Professional Documents
Culture Documents
MELUKOTE
8
CANAL ALIGNMENT
INTRODUCTION:
A section of canal is said to be most economical when the canal is minimum.
But the cost of construction of canal depends upon the lining. To keep the
cost down or minimum the wetted perimeter for a given discharge should be
minimum.
ALIGNMENT:
After construction of tank the water stored in the tank has to flow through the
canal for irrigating the command area. The slope of the is an important factor.
The slope to be provided should be such that the water shall flow with non-
scouring and non-silting velocity. The nature of soil is to be taken into account
to fix the gradient of the canal with physical verification of the type of soil in
the command area gradient of 1 in 2000 has been fixed.
SPECIFICATIONS:
Canal is aligned in a falling contour
Depth of cut should be minimum
There should be few cross drainage works
Straight canal is preferred and curves are avoided as for as possible.
DEFINITION:
Classification of canals:-
Based on the discharge carrying capacity they are classified as: main,
branch, major branch distributary, minor distributary and filed canals.
Based on alignment, they are classified as contour canals, watershed or
ridge canals and side slope canals and detour canals.
CONTOUR CANALS:-
Contour canals are aligned roughly parallel to the ground surface. Such
canals have command area on only one side as the other side of the canal will
be at higher level, these canals are also known as single bank canals.
These canals follow the ridge line of the country and can irrigate on either
sides. Such canals have to be avoided when they intercept important places,
places of worship costly and precious forests.
These canals are aligned roughly at right angles to the contours of the
country and hence they run parallel to the natural drainage.
DTOUR CANALS:-
Generally contour canals have to cross many obstacles like deep valleys.
High ridges etc..thereby the cost would be very very high. Hence in order to cut
down the cost of production, lengthy alignment is adopted, such canals are
known as detour canals. The main drawbacks of such canals are: the command
area reduces and the number of cross drainage work tends to increase.
In the present work the proposed new tank is bounded by hillocks on
either bank or the ground terrain slopes towards the natural drain, therefore,
contour canal alignment is really suited.
As far as possible, large filling and deep cutting shall be avoided. The fill
and cut shall be balanced as far as possible.
The cross drainage works shall be minimum.
The alignment should be fairly straight , without sharp bends.
The longitudinal slope for the canal shall be as flat as possible and this is
guide by the minimum permissible velocity. The resulting slope shall be such that
the velocity in the channel is neither silting nor scouring. The value of longitudinal
slope caries from 1: 500 to 1:12500, depending upon the terrain and type of
canal.
OBJECTIVES OF SURVEYING:-
FIELD WORK:
It is very well known that a contour canal follows a contour and it should
be in cutting. To fulfill this requirement , the survey work is doen taking the top
level of the canla as the reference RL.
Having known the bed level of the canal ie sill level of sluice and assuming
the depth of flow of water and suitable freeboard, we can fix up the level of the
top of the canal and proceed with survey work.
EQUIPMENTS REQUIRED:
E) PROCEDURE:-
Starting from the nearest BM a point along the center of proposed bund
having an RL 884.5 m is established on the right bank of bund.
This point is fixed with respect to three pemenant points by taking
bearings and distance.
The next pint is established on the ground corresponding to a slop of .
015 m at meter from the starting pint.
EXAMPLE:-
RL of the contour at 0 chainage i.e at sluice point = 858.355m
5. The procedure shall be continued keeping in mind that the canal must
be almost straight. However curves with large radius shall be set
whenever required.
BLOCK LEVELING:-
If the alignment crosses a natural valley, block leveling shall be carried out
so as to propose suitable cross drainage works.
Starting from the end point of the canal, the tail is traced using compass
and chain.
The final pint is the point where it reaches the mother valley.
{note: the canal can also be tailed off directly into the mother valley if
feasible.}
Note: the day’s work shall be closed on the benchmark by fly leveling.
OFFICE WORK
After collecting the required data from the field. Following working
drawings are to be prepared.
All the cross sections indicating proposed canal cross section, full supply
depth berms etc. Typical proposed cross sections for canal depending
upon canal are illustrated.
It is the area enclosed between the interline of the bund, mother valley,
and the centerline of canal and the tail drain. This can be calculated using a
planimeter.
Obtain the yield from the catchment area using suitable equation.
Calculate the irrigable area. If the irrigable area is larger than the
command area for further calculations.
LACEY’S THEORY:-
The main drawback of Kennedy’s theory was that neither the silt size nor
the silt load was considered anywhere in the design. However this pint is
taken care in the Lacey’s theory, the observation is that Kennedy defined
a regime channel as that which neither slits nor scours. However lacey
mentioned the regime in 3 stages , they are
(i) INITIAL REGIME:- This is the channel condition at which the cross
setion hs formed but the bed slope not yet secured.
REGIME CONDITION
Lacey felt that for channel of elliptical section, there is a certain velocity
below which the calculated wetted perimeter cannot contain any area.
Hence no attempt has been made to design channel of smaller
discharges with these formulas.
It is also seen that the lacey’s silt factor f in various formulae is not
dimensionally the same and no notice has been taken of this
discrepancy.
The constant in the equation p= 4.75√Q actually varies from 3.8 to 5.8 or
even within wider limits, but for design purposes , the above equation is
adhered to.
RETURN WALL
The cross section of return wall is same as downstream wing wall. Return wall is
made sufficiently long so that it projects well into the top of bank at downstream
of drop.