POWER CONSUMPTION REPORT

DATE 9-Aug-21
S.NO DESCRIPTION ON DATE MTD YTD
ELECTRICITY BOARD
1 EDG METER 172.00 1620.00 7895.00
CRUSHER SECTION
2 Primary Crusher 1139.8 4561.53 46813.59
3 Secondary Crusher 3114.48 7686.12 62007.22
4 Crusher Auxillaries MCC 2349.13 10043.99 138335.51
TOTAL 6603.42 22291.64 247156.32
RAW MILL SECTION
5 Raw Mill Main Drive -1 19156.49 166460.72 538546.16
6 Raw Mill Main Drive -2 18886.87 164283.75 540628.74
7 Raw Mill Vent Fan 7990.67 70690.03 246474.41
8 RABH MCC 334.31 2943.37 14966.62
9 Raw Mill Hopper and Mill Auxillaries 3613.38 30279.61 183866.40
TOTAL 49981.71 434657.48 1524482.33
COAL MILL SECTION
10 Coal Mill Main Drive 4147.42 40350.87 121955.89
11 Coal Mill CA Fan 760.10 7263.99 27953.31
12 Coal Mill Auxillaries MCC 1586.33 14239.26 77952.89
TOTAL 6493.85 61854.12 227862.09
KILN, COOLER, ESP SECTION
13 Kiln Main Drive 955.06 9960.31 46861.64
14 PREHEATER FAN 1085.65 73010.06 246858.75
15 RABH Fan 10151.02 93666.84 355376.52
16 ESP fan 0.00 4591.84 15112.26
17 Silo Extraction& Kiln Firing MCC 165.62 1526.01 7394.44
18 Cooler Fans & ESP MCC 75.62 695.62 2416.37
TOTAL 12432.97 183450.68 674019.98
CLINKER EXTRACTION
19 Clinker Extraction MCC 4.00 15.88 95.07
UTILITIES
20 Lighting Panel 2224.50 19201.42 445217.99
21 Workshop 109.00 1536.66 18445.79
22 Water Pump House 1016.11 9456.32 86132.90
TOTAL 3349.61 30194.40 549796.68
GRAND TOTAL 78865.56 732464.20 3223412.47
Loss (EDG-PLANT KWH TOTAL) -78693.56 -730844.20 -3215517.47