You are on page 1of 10

Available online at www.sciencedirect.

com

Electrical Power and Energy Systems 30 (2008) 393–402


www.elsevier.com/locate/ijepes

Determination of installation capacity in reservoir hydro-power


plants considering technical, economical and reliability indices
S.M.H. Hosseini a,*, F. Forouzbakhsh b, M. Fotouhi c, M. Vakilian c
a
Electrical Engineering Department, Faculty of Engineering, Islamic Azad University South-Tehran Branch, Mohallati Expway, Tehran, Iran
b
Electrical Engineering Department, Faculty of Engineering, Campus No. 2, University of Tehran, North Kargar Avenue, Tehran, Iran
c
Department of Electrical Engineering, Sharif University of Technology, Azadi Avenue, Tehran, Iran

Received 14 June 2006; received in revised form 9 January 2008; accepted 29 January 2008

Abstract

One of the most important issues in planning the ‘‘reservoir” type of hydro-power plants (HPP) is to determine the installation capac-
ity of the HPPs and estimate its annual energy value. In this paper, a method is presented. A computer program has been developed to
analyze energy calculation and estimation of the most important economic indices of an HPP using the sensitivity analysis method.
Another program, developed by Matlab software, calculates the reliability indices for a number of units of an HPP with a specified load
duration curve using the Monte Carlo method. Ultimately, comparing the technical, economic and reliability indices will determine the
installation capacity of an HPP. By applying the above-mentioned algorithm to an existing HPP named ‘‘Bookan” (located in the west-
north of Iran); the capacity of 30 MW is obtained.
Ó 2008 Elsevier Ltd. All rights reserved.

Keywords: Reservoir type of hydro-power plant; Economic analysis; Monte Carlo method; Installation capacity

1. Introduction issues worthy of study in the reservoir type of HPPs stud-


ies. In other words, calculating the suitable installation
HPPs have found special importance due to their rel- capacity is one of the most important factors in planning
atively low administrative and executive costs and a short HPPs.
construction time compared to large power plants. These
HPPs are in the ‘‘reservoir” (annual or seasonal regula- 2. Installation capacity
tion reservoir) category with a domain capacity from
10 MW and upper. The generated capacity is based on To determine the installation capacity of HPPs all
the accumulation of water reservoir and consists of a res- technical, economic and reliability indices are considered
ervoir dam, penstock, power house, and tailrace structure in the trade-off relations. Using this approach, the
of the body of HPP, as well as, other electrical and amount of annual energy is determined by using catego-
mechanical equipments. Seasonal regulation of the water rized statistics of the output and overflow volume of
volume in the headpond is used to get maximum power water in different months or even days. Then, after spec-
from the HPP during peak and base hours. The amount ifying the income and costs of the plant, the economic
of energy generated during different daily hours and/or indices of different alternatives are extracted then the reli-
different seasons of the year are the most important ability index is calculated. Ultimately, through compari-
son of the technical, economic and reliability indices, a
*
Corresponding author. Tel.: +98 2188738166; fax: +98 2188737752. superior alternative can be selected, determining the
E-mail address: smhh110@yahoo.com (S.M.H. Hosseini). installation capacity.

0142-0615/$ - see front matter Ó 2008 Elsevier Ltd. All rights reserved.
doi:10.1016/j.ijepes.2008.01.002
394 S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402

