Project Name : Rajiv gandhi Housing Project

Contractor: Universal Builders


Contact Person: Shyam yadav

Sl.no Inspection Description Evidence photograph

Date of casting and unique serials nos for


1 the precast panels to be provided on all the
casted panels for traceablicty of curing

presently cubes for testing are casted on


alternate days of concrete, but concrete is
2
happening on all the days and cubes to be
casted on daily basis

In cube register description of the works


are not mentioned and traceablity of the
3 cubes are missing (for eg in description of
work daily cated panels with unique
numbering to be entered )

for last one month cubes are not tested


due to covid near by collages are closed
4 alternate solution to be idntified for testing
of cubes on daily basis

Pour card to be implemented at site for


5 prepour inspection and post pour
inspection for precast panels
Erection checklist to be prepared and
implemted for erection of panels buildings
6
wise with all the details like erection date,
panels nos, jointing date, finishing etc

Screed concrete can be completed before


7
doing water pond test for the buildings

In cutouts openings PVC pipes are


provided, provide the cut out opening pvc
pipes applied with oil and can be removed
8
after intial setting time, presently they are
damaging the pipe before installing the
panels and it is very hard to remove.

In house no 669 below the foundation


found with voids and gap to be reffilled
9
immediatle to avoid settlement of
founation

Water drip/water cut to be provided in the


10 roof slab projecting outside of bathroom
side

In house no 627 bottom side of the canopy


11 are found with cracks to be rectified,
Masking tape, baker rods to be removed
House no 627 entrance of bathroom floor
slab has been projected to be rectified by
12
chipping it off or by constructing additional
step

One anchor bolt was missing in foot step


launder slab MS angle and all the MS plates
13
in all buildings to be made rust free by
painting with redoxide and paint

Insert plate to be fixed in the thread of the


stair case hence hand rails can be welded
14 and stability of the hand rail will straong
enough, presently only one rod is being
welded for support.

From house no 624 to 627, launder slab of


15 foot step to be plaster, found with minor
honey combs and exposed reinforcements

Where ever joint free tiles are fixed


workmanship to be improved cutting of
16
tiles, jointing of tiles, line of tile and pasting
to be checked properly in further buildings

Floor tiles grid are mismatched with the


17 wall tile grid, further care to be taken in
other houses
Plumbing opening not provided in House
18
no 626 bathroom in tile work

Kitchen roof slab found with crack, crack to


19
be opened and treated with filler material

House no 625 two bottom tiles got


20
damaged to be replaced

Parapet wall no PP4 to be extended and 5


to be reduced In size for making 90degree
21
joint, presently they are breaking PP5 for
fixing the the parapet walls

In precast wall panels one outer side is


fixed with ply board which has got
22
damaged enteirly to be replaced with MS
shutters for smooth finish

Shuttering oil is applied more in the precast


23 moulds, which has mixed up with the
reinforcement rods further care to be
taken to avoid
Bottom of the slab erected with cleaning in
24
House no 639

At the skirting placce plastering can be


25 avoided and in precast itsef roufgh surface
can be made for good adhesion

Special attention is required in casting of


shear walls over foundation and backfilling
26 soil can be done in layers with water
consolidationd and rammer to avoid
futhure settlement
Housing Project
rsal Builders Date: 18.10.2020
m yadav

Rectification photo Rectification date Remarks


for all
buildings
painting to
be done
for MS
plate