Project name : SPIS-R1

Location : Badoc and Pasuquin, Ilocos Norte

Subject : Task Schedule

Task Commitment Date to Remarks


Accomplished
Water Distribution Installation December 21,2019 Need Materials and pump to
proceed installation

Weekly Report for Napu, December 7,2019 Done


Pasuquin and Vintar Site as of
Dec.6,2019
Solar Array Mounting December 10,2019 On-going (90% accomplished)
structure at Badoc Site

Structural works at Pasuquin December 20,2019 On-going


site

Prepared By:

Princess Joan Ult


Site Engineer

Checked/Noted By:

Engr. Kelvin Bueviaje


Technical Head