2.1. Energy calculation PFi ¼ ea =ðP i  8760Þ


¼ T i =8760; plant factor of hydro-power plant
The calculation of energy is based on the status table of
the output and overflow of the accessible water monthly
and even daily, as well as the net level of water recorded 2.2. Economical calculation
in different years. The net height of the reservoir is a func-
tion of the input of water into reservoir and also the level of In this section, the method of evaluation of income and
the water in the reservoir. Therefore, the height is not fixed costs and ultimately, the economic analysis of HPPs are
in different months. The useful net height can be extracted described. The costs of the project are divided into two cat-
from the subtraction of the level of water in the reservoir egories: investment and annual costs. Investment costs
and the level of axis of turbine. Basically, the relationship include civil costs, electro-mechanical equipment, power
between power and water flow and the head water is as transmission line, and other indirect costs. Annual costs
below include the depreciation of equipment, operating and main-
tenance, and replacement costs [2]. The income of the pro-
P ¼ 9:81  g  Q  H ¼ A  Q:H ðkWÞ ject is based solely on the sale of electrical energy.
which
2.2.1. Investment costs
A = (q  g  g)/1000 is a coefficient Civil costs: Consist of the construction and hydro-struc-
g = the efficiency of the turbine/generator tural costs of the project, including a reservoir dam, the
Q = design flow through the turbine (m3/s) water penstock structure, the power house, the tailrace
H = net (effective) head (m) structure, the access road and any future unpredicted costs
q = water density (kg/m3) taken from the preliminary designs of a feasibility study.
g = 9.81 (m/s2) Electro-mechanical equipment costs: Include turbines,
ei = Pi  ti (kW h) as generated energy generators, governors, gates, control systems, a power sub-
epi = Pi  (365  tp) (kW h) peak generated energy station, electrical, and mechanical auxiliary equipment, etc.
em (kW h) monthly generated energy [2,3].
Pi (kW) rated power Power transmission line costs: Include a power transmis-
ti (h) operation hours sion line for delivering generated energy from the power
tp (h) daily peak hours plant to power transmission network. The transmission
P line cost depends on the location, type of existing system
ea ¼ 12 n¼1 emn (kW h) annually generated energy
(overhead line or cable system), and the capacity of HPP
as well as length of transmission lines, which have a very
Due to considering the above-mentioned items in differ-
high effect on the project costs.
ent months and also days, the maximum efficiency of HPP
Indirect costs: Include Engineering and Design (E&D),
and the earned energy can be calculated. Ultimately, the
Supervision and Administration (S&A), and inflation costs
mean gained energy can be estimated. It should be noted
during the construction period.
that due to the section type of the turbine according to
E&D costs: These costs are affected by many parame-
the U.S. Bureau of Reclamation (USBR) standard, and
ters, such as type, size and location where the project is
the other constraints of the turbine in the output and the
being constructed. The E&D costs are usually expressed
net height of the reservoir the calculations are being done.
as a percentage of construction costs, including civil and
Fig. 1 shows the energy calculation algorithm.
equipment costs, and the amount of this percent differs
In addition, with respect to the by-laws of the Iranian
from one location to another. Recently, a case study on
Ministry of Energy regarding energy purchases, energy
these HPPs has shown that this figure could range from
generation in a day must be divided into three different
5% for small and medium sized projects, to 8%, for very
types: peak load (4 h), normal load (12 h), and low load
large sized projects [4,5].
(8 h). The high value of energy is categorized based on
S&A costs: These costs include the purchase of land,
the peak, normal and low loads, respectively, so the plan-
management, inspection and supervision costs, and other
ner can choose different alternatives with the highest energy
miscellaneous costs in the region. Similar to the E&D costs,
generation relative to the load. While coordinating between
the S&A costs are expressed as a percentage of the con-
energy in peak and base states, the technical indices such as
struction costs. A recent case study on HPPs has shown
the plant factor of an HPP should be within a reasonable
that this figure could be anywhere from 6% to 8% [4,5].
and acceptable limit. With respect to the role of a medium
Inflation costs during construction: To precisely calculate
size of HPP (between 10 and 100 MW) in the power system
the investment cost of a project, it is necessary to take into
network, the recommended index sizes a figure between
account the inflation rate during the course of the project
29% and 45% [1] while for large size of HPP this figure
and adjust the investment cost with respect to the inflation
would be lower (25% or less).
rate. The inflation rate of future years should be determined
T i ¼ ea =P i ; ðhÞannual operation hours by obtaining the average of previous years’ inflation rate.
S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402 395

Input Data
• Output & overflow of water
• Water level limits (Reservoir and tailrace)
• Net head

A=Ax
A: Alternative
Ax: xth alternative

n=1
n: statistical year

Calculation of min & max of absorbable power


(Considering the condition of the turbine operation & Hill Chart curve and its efficiency)

Calculation of net output power


Ax= Ax+1 P = 9.81. η. Q . H = A. Q.H

Estimated assignment the number of power generation units

Calculation of total annual energy


j=12
n =n + 1 ea1 = em1 + ... + em12 = ∑ emj
J=1

Y
If n ≤ nmax

N
Y
If Ax ≤ Amax
N

Output:
Different alternatives Installation capacity & average annual energy
nmax
E ave = ( ∑ e ay ) / n max
y =1

Output:
Technical index plant factor for different alternatives
PF = E ave /( P . 8760 ) = T / 8760

END

Fig. 1. Energy calculation algorithm.

