You are on page 1of 17

2008/1/28

PROCEDURE of ON-SITE EQUIPMENT SET-UP & INITIAL TEST for 5000S

This procedure might be useful to execute the equipment initial setup and initial test on-site.
This procedure is procedure to initial setup the equipment simply on-site. And, should refer
to the equipment instruction manual and the PNMT operating manual for detailed equipment
operation and the test procedure.

Work flow of ON-SITE EQUIPMENT SET-UP & INITIAL TEST

Equipment Installation Aerial installation

Equipment Antenna
Installation Installation

Feeder
Installation

Dehydrator
Installation

Check point Dehydrator Air


Dehydrator gage
Leakage
indication
Check

In-put Power Check point


Equipment bay top
Voltage Check

Equipment
Power-ON

DC-DC CONV Check point DC-DC CONV


Voltage Chack check terminal

Connect
PNMT
Check
By PNMT Equipment
Configuration

Antenna
By PNMT Alignment
Mode
Refer to appendix-1

Antenna
Orientation

By PNMT SD DADE
Adjustment
Refer to appendix-2

INTFC Delay
By PNMT
Adjustmant
Refer to appendix-3

By PNMT Local Test

Refer to ON-SITE TEST PROCEDURE

By PNMT Hop Test

Refer to ON-SITE TEST PROCEDURE


Appendix-1
Antenna Orientation

At opposite site
1. Set the “Maintenance Mode”.

“Configuration” → “System Maintenance”

“CTRL[ ] Maintenance” → “ON” → “Execute”

2. Set the “Manual Transmit Mode”.

“Configuration” → “Maintenance Control” → “TRP-MODULE” or “TRP-SYS”


“Manual Transmit Level Control Power” → Manual Transmit Level Control “ON” →
Manual Transmit Level Control Power “put attenuation value (one either of -20 to 0dB)” →
“Execute”

At local site

3. Set the “Maintenance Mode”.

“Configuration” → “System Maintenance”

“CTRL[ ] Maintenance” → “ON” → “Execute”


4. Set the “Antenna Alignment Mode”.

“Configuration” → “Maintenance Test” → “MDP-[01-05]-MODULE” or “MDP[01-05]-SYS”

“Antenna Alignment Output” → Antenna Alignment Mode “Enable” → “Execute”

After execute alignment mode, change status Normal to “Enable”


5. Connect the lead wire of the AGC monitor to the IDB connector (Z5 or Z25). And, lead wire
reaches the position near the antenna on the tower, and connects it with the VOLTMETER.

VOLTMETER
IDB

Z5 or Z25

Lead wire

6. Execute antenna orientation.

7. After RX level reached design value and completing the antenna alignment, change back the
setting of both sites to the original setting state
Reference

*IDB connector pin assignment for AGC monitoring.

MAIN SD

MAIN SD
AGC monitor AGC monitor

*AGC Monitor curve


Appendix-2
DADE Adjustment

At opposite site

1. Set the “Maintenance Mode”.

“Configuration” → “System Maintenance”

“CTRL[ ] Maintenance” → “ON” → “Execute”

2. Manual Transmit Level Control

“Maintenance Test” → “TRP-MODULE or TRP-SYS”


“Manual Transmit Level Control” → Manual Transmit Level Control of corresponding SYS
“ON” → Manual Transmit Level Control Power “put attenuation value (one either of -20 to
0dB)” → “Execute”

3. Carrier Level Sweep Function

“Maintenance Control” → “TRP-MODULE” or “TRP-SYS”

“Carrier Level Sweep Function” → “Carrier Sweep Function”


“Sweep for DADE V” → “Execute”

At local site
4. Connect VOLTMETER to IDB connector to monitor the DADE V for DADE adjustment.

IDB
VOLTMETER

Z5 or Z25

IDB connector pin assignment

DADE V monitor
5. Set the “Maintenance Mode”

“Configuration” → “System Maintenance”

“CTRL[ ] Maintenance” → “ON” → “Execute”

6. DADE adjustment

“Maintenance Control” → “TRP-MODULE or TRP-SYS”


“SD” “Adjust” of corresponding SYS → “SD” or “Main” (selected to be adjusted) →
Execute

Open the Warning → “OK”

The window of Adjust Operation Value and Adjust Operation are changes into the yellow
highlight.
Adjust Operation Value → Adjust Operation (enter the value of the delay time with Main and
SD (one either of 1 to 127ns)) → Adjust → Execute

The window of “Adjust Operation Value” is changed adjusted value into the yellow highlight
and window of “Adjust Operation” is changes to “Adjust”.

Enter another value and execute repeatedly until the voltage of the DADE V monitor become
minimum (approximate0.1V).
VOLTMETER

Make to minimum voltage.


Minimum (approximate 0.1V)
7. Completed DADE adjustment

After DADE monitor voltage become minimum voltage,


“Adjust Operation” → Save → Execute → The word character of "Adjust Operation Value"
and "Adjust Operation" was masked. And, DADE adjustment is completed

8. After completing the DADE Adjustment, change back the setting to the original setting state.
Appendix-3
INTFC Delay Adjustment
1. Set the “Maintenance Mode”.

“Configuration” → “System Maintenance”

“CTRL[ ] Maintenance” → “ON” → “Execute”


2. TX Test Operation.

Set the TX Test Operation Mode for corresponding channel.

Open the “Link Summary” window.

“TX Test Operation” → TX Test Operation “ON” → “Execute”


3. INTFC Delay Adjustment.

“Maintenance Control” → “MDP[01-05]-SYS”

“Delay Adjust” of corresponding SYS → “Execute”

Open the “Warning” window → “OK”


4. Completed delay adjustment.

Confirm the LED of IN PHASE on the INTFC card is turned on and “PROT FASYNC”, REG
FASYNC” and "Adjust Time Out" in the Delay Adjust window of PNMT becomes "Not
Occurred".

5. After completing the INTFC Delay Adjustment, change back the setting to the original setting
state.