
“For contracts that are with full and detailed particulars and
Appeal confirms that a party to a
already on foot, it is construction contract must strictly the evaluation of the claim”.
imperative that parties, in comply with all conditions precedent When the case went to arbitration,
particular, contractors and when notifying the other party of its the arbitrator rejected Bauer’s claim
subcontractors carefully claim(s) under the contract regardless for a variation as it had failed to
of how stringent the conditions follow the contractual mechanism
comply with all conditions precedent may be or how meritorious and obtain a formal instruction
precedent when giving their case is. Failure to comply with from the Engineer. However, the
notice of claims.” conditions precedent will put a party arbitrator – who was sympathetic to
at risk of being time-barred. Bauer’s claims – found that Bauer
Background had complied with the requirements
of clause 21 of the subcontract by
The Employer, MTR Corporation setting out the factual basis of its
(MTRC), awarded a contract to a claim (notwithstanding that it had
joint venture which comprised not set out all of the contractual
Maeda Corporation and China State bases for its claim). In particular, the
Construction and Engineering (JV) arbitrator held that “as a matter
for the construction of tunnels for the of sympathy and as matter of
Hong Kong to Guangzhou Express Rail construction, the contractual basis
Link. The JV, in turn, entered into two of the claim stated in the clause
subcontracts with Bauer Hong Kong 21.2 notice did not have to be the
Ltd (Bauer) to carry out excavation contractual basis on which the party
works for, and the installation of, in the end succeeds in an arbitration.
diaphragm walls for the tunnels. First, to expect a party to finalize
During the excavation works, Bauer its legal case within the relatively
encountered unforeseen ground short period and be tied to that case
conditions causing it to excavate through to the end of an arbitration
more rock than it had initially is unrealistic. Secondly, what is
anticipated. Bauer submitted various important from the point of view of
notices to the JV stating that it was the Contractor is to know the factual
entitled to a variation under clause 19 basis for the claim so that it can
of the subcontract in respect of the assess it and decide what to do.”
unforeseen ground conditions. The JV was granted leave to appeal
The dispute was referred to the arbitrator’s decision, in a case
arbitration. In the arbitration Bauer which came before both the Court of
argued that it was entitled to a First Instance and the Court of Appeal.
variation under clause 19 of the Court of First Instance
CONSTRUCTION BULLETIN MARCH 2021
International Construction
Arbitration Webinar
26 May 20201 (9am – 10 am GMT)
Speakers: Max Wieliczko, Michael
Sergeant, Ben Mellors, Kijong Nam,
James Plant, Katherine Doran
hfw.com
© 2021 Holman Fenwick Willan LLP. All rights reserved. Ref: 002797
Whilst every care has been taken to ensure the accuracy of this information at the time of publication, the information is intended as guidance only.
It should not be considered as legal advice. Holman Fenwick Willan LLP is the Data Controller for any data that it holds about you. To correct your
personal details or change your mailing preferences please email hfwenquiries@hfw.com