2.2.2. Annual costs O&M costs: Include salary/wages of personnel, labor,


In addition to investment costs, annual costs should be insurance, tax, duties, landscape, and consumable materi-
calculated to obtain the net benefit of a project. Annual als. These costs are increased only by the annual inflation
costs include depreciation of equipment, Operating & coefficient. A 5% inflation rate is used in the economical
Maintenance (O&M), and replacement and renovation calculations. The costs which are related to the salary/wage
costs. and consumable materials make up one percent of annual
Depreciation of equipment: In the economical analysis of investment costs, and insurance, tax, duties, charges, and
the project, depreciation and other factors affecting the unpredicted cases are also taken as one percent of annual
equipment should be considered. investment costs. It should be noted that in order to
396 S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402

calculate investment costs, the interest rate during con- Table 1


struction should also be considered [4–6]. Distribution of costs versus construction years
Replacement and renovation costs: The main parts of the Construction years 1 (%) 2 (%) 3 (%) 4 (%) 5 (%) 6 (%)
HPP, such as generator windings, turbine runners and 1 100 – – – – –
other parts will eventually need replacement and renova- 2 77 23 – – – –
tion. To estimate the costs for large and medium sized 3 37 56 7 – – –
4 16 62 18 4 – –
power plants, the percentage of renovation and replace- 5 9 49 30 9 3 –
ment should be determined for different sections sepa- 6 6 31 40 15 6 2
rately [2,3].

2.2.3. Income and benefits ering the investment value. For example, according to
There are two benefits for the HPPs: (1) tangible bene- Table 1, for a 3-year construction project, the percentages
fits; (2) intangible benefits. The tangible benefit is the sale of the cost in each year are as follows: 37% of capital in
of electrical energy. Based on approval by Iranian regula- the middle of the first year, 56% in the middle of the second
tors, the purchase of electrical energy from HPPs has been year, and 7% in the middle of the third year.
guaranteed by the Iranian Ministry of Energy in which the
purchase will be done from four sectors: (1) the govern- 2.2.5. Economical calculation
mental sector without transmission lines; (2) the govern- According to the previous sections, an algorithm has
mental sector with transmission lines; (3) the private been developed for the economical calculation. Fig. 2 shows
sector without transmission lines; (4) the private sector the economical calculation algorithm. In this algorithm the
with transmission lines. In each case, the electrical energy economical indices are such as benefit to cost (B/C), net
purchasing rates are being provided in different months present value (NPV), expenses for each kilowatt hour ($/
of the year based on the peak load (4 h in a day), normal kW h), depth coverage ratio stands for (DCR) and return
load (12 h in a day) and low load (8 h in a day). Meanwhile, on equity stands for (ROE). Some of the required equations
for the private sector, different purchase rates are being in the analysis are given in the Table A.1 of the appendix.
presented with four options, namely, 100%, 75%, 50%,
and 25% of private investment. Due to peak hours of 2.3. Reliability calculation
energy consumption, the purchasing rate would be more
attractive for the producer of energy. The annual infla- The reliability index of Loss of Load Expectation
tion-purchasing rate is being considered to be 5% in the cal- (LOLE) is calculated using the Monte Carlo simulation
culation. The intangible benefits cover the positive [7,8]. This method is one of the strongest engineering tools
environmental effects, flood control, agriculture and irriga- that enable us to perform a statistical analysis of the uncer-
tion, fish farm pools, camps and recreation centers which tainties involved in engineering problems. This method is
eventually turn into quantitative values. The intangible very applicable in solving complicated problems where
benefits are not included in this economic analysis of the many random variables are involved in non-linear equa-
project, but naturally a more desirable result will be tions. The Monte Carlo analysis can be imagined as a sim-
obtained for the economic indices when taking these fac- ulation method, which replaces a practical execution with a
tors into account [2–4]. computer simulation. The basis of the Monte Carlo analy-
sis is to produce a series of random numbers. The produced
2.2.4. Financial and time specification homogenous random numbers retain the same characteris-
Capital depreciation period for construction 50 tics of the probability of their occurrences in the selected
costs: years domain between 0 and 1. In this method, ‘‘n” random num-
Replacement and renovation of electro- 25 bers are first generated for each one of the existing random
mechanical equipment: years parameters in the given equation and this equation is then
Duration of construction: 3 years solved for each single random selected number. Finally,
Annual interest rate: 6–20% ‘‘n” values are obtained for the concerned equation by
Annual inflation rate: 5% using the related relations to obtain the statistical informa-
tion of the histogram sample. It should be noted that as the
Table 1 shows the capital distribution during the invest- number of iterations increase, the answer would more clo-
ment period. This table presents construction time from 1 sely approach the real value. With a decreasing probability
to 6 years [2–4] in this table, the construction costs are of not supplying electricity to subscribers (customers) there
expensed in the relevant subsequent years. Thus, with the is a direct relation to an increase in the number of genera-
effects of interest and inflation, the costs of the subsequent tion units and as a result, an increase in investment design
years can be predicted. Social and economic factors could status and/or utilization. More investment will definitely
also be included in this calculation. When execution activ- lead to an increase in utilization costs, which should be
ities begin, the annual payments should be expensed in the reflected in the tariff of energy sale. Subsequently, eco-
midyear, in order to lessen the effect of inflation, thus low- nomic limitations would lead to a decrease in the reliability
S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402 397

