Project Timeline Gantt Chart

Jul 2021 Aug 2021 Sep 202 1 07/21/2121Oct 2021 Nov 2021 Dec 2021
ID Task Name Start Finish Duration
25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9 26/9 3/10 7/11 5/12

1 Documentation 6/21/2021 8/3/2021 32d

2 Presentation 8/4/2021 8/4/2021 1d

Fact finding and


3 requirements 8/5/2021 8/12/2021 6d
gathering
Information/ data
4 8/13/2021 8/17/2021 3d
analysis

5 Feasibility study 8/18/2021 8/18/2021 1d

6 System design 8/19/2021 8/25/2021 5d

7 Presentation 8/26/2021 8/26/2021 1d

System
development
8 8/27/2021 11/9/2021 53d
testing and fine-
tuning

9 Report Writing 11/10/2021 11/11/2021 2d

Final
10 11/12/2021 11/12/2021 .5d
Presentation