Q1 Consider the following table of the project.[8] BCT/BEX Activities Predecessors O m P A - 5 6 7 B - 1 3 5 C - 1 4 7 D A 1 2 3 E B 1 2 9 F C 1 5 9 G C 2 2 8 H E,F 4 4 10 I D 2 5 8 J H,G 2 2 8 O-(optimistic time in week) M-(most likely time in week) P-(pessimistic time in week) a. Construct the project network diagram b. Find Expected duration and variance of each activity c. Find critical path and expected project Completion time d what is the probability of completing the project in 22 weeks Q2 Prepare a statement of work (SOW) for a project which is to develop Engineering college MIS. You are free to make your own assumption regarding the system. [6] BCT Prepare a request for proposal (RFP) for a project which is to develop Engineering college MIS. You are free to make your own assumption regarding the system. BEX
Q3, write short notes (any 3)[6] BCT/BEX
a) TQM b) EVM c) Box plot d)cost and schedule index e) Pareto chart f) Evaluation criteria for seller section g) Risk register for MIS of Engineering college Use normal distribution table for Q1