Input Data
• Installation Capacity
• Total annual Energy (Base & Peak)
• Sale of Energy

P1 = Estimation of total Construction Costs


• Hard Costs
• Soft Costs

i= ix

i (1 + i)
n x
C= ∑ Ct (1 + i)
x
Acc=P1
(1+ i)n − 1 t =1

i (1+ i)
n
Acc: Annual uniform costs of P1
A1=C
n: life cycle of project
(1+ i)n − 1
AO&M= 0.02 × A1
j=1 C: Construction cost including interest rate
j: Number of life cycle year of project Ct: Distribution of construction cost
x: Number of construction years
A1: Annual uniform costs
AO&M: O&M costs
ix = 6%, 8%,
10%, 12%,14%, Tc= Acc + AO&M
Tc: total annual cost
16%, 18%, &
20%
Calculation of
senility analysis for
interest rates TEP = purchase × total annual energy
TEP: total energy purchase

PWF= 1
(1 + i) j Tc = Acc + AO&M + Rc
Rc: Replacement & renovation cost
PWC= Tc × PWF
PWB= TEP × PWF
j=j+1 PWS= PWC - PWB
PWF: Present worth factor
PWC: Present worth costs
PWB: Present worth benefits
PWS: Present worth (costs – benefits)

N
if j ≠ n / 2 = 25

Y Y
If j ≤ n = 50
N

Output
Economical indices, B/C, NPV, $/kWh, DCR, ROE

END

Fig. 2. Economical calculation algorithm.

of the system. Therefore, there could be a compromise ity = 100%). The LOLE calculation algorithm, using the
between reliability and economic restrictions that could Monte Carlo method, is in Fig. 3 [8].
lead to difficult managerial decisions in both the design
and operational stages [7,9]. In general, a study of the reli- 3. Case study
ability of the three sections of generation, transmission and
distribution of power systems should be done. In this The case study of a medium size of HPP ‘‘Bookan” dam
paper, only generation reliability is being considered to is presented. This HPP is located in the West Azarbaijan
meet the load demands. The transmission and distribution Province of Iran. This HPP is the reservoir type and the
reliability have been assumed to be perfect (reliabil- goal is to determine the suitable installation capacity.
398 S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402

