Method Statement for Tower Erection & Stringing within Switchyard
METHOD STATEMENT @
DOCUMENT TITLE
ACCESSIBILITY.
coneibenrial []
‘Approved By
Ajendra Agarwal
M, Sivaprosad
ResrRicreD CI controueo CI UNCONTROLLED 6
Prepored By sunilOubey Sa 0
At Noyok
Reviewed By Sushil Krishnan
S.PDas
G.$ Thokur GE T&D India Limited
DATE
NAME
SIGNATURE
Doc No: sHeeT | SH. END
1 1
This document is the exclusive property of GE T&D India Limited and shall not be used, copied or communicated to third
parties without prior authorization
Pago totMETHOD STATEMENT @
Amendment Sheet
REVIND.
PURPOSES OF THE MODIFICATION.
first Issue with Derogation - Applicable Til 30" Nov 2017
Lifting & Stringing arrangement with Winch Machine
TABLE OF CONTENTS
1.0
2.0
10 Purpose
2.0 Scope of Work
3.0 Definitions
40 Plant & Equipments
5.0 Safety
60 Receipt & Storage
7.0 Site Inspection
80 Planning & Pre-requisites
9.0 Installation Procedure
10.0 Responsibilities
110 Declaration
Purpose
1.1 To ensure the Stringing Works, Lifting of Tower & Beom parts is executed Safely and
12
13
in accordance with EHS guidelines and contract requirement.
To ensure implementation of approved Field Quality Plan,
This Method Statement is Only for Stringing & Lifting works within Switchyard area
and shail not be used for Transmission Line works or any works outside switchyard
area
Scope of Work
21
22
23
2m
Material Hondiing ond Storage
Inspection of Moteriat
Stringing Works
Lifting Works
Page 20423.0
4.0
5.0
QD
alee STATEMENT @
Definitions
31 GEPM GE Project Manager
32 GESM GE Site Manager
33 GESE GE Site Engineer
34 GESO GE Safety Officer
35 CSM Contractor Site Manager
36 CSO Contractor Safety Officer
37 CSE Contractor Site Engineer
38 RA Risk Assessment
39 FOP Field Quality Plan
3.10 EKD Erection Key Diagram
Plant & Equipment
4l
42
43
4a
4s
46
ar
48
49
410
411
412
413
414
415
Safety
51
52
Motorised Winch Machine ISWL - 5 Ton or above}
Tractor with Trolley - 01. No {not for pulling/pushing works)
4/2 Sheave Pulley (STon SWL ~ 02 Nos (with TPH
Single Sheave Pulley (5Ton SWLI - 01 No (with TPI)
Come Along Clamp (5 Ton SWL or Suitable for respective Conductor)
D~ Shackle (5 Ton SWL) - 02 Nos {with TPH
Wire Rope Pulley (Min 12mm of 1,75 Ton SWU (with TP)
Spanners Set / Wrench Set
Cable Drum Jack
F15 / Hydra - 12 T/ 14 T (with trained Banksmen)
LOTO Kit along with VAV Equipment
Personal Protective Equipment IPPE -15,CE,EN standard only}
Collective Protective Equipment (CPE -IS,CE,EN standard only)
Rescue Kit
‘12mm Dia Wire Rope with TP
All workforce and Engineers exposed to hazards related to "Work at height” shall
have valid “Green Safety Poss’ & if exposed on Electrical Risk shall have valid
"RED Safety Pass".
All the workers involved in the job must have gone through induction training
followed by the job specific training.
Page sot 12METHOD STATEMENT @
6.0
53 GESE shall ensure availabilty of Safety barriers, warning tape, signage, and
watchman lif required), scaffolding / CPE's / test certificate of Winch Machine
Hydra, Pulleys, D - Shackles, Wire Rope, Licence of Tractor Operator,
Competency of Winch Machine Operator, etc. in coordination with GESO.
54 Physical verification of the lifting equipment and tools/tackles shall be ensured
at site before commencement of the job. Tagging and color coding of the samme
shall be ensured.
55 GESM shall conduct Risk Assessment & preparation of SOD jointly with GESO and
shall ensure the communication of hazards & implementation of corrective
actions to the Working Team.
5.6 Lifting plan shall be prepared and communicated. Lifting Permit to be taken.
5.7 Area beneath the suspended load shall be protected for restricting the access of
other workers in the vicinity
58 Work Permit for Work at Height” & "Lifting Activity” shall be obtained prior to the
activity commencement
59 Prior to the commencement of any activities, Tool Box Talk on the hazards
related to an activity shall be delivered to workforce jointly by GESE & CSO.
5.10 Work shall be carried out in compliance with GE Operating Instructions, EHS &
Project EHS Plan.
5.11 On-site emergency response plans shall be prepared and communicated with
all the stake holders
With the change of working condition, the procedure shall be amended and persons
shall be trained accordingly.
