Professional Documents
Culture Documents
Pipework Installation Procedure
Pipework Installation Procedure
procedure
Hägglunds products
Replaces:
Instruction -
RE DD000*****/02.2015 English
2/6 Pipework installation procedure
1 Purpose
1.1 General
To ensure that all drives of Hägglunds pipe installations conform the specified
requirements.
2 Scope
2.1 General
This procedure applies to all pipe work installed for and by Bosch Rexroth Mellansel
AB
3 Responsibility
It is the responsibility of the sales engineer to ensure this instruction is carried out
as per the procedure.
4 Procedure
4.1 Material
Generally, all equipment should be selected from high quality materials, designed to
operate under the conditions and pressures required by the drive system.
Recommended standards:
4.4 Hoses
a. To avoid damage caused by vibrations it is appropriate for the power unit
and motor to be connected to pipes by means of hoses.
The hoses must be short and have the smallest possible diameter in order
to obtain a small compression volume. Allowance must be made for the
velocities, as listed under ”Pipe Sizes”. Allowance must also be made for the
minimum permissible bend radius as according to the data provieded by the
hose manufacturer.
b. All hoses shall be cleaned using the ”CompriTec” cleaning system. The
method of a pull through rag with solvent is not recommended.
acid with hot water (70-90ºC). Surface oxides and mill scales can
be removed by continously agitating the pickling solution around the
surface and by circulating it around inside the pipe.
3. The pickling time should be between two to three hours. The pipe
should be lifted out of the solution at least three times every hour.
4. After pickling, the pipe should be washed in hot water (70-90ºC) for
approximately 15 minutes.
5. The pipe should then be neutralized in an alkaline solution of 0.5%
Caustic soda and 0.75% Trisodium Phosphate in hot water (70-90ºC).
Neutralization time in this solution should be 30 minutes.
6. After the pipe should be washed in hot water (70-90ºC) for
approximately 15 minutes.
7. The pipe should then be dried and anti rust compound such as Rust
Veto from E.F. Houghton and Co. quickly applied inside and outside the
pipe.
8. If the pipe is stored for any period of time, the ends must be covered
with plastic plugs or similar.
4.6.1 Pipes.
a. The pipes can be pre-cleaned at the workshop. After the ends are flared
and flanged they are to be blown with filtered and dry air of standards workshop
cleanliness level (ISO 8573-1:1991, 4/5/4. Filtration of 15 µm, dew poiont of +7ºC,
oil content of max 5 mg/m3). Plastic foam cleaning plugs are then blown through the
pipes (CompriTec system or equivalent).
b. The pipes are to be rust protected inside and out then capped at both ends
with protective plugs and or heat shrink plastic film.
c. Once the pipes are site installed the overall system undergoes an oil flush in
order to reach the required cleanliness level for the system. See 4.8.
4.6.2 Hoses
a. Prior to assembly of fittings, the hoses are inspected for any visual external
or internal flaws, cuts or damage. The required hose length is then
measured, cut, cleaned and blown with filtered and dry air of standard
workshop cleanliness level. After this preparation, the fittings are crimped
on, to complete the assembly. Plastic foam cleaning plugs are blown
through the complete hose assembly.
b. Hoses are delivered to site with rust protection and with protective plastic
plugs in both ends.
5 Documentation
Witness documentation is required if welded pipe is used to qualify procedural
adherence.