Table A.1
Shows summary of interest formulas for economic evaluations
Name of formula To find Given Equation Use
n
Single compound amount F P F = p(1 + i) Find a future sum equivalent to a present sum
1
Signal present worth P F P ¼ F ð1þiÞ n Find a present sum equivalent to a future sum
n
Uniform series compound amount F A F ¼ A ð1þiÞi 1 Find a future sum equivalent to a uniform series of end-of-period sums
Uniform sinking fund A F A ¼ F ð1þiÞi n 1 Find a uniform series end-of-period sum equivalent to a future sum
n
ið1þiÞ
Uniform capital recovery A P A ¼ P ð1þiÞ n
1
Find a uniform series end-of-period sum equivalent to a present sum
n
Uniform series present worth P A P¼ A ð1þiÞ
ið1þiÞn
1
Find a present sum equivalent to a uniform series of end-of-period sums

Variable definitions: P is a present sum of memory F is a future sum of memory at the end of N periods i is an interest or discount rate per period n is the
number of interest or discounting periods A is a end-of-period payment (or receipt) in a uniform series of payments (or receipts) over N periods at i interest
or discount rate.

λ i , μ i , PGi ; i = 1,..., G
Input PLmin , PLmax , iteration

Drawing of load duration curve

μi
Ai = ; i = 1,..., G
μ i + λi

n=1 , i = 1, pt = 0 , LOLE’= 0

Random selection of one day in year and the related load of it (PL)

Producing a random value between 1 & zero (Ri)

N
Ai ≥ Ri ?
Y
Pt = Pt + PGi

N
i= G ? i=i+1
Y
Y
Pt ≥ PL ?
N
LOLE’ = LOLE’ +1

i=1 N
n=Iterations ?
n=n+1
Pt = 0
Y

LOLE =
LOLE '× 365
Iterations
LOLE days [ years ] Output

Fig. 3. The LOLE calculation algorithm, using the Monte Carlo method.

3.1. Energy calculation of the Bookan HPP case, the monthly net output (output plus overflow) in res-
ervoir and net height in the reservoir for different months
The simulation has been done for a period of 33 years which have been given in the followings (the difference
according to the data extracted from 1964 to 1997. In this between the level of water in reservoir and the level of axis
S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402 399

of the turbine has been extracted in these periods) have Table 2


been extracted for this duration. According to the special Obtained annual energy for different alternatives of Bookan HPP
specification of the plant and the feasibility study, different Alternative The rated power The rated The mean Plant
alternatives have been considered, based on the expertise number and number of units power annual factor
(N  MW) (MW) energy (PF) (%)
judgment. In these alternatives, the calculated energy is (GW h)
based on the different number of the vertical Francis tur-
1 2  2.5 5 25.33 0.58
bines. Ultimately, the annual energy is being drawn after 2 2  3.75 7.5 36.80 0.56
getting mean value of them [10]. 3 25 10 47.23 0.54
P 4 2  6.25 12.5 57.67 0.53
ea1 ¼ em1 þ    þ em12 ¼ n¼12
n¼1 emn [kW h] the first annual 5 2  7.5 15 67.26 0.51
energy in year 1964 6 2  8.75 17.5 76.03 0.50
ea2 [kW h] the second 7 2  10 20 83.41 0.48
annual energy in year 8 2  11.25 22.5 89.20 0.45
1965 9 2  12.5 25 93.19 0.43
10 2  13.75 27.5 96.52 0.40
eyearnumber 11 2  15 30 99.40 0.38
ea33 [kW h] the last annual 12 3  10 30 99.73 0.38
P energy in year 1997 13 2  16.25 32.5 101.71 0.36
Eave ¼ ð y¼33
y¼1 e ay Þ=33 [kW h] average annual 14 2  17.5 35 103.65 0.34
energy in 33 years 15 2  18.75 37.5 105.31 0.32
16 3  12.5 37.5 107.99 0.33
17 2  20 40 107.64 0.31
The maximum level of water in the reservoir is about 18 4  10 40 110.85 0.32
19 2  22.5 45 112.52 0.29
1421 m, and the installation level of turbines is 20 3  15 45 115.40 0.29
about 1380 m. Therefore the max height of the HPP is 21 2  25 50 116.14 0.27
about 41 m. According to the recommendations given by 22 4  12.5 50 119.80 0.27
the USBR standards, the constraints of vertical Francis 23 3  17.5 52.5 120.28 0.26
turbine are as below 24 3  20 60 124.55 0.24
25 4  15 60 127.43 0.24

