You are on page 1of 1

Project Management Home assignment

Answer must be handwritten


Q1 Consider the following table of the project.[8] BCT/BEX
Activities Predecessors O m P
A - 5 6 7
B - 1 3 5
C - 1 4 7
D A 1 2 3
E B 1 2 9
F C 1 5 9
G C 2 2 8
H E,F 4 4 10
I D 2 5 8
J H,G 2 2 8
O-(optimistic time in week)
M-(most likely time in week)
P-(pessimistic time in week)
a. Construct the project network diagram
b. Find Expected duration and variance of each activity
c. Find critical path and expected project Completion time
d what is the probability of completing the project in 22 weeks
Q2 Prepare a statement of work (SOW) for a project which is to develop Engineering college
MIS. You are free to make your own assumption regarding the system. [6] BCT
Prepare a request for proposal (RFP) for a project which is to develop Engineering college MIS.
You are free to make your own assumption regarding the system. BEX

Q3, write short notes (any 3)[6] BCT/BEX


a) TQM b) EVM c) Box plot d)cost and schedule index e) Pareto chart f) Evaluation criteria
for seller section g) Risk register for MIS of Engineering college
Use normal distribution table for Q1

You might also like