MAIN OFFICE

DATES ACTIVITY DETAILS REQUIRED MATERIAL


19-Aug CHAIR BOX PREPARATION & CARPENTER WORK
20-Aug CONCRETE FOR CHAIR
21-Aug BLOCK & STEEL WORK FOR DOWN BEAM
22-Aug CONCRETE FOR DOWN BEAM VIBRATOR
23-Aug BACKFILLING OF SOIL, LEVEL & PRODUCTION AREA EXCAVATION
24-Aug MESH WORK FOR FLOOR + PRODUCTION AREA
25-Aug CONCRETE FOR FLOOR + PRODUCTION AREA
26-Aug WALL BLOCK + BEAM CARPENTER WORK
27-Aug WALL BLOCK + BEAM CARPENTER WORK
28-Aug CONCRETE FOR COLUMNS REQUIRED JACK/ PLY + VIBRATOR
29-Aug PLY ARRANGEMENT FOR ROOF STEEL
30-Aug PLY ARRANGEMENT FOR ROOF + STEEL MESH
31-Aug PLY ARRANGEMENT FOR ROOF + STEEL MESH
1-Sep PLY ARRANGEMENT FOR ROOF + STEEL MESH
2-Sep CONCRETE FOR ROOF VIBRATOR
3 SEP - 10 SEP ELECTRICAL WORK INSIDE
3 SEP - 10 SEP PLASTERING OUTSIDE
6 SEP - 10 SEP INSIDE WALL + ELECTRICAL WORK
11-Sep REMOVAL OF ALL JACK & PLY
12-Sep INSIDE PLASTERING & WATER LEVEL FOR HALF WALL +ROOF
13 SEP - 21 SEP PUTTY + BASE COAT STARTING
14 SEP - 22 SEP TILES STARTING
15 SEP - 24 SEP ELECTRICAL WORK STARTING (AC + INTERNET CABLE + SWITCH + LIGHT)
19-Sep GLASS WORKER TO VISIT
26 SEP - 30 SEP GLASS WALL + WINDOW + DOOR

HR + ENGINEERING OFFICE
19-Aug WALL HOLE CLOSING + VID ROOM MODIFICATION + ELECTRICAL CABLE WORK
20-Aug ELECTRICA WIRING + PRE- PLASTERING INSIDE
21-Aug
22-Aug REMOVE SHUTTERING + JACK
23-Aug INSIDE ALL PLASTERING + WATER LEVEL OF HALF WALL
24-Aug PUTTY + PRIMER COAT + GLASS WORKER VISIT
25-Aug OUTSIDE PLASTERING + TILES
26-Aug ELECTRICAL WORK ( AC+ LIGHT + INTERNET)