The minimum admitted flow of turbine is about 40% of


the designed rated flow;
The maximum admitted flow of turbine is about 110% Value of DCR index
of the designed rated flow; 3
The minimum operational height of turbine is about 2.5
65% of the designed operational height; 2
The maximum operational height of turbine is about
DCR

1.5
125% of the designed operational height;
1

According to the above-mentioned points, the following 0.5


results have been extracted: 0
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49

The minimum height is about 21.5 m; Year


The nominal height of is about 32.5 m; Fig. 4. DCR index value for 50 life cycle of Bookan HPP, interest rate:
The maximum permanent overload of the generators is 8%.
about 10%;
The accessibility of the HPP has been considered to be
98%;
Value of ROE index
The results associated with different alternatives are 1
given in Table 2.
0.5

3.2. Economical calculation of the bookan HPP 0


ROE

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49
The calculated civil, equipment and total investment -0.5
costs of the Bookan HPP have been extracted from the fea-
-1
sibility study. These costs for a mean duration of HPP is
about US$1000/kW (US$600/kW for civil works and -1.5
US$400/kW for the equipments). Year
The economic analysis has been carried out consider- Fig. 5. ROE index value for 50 life cycle of Bookan HPP, interest rate:
ing costs and obtained incomes, according to the given 8%.
400 S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402

Table 3
Economic indices of different alternatives with private section contribution for Bookan HPP (the inflation rate is 0.2% for sales of energy and is 5% for
annual cost)
Alternative The rated power and number of The rated Interest rate (8%) Interest rate (10%)
number units (N  MW) power (MW)
Final costs B/C NPV Final costs B/C NPV
(USCent/kW h) (US$million) (USCent/kW h) (US$million)
1 2  2.5 5 1.70 2.28 7.41 2.11 1.82 4.63
2 2  3.75 7.5 1.76 2.21 10.49 2.17 1.76 6.46
3 25 10 1.82 2.12 13.02 2.25 1.70 7.86
4 2  6.25 12.5 1.87 2.07 15.57 2.31 1.66 9.28
5 2  7.5 15 1.93 2.02 17.67 2.37 1.61 10.34
6 2  8.75 17.5 1.99 1.95 19.34 2.45 1.56 11.08
7 2  10 20 2.07 1.87 20.20 2.55 1.50 11.19
8 2  11.25 22.5 2.18 1.78 20.41 2.69 1.43 10.78
9 2  12.5 25 2.31 1.68 19.59 2.86 1.34 9.58
10 2  13.75 27.5 2.45 1.58 18.43 3.04 1.26 8.11
11 2  15 30 2.60 1.49 17.08 3.21 1.19 6.50
12 3  10 30 2.60 1.49 17.08 3.21 1.19 6.50
13 2  16.25 32.5 2.75 1.41 15.34 3.40 1.12 4.58
14 2  17.5 35 2.92 1.33 13.45 3.60 1.06 2.54
15 2  18.75 37.5 3.05 1.27 11.78 3.76 1.02 0.68
16 3  12.5 37.5 3.05 1.27 11.78 3.76 1.02 0.68
17 2  20 40 3.17 1.23 10.44 3.90 0.98 0.92
18 4  10 40 3.17 1.23 10.44 3.90 0.98 0.92
19 2  22.5 45 3.40 1.14 7.25 4.20 0.91 4.53
20 3  15 45 3.40 1.14 7.25 4.20 0.91 4.53
21 2  25 50 3.65 1.06 3.54 4.51 0.85 8.55
22 4  12.5 50 3.65 1.06 3.54 4.51 0.85 8.55
23 3  17.5 52.5 3.76 1.03 1.83 4.64 0.82 10.44
24 3  20 60 4.11 0.94 3.88 5.07 0.75 16.58
25 4  15 60 4.11 0.94 3.88 5.07 0.75 16.58
The bold values shows the best choice alternative.

