Change Hours/Day in Calendar

but keep Activity Duration


unchanged in Primavera P6

We make a schedule using 8 hours/day calendar.


Now we want to change to 10 hours/day calendar.
We can see the Activity Duration now change to 8 days and Project
Completion date is now earlier.

How can we change Hours/day but keep duration unchanged?

I will show you how to do it.


Go to Tool -> Global change. Click New.

Enter Data as below picture:


Click on Change button. Primavera will show us a Preview. Then click on
Commit Change
Now we can see Activity Duration change back to 10 days and Project
completion date is the same with original one.
 