Receipt & Storage
6.1 Receiving & Storage of the material shall be done strictly as per Approved FOP.
62 Ensure that Insulator String / Long Rod is handled carefully and stored separately.
63 Check Clamp and Connectors received as per Approved EKD_
64 Check the quantity of conductor received from Vendor, damages to drums /turns
of conductor & conductor ends are sealed properly.
65 Ensure proper use of Equipment like Hydra / Crone shall be used for loading /
unloading the Conductor Drum on / from to the trolley.
66 Old generation Hydra is a very dangerous equipment. It topples rapidly. Use it
carefully with trained Banksmen only, No tandem lfting/shifting is allowed with it
Try to use F15 crane.
Page ot 12METHOD STATEMENT @
7.0
8.0
67
68
69
6.10
Ensure that after loading the Conductor drum on Tractor Trolley, drum is tied
properly to ensure No Toppling of the same.
Ensure availability of Drum Jack at site for unwinding the conductor, Conductor
Drum should always be rolled in the direction of arrow marked on the drum,
Strictly follow the instructions given by the Supplier for unloading & handling of
ony materia
Maintain all records as per approved FOP and intimate to HO immediately
for damages / defects, if any.
Site Inspection
7
72
73
Before starting any Stringing Activity, carry out thorough inspection of site and
ensure following;
Ensure to make Lifting plan (Refer GE crane manual 2003),
7.1.1 Check for torque tightness of Gantry Structure / Support Structure,
7.1.2 Check all T&Ps as mentioned above are available and are in good state of
condition to use.
7.13. Check and ensure the area is dry. Stringing ‘activity shall be avoided
during rain or in wet conditions,
7.1.4 Check the around stability / compactness before using crane on it.
7.15 Check and ensure that anchoring points, if provided are firm to the
ground,
7.1.6 In case of non-availability of anchoring point, anchoring shall be done
with the Tower foundation and the foundation shall be checked for
firmness before being used
Before Starting any Lifting activity, check site and ensure following:
7.21 Check all T&Ps os mentioned above and are in Good state of condition
and have valid TPI, if required,
7.2.2 Check and ensure anchoring points, if provided are firm to the ground.
7.2.3. In case of non-availability of anchoring point, anchoring shall be done
with the Tower foundation and the foundotion shall be checked for
firmness before being used,
Specific checks to be carried out for below scenarios used for Lifting or Works:
Planning & Pre-Requisites
The following are the pre-requisites before start of Stringing / Lifting Activity.
81 Ensure the availability of approved Method Statements for the above activities,
82 HIRA & PTW for the above activities shall be jointly prepared by GESM, GESE, GESO &
CSM and communicated to the workforce.
Pogo of 12METHOD STATEMENT @
83 Ensure, check and obtain necessary site clearance,
84 Ensure the availability of all Tools and tackles as Listed above and other material,
85. Ensure all Tools, required for Stringing / Lifting activity, are tested and certified by
Approved Inspection Firms and necessaty certificates are available.
8.6 Ensure Lifting Plan and RA associated with work should be prepared in
consultation with sag-tension chart for the said span prior to commencement of the
work, jointly with GESM, GESO & CSM and is communicated to workforce.
87 Ensure all requisite Permits are obtained
88 Ensure availabilty of approved Sag - Tension Chart.
Installation Procedure
Stringing / Lifting activity shall be executed using ST Winch Machine with 12mm Dio Wire
rope or Manual with 24mm Dia PP rope only. Do not use PP rope with Winch Machine.
Keep a close eye on Pulley movement during operation. Standord pulley to be used.
Colour coding to be done. GESM along with GESO & CESM shall jointly conclude for the
best methodology to be adopted with necessary check points as detolled in each
methodology,
Before start of any stringing / lifting activity, maximum pull required for Stinging / Lifting
shall be calculated w.t the load
For Lifting works, below details are required to get maximum Pull required:
1. Wire rope to be used for Pulling ~ 122mm
SWI of above Wire Rope ~ 2.5 Ton (Vertical Hitch)
Max Length of Wire rope for the highest part of 765kV Gantry Tower (Section 4 / Peak)
= (40Mx4 ~ ffor Double Sheave Pulley] + (50 ~ (Pulling Lengthil= 210M
Weight of Wire rope - 0.7 Ko/Mtr
Total weight of wire rope - 0.7 x 210 = 147Kgs
2. 2 Sheave Pulley with latch (5 Ton SWL)- 02 Nos
3. D-Shackle (5 Ton SWL} - 03 Nos
4. Wire Rope - 12mm for tying Derrick with the Tower Leg - 03 Nos at an equal distance
‘Note: 24mm Dia PP Rope with TP! to be used for manual erection with all barricading, etc.