algorithm. The economic basis is considered so that the PG = 10 and 15 MW rated capacity of
investor may receive a loan from a financial source and generating units
pay it back with a specific interest rate through annual N = 50 (years) HPP’s life time
installments during the utilization stage. The economic k = 1/25 (f/years) failures rate
analysis has been calculated for fully governmental, fully l = 2 (r/years) repairs rate
private and governmental-private financings, then the
economic indices including B/C, NPV, DCR, ROE (see
Figs. 4 and 5) and US$/kW h of energy have been calcu-
lated. The interest rate has been settled as 8% and 10%
in order to attract foreign investment in developing 16
countries. This rate is considered a normal rate by global
financial institutes for economic feasibility studies of 14

water resource development, and the results have been


12
presented in Table 3. In all the cases the effect of interest
rate changes is studied by sensitivity analysis. As it is
LOLE (days / year)

10
shown in the table, the economic indices of different
alternatives with private section contribution have been 8
brought into calculation or Bookan HPP with the infla-
tion rate is 0.2% for sales of energy and is 5% for annual 6
cost.
4

3.3. Reliability calculation of the bookan HPP


2

To study the effects of an increase in the number of gen-


0
eration units and subsequently, an increase in the cost on 0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

the LOLE index, various combinations of generation units Number of trials


are being used for the Bookan HPP, each with the follow- Fig. 6. The graph of calculated LOLE with the Monte Carlo method for
ing specifications: option 4 (min and max load between 10 and 30 MW).
S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402 401

Table 4 US$17.08 million, a USCent/kW h equal to 2.60 and the


Index of reliability for the Bookan HPP suitable loss of load expectation (LOLE) index of 10
LOLE index (day/year) Minimum load Maximum load days/year. By increasing the installed capacity, the LOLE
(MW) (MW) decreases so that even with a 3  10 MW installation
Option Option Option Option
1 2 3 4 capacity (option 4) the failure will reach minimum and will
101 10 7.2 6.9 5 25 even become a zero value. It should be noted that with such
132 9.5 10 6.5 10 25 a situation, more expense for generating a kW h electrical
180 100 10 12.6 10 30 energy is required, obviously not desirable. Furthermore,
230 130 11 15 15 30
the PF and the economic indices are also not suitable. With
an installation capacity of 2  15 MW, the number of fail-
ures, PF and other economic indices are very relatively pro-
The minimum and maximum load values are consid-
portional and the costs of a kW h energy is also at an
ered based on the loads in different years. The specifica-
acceptable limit.
tions of the loads are as follows (a sensitivity analysis
Furthermore, a sensitivity analysis of interest rate from
has also been performed on the load values for more
6 % to 20 % have been calculated and the results are shown
assurance):
 in Table 5. As it is shown in the table, Economic analysis
PLmax ¼ 35 ðMWÞ average maximum load results on alternative no. 11 with different interest rates
PLmin ¼ 5 ðMWÞ average minimum load with the inflation rate is 0.2% for sales of energy and is
5% for annual cost and the index of reliability for the Boo-
There are 2000 iterations for calculating the LOLE in
kan HPP.
the Monte Carlo algorithm. Installing different numbers
of generation units created the following possible options;
8 4. Conclusion
> Option1 2  20 MW
>
>
< Option2 2  12:5 MW 1. One of the most important issues in designing an HPP is
> Option3 2  15 MW to determine the suitable installation capacity. In this
>
>
: paper, the methods of energy and the economic and reli-
Option4 3  10 MW
ability calculation have been presented. This algorithm
LOLE calculation with the Monte Carlo method for has been studied for a sample HPP.
option 4 has shown in Fig. 6. 2. The economic indices have been calculated based on the
The results of these calculations are listed in Table 4. As developed algorithm and conducting a number of sensi-
it is shown in the table, the index of reliability for the Boo- tivity analysis.
kan HPP has been calculated. 3. The reliability indices have been calculated by employ-
ing the Monte Carlo method based on an algorithm.
3.4. Results analysis 4. The calculated installation capacity has been obtained
by establishing a compromise between the technical,
With respect to the results presented in Tables 2–4 and economic and the reliability indices.
studying the technical, economic and reliability indices, 5. The aforementioned method has been applied to a sam-
the alternative no. 11 is clearly the best option, with a ple HPP named ‘‘Bookan” by comparing the plant fac-
30 MW installation capacity, an annual energy of tor (PF), the B/C, NPV, USCent/kW h, and the
99.40 GW h, a plant factor (PF) of 38%, a B/C that equals reliability index LOLE, so the optimal installation
1.49 (for inflation rate equal 8%), a NPV equal to capacity of 30 MW has been obtained.

