As per original / Expected
7 Completion Date
revised PC-I
19-08-2018 30-06-2020
1 2 3 4 5 6 7
1. Academic Block 120,464 sqft 283.090 263.132 0% Nil
2. Hostel 64,732 sqft 150.591 171.031 0% Nil
3. Admin Block 58,430 sqft 146.075 127.224 13% Nil
4. Residence/Apartments 17,260 sqft 38.835 33.634 05% Nil
External Works(Sui Gas,
5. PTA connection, External 59.286 36.238 0% Nil
Electrification) 9 No.
External Development Works
a 143.379 155.652 0% Nil
(Tender Work)
Consultancy including 36 Man-
6. 25.192 35.831 10% Nil
overall supervision@3% Months
7. Escalation for Year 2 and 3 Rs. 34.670 28.994 100% Nil
Office Automation & ICT
8. No. 1,811 19.921 0.000 100% Nil
Facilities
Furniture / Fixture &
9. No. 7,939 49.901 46.423 0% Nil
Teaching Aid
10. Project Coordination Staff No. 1 5.675 3.601 0% Nil
11. Operational Transport No. 5 26.250 26.250 0% Nil
12 Contingencies @ 1.5% L/S 14.743 6.680 L/S Nil
*Expenditure in the salary head has been increased due to revised project pay scale
10 Physical progress ( % ): 87%
Page 2 of 3
.
11 No. of previous extensions ( indicate approving authority and period with dates):
Higher Education Commission (HEC) Islamabad has so far granted two (02) extensions in the
execution period of the project. The detail is given below:
University is totally committed to complete the remaining work within the extended period of
time till end of June, 2020. Despite the fact, we have lost precious construction time due to
lockdown and deceleration of KSK Campus as quarantine. However, we are making
arrangements to catch up with the progress as soon as we will be allowed to start construction
work again. In case if extension is required, we will let you know accordingly.
16 Recommendation:
Page 3 of 3