Page 6 of 12METHOD STATEMENT @
Maximum Pulling load including above Fabricated members and lifting accessories will be
between 15 T to 2 T {To be calculated from BOM)
Total Load = Line Pull x Angle Factor {@ 30Deg, Angle Factor is 193. @ 90Deg AF - 141, @
120Deg AF - 1)
Pull Required = Weight To be Lifted / Mechanical Advantage (Mechanical of 2 Sheave Pulley is
FA)
Calculate the load of each section prior erection and maximum load should not exceed 2
‘Tons at any point of time.
Pulling of the above assembly sections shall be done using Manual or Winch only. Use of
Tractor/Hydra as pulling equipments strictly prohibited.
Fix spacers as per specification/ drowing. Use horizontal ife ine (12mm Wire rope} during spacer
fixing and jumpering / droppers fixing and if practical use MEWP for same activity
Papo 70112METHOD STATEMENT @
‘Typical Erection Methodology for Erection of 765KV Gantry Tower
Section - 3
Section - 2
Section - 1
Erection of 765kV Gantry Tower is divided in various Parts as highlighted in the above drawing,
‘A, Erection of Section - 1
1. Erection of Section -1, shall be carried out using F-15 or similar equipment. All Lifting
accessories and Lifting Equipment shall undergo valid Third-Party inspection
certification.
2. Method Statement for Section -1 shall be similar to Method Statement used for
erection of Low Height Equipment Lattice Structure.
Page wot t2BE
METHOD STATEMENT @
8. Erection of Section - 2
1 For Erection of Section - 2 as highlighted in the above picture of Gantry Tower,
Derrick shall be used. Detailed Load Calculation of Derrick and details of other Lifting
Accessories ta be used for this are as mentioned below.
Weight of Section - 2 shall be calculated as per 8OM without legs.
Legs of this section shall be erected using Derrick separately. Once all legs are
erected, assemble section - 2 each side separately,
Main Members (with step bolts fitted on one of the members) of the bottom section are
placed on foundation and cross bracing are assembled. Next section main members (with
step bolts fitted on one of the members| are lifted one by one manually or with Winch
machine arrangement, Remaining sections are erected in the same manner,
C. For erection of balance Section - 3, follow the steps used for Erection of Section - 2.
D. Erection of Section - 4 / Tower Peak or Cross Arm.
1. Weight of Fabricated members of above Tower Peak or Cross Arm varies between
13T to 15 Ton.
All Lifting Accessories and Derrick as mentioned in Erection Methodology of
Section ~ 2 shall remain same for the erection of Tower Peak / Cross.
Maximum Pull required for the above section will be approx 1000 Kgs.
Tower Peaks assembled on ground and lifted either manually or with Winch Machine.
Erection Procedure for Gantry Beam
For Erection of Gantry Beam, two sides of Beam are assembled on ground and lifted from both
Gantry Tower with 2 Winch machines or manually using 2 Sheave Pulleys tied on Top of Gantry
Tower.
Page wotMETHOD STATEMENT @
Complete assembled one side of Beam shall be lifted from both sides parallelly to avoid any jerks.
Proper co-ordination shall be maintained to ensure smooth operation.
Procedure for Stringing works. to get maximum Pull required:
In addition to the above detai's, additional detoi’s os mentioned below are required for stringing
‘works to calculate maximum Pull required,
1
2.
3.
4
5. Weight of String Hardware
Gantry Span Length
Weight of the Conductor
No. of Conductor required for Stringing
Weight of insulator String / Long Rod Insulator
GESM/GEEE/GESO shall ensure that above details are within permissible limit as described above.
Typical Picture for Winch Machine - ST
‘Typical Anchoring Arrangement of Winch Machine
Pape 10 012METHOD STATEMENT @
10.0
Responsibilities
10.1
10.2
103
10.4
GEPM/GESM will ensure that the necessary resources to implement the
approved Method Statement have been allocated to the task,
The GESM will ensure that the site preparation activities are conducted
According to the approved Method Statement.
The GEPM will ensure that the materials being used are in accordance to
the Project Specifications, the approved Material Submittals.
Itis the GESM and GESO responsibility to organize the work in « safe
Manner to ensure that safety and protective equipment are being
properly utilized.
itis responsibilty of GE & SC staff to ensure that necessary action are
initioted every time any deviation is observed and stop works in any
Paget ot 12METHOD STATEMENT
stage, if any deviation is observed wrt Method statement, RA & Lifting
Plan.
11.0 Declaration by Site Execution Team (GE + Subcontractor)
This is to certify that we have read the method statement completely and
commit to comply it in full for safe and timely execution of respective activity
Ais prepared ond shall be reviewed and communicated to the members of
Working party as and when required prior to starting any related works
Name of the authorized | Designation/Organization | Signature Date and
person time