Table 5
Economic analysis results on alternative no. 11 with different interest rates (the inflation rate is 0.2% for sales of energy and is 5% for annual cost)
Interest rate(%) Unit 6 8 10 12 14 16 18 20
Energy cost USCent/kW h 2.02 2.60 3.21 3.84 4.47 5.11 5.75 6.39
Benefit cost ratio (B/C) and (P/t = 1) 1.94 1.49 1.19 0.98 0.83 0.72 0.64 0.57
Benefit cost ratio (B/C) and (P/t = 0.75) 1.78 1.37 1.09 0.9 0.77 0.66 0.58 0.52
Benefit cost ratio (B/C) and (P/t = 0.5) 1.62 1.25 1 0.82 0.7 0.6 0.53 0.47
Benefit cost ratio (B/C) and (P/t = 0.25) 1.46 1.13 0.9 0.74 0.63 0.55 0.48 0.43
Benefit cost ratio (B/C) and (P/t = 0) 0.73 0.56 0.45 0.37 0.31 0.27 0.24 0.21
Net present value (NPV) and (P/t = 1) US$million 34.17 17.08 6.50 0.51 5.42 9.04 11.80 13.99
Net present value (NPV) and (P/t = 0.75) US$million 28.41 12.84 3.20 3.18 7.66 10.96 13.49 15.49
Net present value (NPV) and (P/t = 0.5) US$million 22.64 8.60 0.10 5.86 9.90 12.89 15.18 16.99
Net present value (NPV) and (P/t = 0.25) US$million 16.88 4.35 3.40 8.53 12.15 14.81 16.86 18.49
Net present value (NPV) and (P/t = 0) US$million 9.74 15.23 18.62 20.88 22.50 23.71 24.65 25.41
Notice: P/t: Ratio of private section investment to total in percent. B/C: Benefit cost ratio. NPV: Net present value.
402 S.M.H. Hosseini et al. / Electrical Power and Energy Systems 30 (2008) 393–402

Appendix A [4] Hosseini SMH, Forouzbakhsh F. Determination of optimal instal-


lation capacity of small hydro-power plants considering technical
economic and reliability indices, energy policy. Elsevier J
See Table A.1. 2005;33(15):1948–56. October.
[5] Engineering and design hydropower, handbook, vol. II. Washington,
DC: U.S. Army Crops Engineering, Department of the Army; 1985.
References p. 1–26 [chapter 8].
[6] International Atomic Energy Agency. Expansion planning for
[1] Energy Ministry of China. Hydro power plant hand book Chinese electrical generating systems. A guide book. Vienna; 1984. p. 155–71.
standard; 1990. p. 180–5. [7] Billinton R, Allan R. Reliability evaluation of power systems. 2nd
[2] Hosseini SMH, Forouzbakhsh F, Vakilian M. Economical analysis ed.; 1996. p. 400–40 [chapter 12].
of financing on medium and small hydro power plants Hydro2005. [8] Billinton R, Allan R. Reliability evaluation of engineering systems.
In: International conferences on hydropower and dams Villach. 2nd ed.; 1987. p. 372–400 [chapter 13].
Austria; October 2005. p. 17–20. [9] IEEE. IEEE recommended practice for design reliable industrial and
[3] Iran Water and Power development resources Company (IWPCO). commercial power systems (guide book); 1985.
Studies management office (2003) economic regulation of medium [10] Ministry of Energy of Iran. Iran water and power development
hydro-power plants. Ministry of Energy of Iran, Small and Medium resources Company (IWPCO). Medium and small-size power plants
Sized Power Plants Department; 2003. report of bookan power plant; 2002.

You might also like